WORK-PLAN, WIFE PROJECT PHASE 1 (REPAIRING GARDEN FENCE, TRAINING AND SENSITISATION ON VIOLENCE AGAINST WOMEN ) DRAFT

Purpose: Directions: To properly implement the project activities and within the specified time period. 1. Using this work plan as a guide to easily carry out each activity and identify in advance the needs for each activities 2. Distribute copies of each work plan to each member of Project Implementing Team, ( PIT), village representative and 1 % club NL 3. Keep copies handy to bring to meetings to review and update regularly

Timeline Activities Objective Responsible Persons


GU Members, PIT, villagers

Anticipated Output

Means of Verificati on
Pictures, videos and participant list

Year: 2011 To 2012


Nov Dec Jan Feb Mar Apri May Jun Jul Aug

1st meeting with village elders, women and youth groups

To share project plans activities, work with community and to identify reps of the village in the project To know actual size of the garden that will help us in our planning To know the actual number of women to benefit

Plan shared barriers identified & noted, Village reps in the project chose

xxx

Measurement of the Garden

Villagers, GU members, PIT, and technician Village reps, PIT and GU members

Actual size of the garden verified and documented.

Pictures, and drawings List, pictures and videos

xxx

Head Count of number of married women in the village

Actual number of beneficiaries ascertain, documented and

xxx

GLOBAL UNIFICATION THE GAMBIA, 151 MOSQUE ROAD, PMB 496, SEREKUNDA PHONE: +2209807770, +2209856691, +2207009171 E MAIL: IN FO @ G LO B A LU N IFIC AT I O NT H EG A MB IA . O R G W E B : W W W .W W W .C LO BA LUN IFIC A T IO N TH E GA MB IA . OR G

WORK-PLAN, WIFE PROJECT PHASE 1 (REPAIRING GARDEN FENCE, TRAINING AND SENSITISATION ON VIOLENCE AGAINST WOMEN ) Timeline Activities Objective Responsible Persons Anticipated Output Means of Verificati on Year: 2011 To 2012
Nov Dec Jan Feb Mar Apri May Jun Jul Aug

from this project and help us in planning for the training Clearing & cleaning the garden and cutting all grasses To clean up the garden and prepare for work To get all the poles required for the fencing To erect the poles To buy the material and keep them ready for transportation to the village To transport the material from the All village youths, Village reps All village youth, reps and women All village youth, village reps, PIT PIT, GU accountant,

adopted in our planning

Grasses and bushes cleared

Pictures

xxx

Gathering poles

Poles made available before work commence. Poles erected Material bought and keep ready

Pictures

xxx

Digging & Erection of Poles Provision barb wires, nails, cement & any required material

Pictures Reciepts voucher, pictures

xxx

xxx xxx

xxx

Transport material to village

PIT, GU members, and

Material transported to village and kept in village

Recipts, voucher,

xxx

GLOBAL UNIFICATION THE GAMBIA, 151 MOSQUE ROAD, PMB 496, SEREKUNDA PHONE: +2209807770, +2209856691, +2207009171 E MAIL: IN FO @ G LO B A LU N IFIC AT I O NT H EG A MB IA . O R G W E B : W W W .W W W .C LO BA LUN IFIC A T IO N TH E GA MB IA . OR G

WORK-PLAN, WIFE PROJECT PHASE 1 (REPAIRING GARDEN FENCE, TRAINING AND SENSITISATION ON VIOLENCE AGAINST WOMEN ) Timeline Activities Objective Responsible Persons
hired driver Village youths, reps and hired technician. Village reps, tractor owner, PIT Village reps, village elders, and women themselves PIT, GU members and vilage reps GU members, PIT

Anticipated Output

Means of Verificati on
pictures and video

Year: 2011 To 2012


Nov Dec Jan Feb Mar Apri May Jun Jul Aug

city to the village Covering Garden with barbed wire To fence the garden

community store Garden covered with barbed wire

xxx

xxx

xxx

Hiring tractor to digg out the entire Garden Sharing the space of Garden among Beneficiaries

To level the topography of the garden To allocate every beneficiary ( women) a space in the Garden To properly secured the garden. To reach an agreement with trainers, discuss training methods

Garden dug-out comletely Every woman given a plot to do her work Pictures and video

xxx

xxx

Contruction Metal Garden Gate

Gate contructed, erected and keys handed over to village reps Agreement reach, contract signed, training methods discussed and agreed

Reciepts, vouchers, picture Contract agreement , pictures.

