Professional Documents
Culture Documents
WELCOME
1
MILL BACKGROUND
2
ORGANIZATION CHART
MILL MANAGER
ZUL HILMEE B.SIRAN
(1ST Grade Steam Engineer)
CHIEF CLERK
ROSLINA BT.
ABDOL RAZI
2ND CLERK
FITTERS FITTERS
(MECHANICAL) (ELECTRICAL) MANDUR
5
BOILER TYPES
6
7
8
9
MAIN FUNCTION
◦ To convert the chemical energy in the palm
shell and fibre to heat energy in boiler
furnace.
10
ESSENTIAL FITTINGS
11
1. SAFETY VALVE
Its function is to protect
the boiler shell from over
pressure and subsequent
explosion.
15
PRESSURE GAUGE
Should be 150mm
dia.
Should be marked to
indicate the normal
working pressure
and the maximum
permissible working
pressure
16
BLOWDOWN VALVE
Ejects the sludge or
sediment from the
bottom of the boiler
To control TDS value
1800 - 2000ppm
17
MAIN STOP VALVE
To isolates / permits the
steam and its pressure
from / to the process or
plant.
It should always be
opened slowly to
prevent any sudden rise
in downstream pressure
and associated
waterhammer, and to
help restrict the fall in
boiler pressure and any
possible associated
priming.
18
FEED CHECK VALVE
Under normal steaming
conditions the check
valve operates in a
conventional manner to
stop return flow from
the boiler entering the
feedline when the
feedpump is not
running.
When the feedpump is
running, its pressure
overcomes the spring to
feed the boiler as
normal.
19
REGISTRATION NO. &
MANUFACTURER NAMEPLATE
20
BOILER OPERATION
21
Make-up Water
Primary Secondary
Pretreatment Pretreatment
Process
Steam Header
Deaerator
Boiler Chemical
Turbine Feed
Systems
Feedwater
Blowdown
WATER TREATMENT PLANT
POLIMER
COAGULANT
24
WATER SOFTENER
Ca, Mg
Na, Na
25
Resin
26
Ion exchange
process
Calcium
Sodium Magnesium Calcium
Sodium Sodium
Calcium Magnesium
Sodium Sodium
Sodium Calcium
Sodium
Sodium
27
DEAERATOR
2 type of deaerator :
# thermal deaerator
# vacuum deaerator
28
THERMAL DEAERATOR
Operation
temperature min
950C
29
O2 Solubility in Water
Oxygen - ppm
28
10 P.S.I.
24 5 P.S.I.
0
10" VAC
20
16
12
0
40 60 80 100 120 140 160 180 200 220 240
Temperature, ° F
30
Relationship of Temp & O2
Content at Normal Temp
31
VACUUM DEAERATOR
Temp 75 – 800C
Pressure -15inHg /
-400mmHg
32
INTERNAL TREATMENT –
chemicals based
To prevent scale formation on heating surface
& thereby prevent overheating & distortion.
Alkalinity adjustment
33
DESIRABLE RESERVES IN
BOILER WATER
TDS 1800 - 2000ppm
Hardness 0 ppm
pH 10- 11.5
Cycle 10- 15
Chloride <600 ppm
34
PRELIMINARY CHECK
– Before Firing
Check all valves – in close position.
Check all fans casing, bearings, v-belts,
holding bolts, etc.
Check water level in gauge glass (level ≈ ½).
Clean glass and guards.
Visually inspect inside the furnace – the bed
is clean – fire bars & brickworks in order.
Check blowdown valves are shut.
Check feed water tank & fill as required
35
START-UP
Open blow down valve (2-3 short burst) until the level to
about ½.
The fire must spread to all the fuel in the furnace and
normally it takes about 5 to 10 minutes
Start secondary air fan & and the damper is adjusted to give
a balance draught inside the furnace. More fuel must then be
continuously fed into the furnace.
36
START-UP (continue…)
Once the boiler is at the operating pressure, check the
safety valves – ensure they are working properly no
sticking or jamming of valves. This can easily be
achieved by tapping the fulcrum arm of the valves. Also
check & test the gauge glasses.
40
STOPPING
The boiler can only be stopped after the steam turbine has been
stopped.
About quarter to half an hour before the boiler is stopped, the fuel-
feeding rate must be reduced.
Shut the main steam stop valve tightly. Stop all the fans.
Pump in water to the drum till the gauge glass is at least three
quarter full, then shut the feed check valve.
Rake out all the fire on the fire grate. Only keep some burning ash
on the fire grate. The purpose is to protect the refractory from
having too high a cooling rate. The furnace doors must be shut.
