To,

The C.E.O. & S.E.(O & M)


DGVCL, Circle Office,
Surat Rural / Surat City / Valsad / Bharuch

Sub: Agenda for the SE/EE’s Conference arranged on Dtd.07.12.2023 at DGVCL,


Corporate Office.

With reference to the above, this is to inform you that SE/EE’s Conference under the
Chairmanship of Hon’ble Managing Director is scheduled on Dtd.07.12.2023 at 11.00 Hrs
at DGVCL, Corporate office, 6th Floor, Conference Room. You are requested to make it
convenient to attend the meeting along with all Executive Engineers of Division Office
and Circle offices.

The agendas for meeting are as under.

1. Robust Network related S.I.T.C. Works—Tender status


 Approval status of Projects-feeder wise, & Planning up to march-2024 with
Amount for revised Budget for F.Y.2023-24.
 Feeder wise work executed and Planning of Departmental work.
 Status of existing Work Order and planning thereof.
 Removal of double circuit HT line by overhead XLPE Cable-Status of projects
and work planning
 Removal of patch work on feeders by providing cable to remove hybrid
network
2. LT SoP
 Sub-division wise S.R. Creation pending & process 1 , 2 & 3
 Prepayment to release – period analysis
 %age On line survey in Geo Urja.
 A Cat > 15 days, B, C, & D > 30 days pendency
 A Cat <15 days released B, C, & D > 30 days released
3. OMS data
 Action taken report of poor power supply reliability feeder (Worst feeder)
 Late data entry
 Post monsoon maintenance progress
4. Review of Distribution losses of Sept-2023 & action taken for loss
reduction.
 Review of high loss feeders-more than 50% loss.
 Comparison of last 2 years-Category wise.
 Statistical data of selected Feeders.
5. Installation checking activity target and achievement for FY-2023-24.
 Performance against 60 % achievement of target.
 LTMD Checking
6. Wrapped Meter Inspection
 Inspection done during last two quarters and month wise for 2nd quarter
 Details of pending wrapped meter Quarter wise
 Separate planning to clear wrapped meter.

Page 1 of 2
7. Transformer Failure & Repairing.
 Analysis against baseline failure data-Sub-division/Division wise.
 Installation of Lightening Arrestor on selected feeder.

[
8. Crossing removal- Planning & inclusion in RDSS
9. Progress of all ongoing Government Schemes.
Achievement against target and planning up to Jan/Feb-2024
10. Solar Rooftop.
11. GWSSB/WASMO/Nal se Jal progress review.
12. Line shifting work of R&B, NHAI, DFCCIL, Gujarat Metro, High Speed Railway,
Private land.
13. Debit arrears and Pending MR
14. HT-LT online payment
15. Pending Govt. ref.

You are requested to prepare the agenda wise data as per the standard format and
submit to this Office on or before 13.00 Hrs of Dated 06.12.2023 without fail.

This is for your kind information and further needful please.

(M.G. Surati)
Chief Engineer (O&M)
DGVCL, Corp. Office, Surat
Copy to :
1. Addl. Chief Engineer (Proc.), DGVCL, Corporate Office
2. General Manager (F&A), DGVCL, Corporate Office
3. Chief Engineer (SD&P), DGVCL, Corporate Office
4. Additional Chief Engineer (C&R), DGVCL, Corporate Office
5. Additional Chief Engineer (GL), DGVCL, Corporate Office
6. Superintending Engineer (IT), DGVCL, Corporate Office
7. Superintending Engineer (Vigilance), DGVCL, Corporate Office
8. EA to MD, DGVCL, Corporate Office

Page 2 of 2

You might also like