xxx

Meetings and signing contract with trainers

xxx

GLOBAL UNIFICATION THE GAMBIA, 151 MOSQUE ROAD, PMB 496, SEREKUNDA PHONE: +2209807770, +2209856691, +2207009171 E MAIL: IN FO @ G LO B A LU N IFIC AT I O NT H EG A MB IA . O R G W E B : W W W .W W W .C LO BA LUN IFIC A T IO N TH E GA MB IA . OR G

WORK-PLAN, WIFE PROJECT PHASE 1 (REPAIRING GARDEN FENCE, TRAINING AND SENSITISATION ON VIOLENCE AGAINST WOMEN ) Timeline Activities Objective Responsible Persons
Trainers

Anticipated Output

Means of Verificati on
Training module

Year: 2011 To 2012


Nov Dec Jan Feb Mar Apri May Jun Jul Aug

Design entrepreneurship training modules Provision of training material

To prepare & designed training modules To buy training material and share them with the trainees To improve the womens skill entrepreneurship & management of small businesses To ascertain perfomance and success of the training To prepare & design training modules To improve womens on

Training modules prepared and shared and adopted Needed material acquired and ready

xxx

xxx

PIT, GU accountant

xxx

xx

Conduct entrepreneurial skill and small scale business management training

Trainers, PIT & GU members

Training conducted

xx

xx

Assess outcome of training, document and share lessons learned and best practices Designing Modules skill training On Garden Management Conduct training

Trainers, PIT, GU members, village reps Trainers & PIT

Reports on lessons learnt from training shared Training modules designed Training conducted

xx
xxx
xxx

Trainers, PIT, GU members,

xxx

xxx

GLOBAL UNIFICATION THE GAMBIA, 151 MOSQUE ROAD, PMB 496, SEREKUNDA PHONE: +2209807770, +2209856691, +2207009171 E MAIL: IN FO @ G LO B A LU N IFIC AT I O NT H EG A MB IA . O R G W E B : W W W .W W W .C LO BA LUN IFIC A T IO N TH E GA MB IA . OR G

WORK-PLAN, WIFE PROJECT PHASE 1 (REPAIRING GARDEN FENCE, TRAINING AND SENSITISATION ON VIOLENCE AGAINST WOMEN ) Timeline Activities Objective Responsible Persons
village reps

Anticipated Output

Means of Verificati on

Year: 2011 To 2012


Nov Dec Jan Feb Mar Apri May Jun Jul Aug

garden management & techniques such as compost making, bed levelling, manure application Assess outcome of training To ascertain perfomance and success of the training To prepare leaflets with pictures for sensitisation To raised awareness about womens rights and harmful traditional pratices To update donors,

Trainers, PIT, GU members and villlage reps

Reports on lessons learnt from training shared IEC materials printed

xxx

Printing of leaflets and other IEC materials

xxx

Conduct sensitization programme

PIT, GU members, village reps

Community Sensitized

xxx

Develop and share Monitoring field

PIT

Monitoring checklist

Reports,

xxx

xxx

XXX

XXX

XXX

GLOBAL UNIFICATION THE GAMBIA, 151 MOSQUE ROAD, PMB 496, SEREKUNDA PHONE: +2209807770, +2209856691, +2207009171 E MAIL: IN FO @ G LO B A LU N IFIC AT I O NT H EG A MB IA . O R G W E B : W W W .W W W .C LO BA LUN IFIC A T IO N TH E GA MB IA . OR G

WORK-PLAN, WIFE PROJECT PHASE 1 (REPAIRING GARDEN FENCE, TRAINING AND SENSITISATION ON VIOLENCE AGAINST WOMEN ) Timeline Activities Objective Responsible Persons Anticipated Output Means of Verificati on
check list and pictures
xxx xxx xxx

Year: 2011 To 2012


Nov Dec Jan Feb Mar Apri May Jun Jul Aug

visits checklist /reporting format with 1% Club, donors & partners Quarterly monitoring treks

1 % club, beneficiaries of progress of work To monitor and supervise work, note short coming PIT

developed and shared

Quarterly M&E field visits conducted End of project evaluation report prepared to submitted to 1%club, Donors and partners

Conduct end of project evaluation

PIT & External Evaluator

xxx

GLOBAL UNIFICATION THE GAMBIA, 151 MOSQUE ROAD, PMB 496, SEREKUNDA PHONE: +2209807770, +2209856691, +2207009171 E MAIL: IN FO @ G LO B A LU N IFIC AT I O NT H EG A MB IA . O R G W E B : W W W .W W W .C LO BA LUN IFIC A T IO N TH E GA MB IA . OR G

WORK-PLAN, WIFE PROJECT PHASE 1 (REPAIRING GARDEN FENCE, TRAINING AND SENSITISATION ON VIOLENCE AGAINST WOMEN )