Close the damper tightly. Keep the lights for the gauge glasses on.
41
LOW WATER DRILL
Low water is when the water level in the
gauge glass is less than quarter and is fast
disappearing (THE LIGHT PANEL GOES TO
RED, INDICATING 2ND LOW AND AUDIBLE
WARNING IS SOUNDED).
42
LOW WATER DRILL (cont…)
Immediate action should be taken as follows:
è START UP AUXILLIARY FEED PUMP, RUNNING THE PUMP AT
MAXIMUM OUTPUT UNTIL NORMAL WORKING LEVEL IS
RESTORED.
43
EMERGENCY SHUTDOWN
Stop the firing and draw out all the fire from
the furnace.
Stop the feed pump & isolate the check valve at once.
Draw out all the fire from furnace. Shut the main stop
valve
Stop all the fans and open the damper fully and allow
the furnace to cool with natural draught.
Investigate the causes for no water in gauge glass.
NEVER PUMP IN ANY WATER INTO THE DRUM
DURING THIS TIME
45
HIGH WATER ALARM
Not a dangerous situation
But it can cause priming, which can lead to
serious damage of turbines and steam
engines.
Following steps should be taken:
è Slow down or stop the feed water pump.
è Blow down the boiler until the normal water level is indicated in
the gauge glass.
46
BURST TUBE DRILL
In the event of tube failure due to local overheating or
mechanical defects, the following actions must be taken
immediately:-
Stop firing and draw out all the fire from the furnace.
Continue to run the feed pump at maximum output. If
the water level still cannot be maintained, start the
standby pump
Isolate the boiler by shutting the main stop valve
Stop all the fans, and the damper must be opened fully
to create maximum natural draught in the furnace to
cool it down.
47
BOILER MAINTENANCE
48
PREVENTIVE MAINTENANCE -
WEEKLY
Clean the boiler furnace & ash pit
49
PREVENTIVE MAINTENANCE -
WEEKLY (cont…)
Check the Mobrey Water Alarm System, gauge
glass and blow-down valve for any leakage. Rectify
if necessary.
50
PREVENTIVE MAINTENANCE –
every 15 month
Preparation for DOSH inspection.
51
PREVENTIVE MAINTENANCE –
every 15 month (cont…)
Clean the boiler tube internally & externally.
52
PREVENTIVE MAINTENANCE –
every 15 month (cont…)
Check furnace bricks and wall for any bulging.
Rectify if necessary.
53
PREVENTIVE MAINTENANCE –
every 15 month (cont…)
Once inspection done by DOSH’s inspector has
completed, reinstall back all fittings and holes.
Hydrostatic test - HT
(1.5 x designed pressure)
shall be conducted before
the boiler is putting back
into operation.
54
PROBLEM IN BOILER
55
Scale
Corrosion
Deposit
Carry over
56
SCALE
Due to high hardness in feed
water.
As a results:
57
CORROSION
Due to presence of O2 & CO2
èO2 corrosion.
Reaction:
◦ Fe -----> Fe2+ + 2e Anode
◦ 2e + 1/2O2 + H2O ---> 2(OH-) Cathode
èCO2 corrosion
Reaction:
CO2 + H2O <---> H2CO3
H2CO3 <---> H+ + HCO3- Pitting – O2 corrosion
58
DEPOSIT
Due to:
59
CARRY OVER
Cause/type of carry over:
Priming
Foaming
Misting
Selective carry over
60
CARRY OVER
è Priming
A large amount of water enters the steam line due to:
# sudden demand of steam
# too high of boiler water level
è Foaming
Presence of stable small air bubbles on surface of
boiler water due to:
# contamination of dissolved and undissolved
substances in water which cause the stability of
a thin layer of water around the vapor bubbles.
61
CARRY OVER
è Misting
The occurrence of wet layer on the boiler water due to:
# bursting of air bubbles on the surface of the water that
splashed water particles into the steam line.
62
CARRY OVER EFFECT
Priming
Foaming WATER HAMMER
Misting
63
PROBLEM IN BOILER - OTHERS
Furnace collapse
64
PROCEDURE FOR TUBES
REPLACEMENT
◦ Submit drawing indicating all the location/position of the tubes to
be replaced and obtain approval from JKKP prior to
commencement of work.
65
PROCEDURE FOR TUBES
REPLACEMENT – CONT…
◦ Install all the new tubes and expand by a special tool. All
expansion of tubes end into the drum shall comply to BS1113.
66
BOILERMAN &
STEAM ENGINEER
???
67
TERIMA KASIH
68