Professional Documents
Culture Documents
SPECIFICATION – CIVIL
Section 08 – Trenchless Pipeline
Installation
Revision: 03
The content of this document material is a property of Haya Water. No part of this document in whole or in part,
may be reproduced in any form, by photocopy, microfilm, scanning or any other means, or incorporated into any
information retrieval system, electronic or mechanical, without the written permission of Haya water Management.
Document No: AM-ENG-SS-02-08 Issue Date: 29/09/2016
HAYA Water
M/s Halcrow on Behalf of Haya Water Asset Management / Projects / O&M
i Document Authorisation
This document is authorized for issue.
Suleiman Al Qasmi
ii Revision History
The following is a brief summary of the most recent revisions to this document. Details of all revisions prior
to these are held on file by the issuing department.
Revisio
Date Scope / Remarks
n No.
0 13/04/2006 Document approved and issued
01 01/06/2008 To incorporate Tender Board and Veolia comments
02 31/12/2010 To incorporate latest changes as per current International standards.
03 29/09/2016 Updated as part of the Haya Water Technical Standards Upgrading project
Classification: Revision: 03
TABLE OF CONTENTS
i Document Authorisation .................................................................................................. 3
ii Revision History................................................................................................................ 3
1. Introduction ................................................................................................................... 6
1.1. Purpose ...................................................................................................................... 6
1.2. Scope .......................................................................................................................... 6
1.3. Distribution/Target Audience .................................................................................... 7
1.4. Definitions .................................................................................................................. 7
1.5. Abbreviations ............................................................................................................. 7
1.6. Standard reference .................................................................................................... 9
2. General ..........................................................................................................................12
2.1. Temporary Works ......................................................................................................12
3. Safety and Environment ..............................................................................................13
3.1. Regulations ...............................................................................................................13
3.2. Safety Procedure on the Site ...................................................................................13
3.3. Traffic and Public Relationship Management Plan .................................................13
3.4. Safety Work Practice ................................................................................................13
4. Quality Management ....................................................................................................15
4.1. Warranty ....................................................................................................................15
4.2. Personnel ..................................................................................................................15
5. Submittals .....................................................................................................................16
5.1. Material ......................................................................................................................16
5.2. Equipment .................................................................................................................16
5.3. Structural Design Calculations ................................................................................16
5.4. Operation Procedures ..............................................................................................16
6. Materials Specifications ...............................................................................................18
6.1. General ......................................................................................................................18
6.2. Grouting/Lubrication and Conditioning Agents......................................................19
6.3. Concrete Encased GRP Jacking Pipe .....................................................................19
6.4. Centrifugal Casting GRP Pipe ..................................................................................20
6.5. Precast Concrete Pipe ..............................................................................................20
6.6. Polyester resin concrete (PRC) Polymer Concrete Pipe (Polycrete Pipe) ............20
7. Delivery, Handling, and Damaged Pipes .....................................................................21
7.1. Delivery......................................................................................................................21
Classification: Revision: 03
Classification: Revision: 03
1. Introduction
1.1. Purpose
The purpose of this document is to communicate the technical requirements and preferences
related to the trenchless installation of Haya Water sewage and treated effluent pipes.
The Specification indicates the guidelines and minimum requirements for trenchless pipeline
installations and it is the responsibility of the contractor to verify the site data and submit appropriate
design and methodology accordingly.
1.2. Scope
i. This Specification covers the following trenchless pipe installation methods:
a) Pipe jacking (PJ) method
b) Horizontal directional drilling (HDD) method
ii. This Specification shall be read in conjunction with Haya Water Civil, Mechanical, and
Instrumentation Control and Automation (ICA) Technical Standards, Haya Water Wastewater
Design Manual, and Haya Water Standard Detail Drawings.
iii. This Specification shall be read in conjunction with “Specification for tunnelling-latest edition”
(British Tunnelling Society & Institution of Civil Engineers). The Contractor shall comply with the
BTS Specification and this Specification for the Works. Clauses of this Specification take
precedence over clauses in the BTS Specification unless noted otherwise.
iv. When HDD operation is considered, this Specification shall be read in conjunction with the Unified
Facilities Guide Specifications (UFGS) latest edition, Division 33 “Utilities” Section 33 05 23.13
“Utility Horizontal Directional Drilling”, published by the American Whole Building Design Guide
(WBDG).
v. In general, the Contractor shall perform trenchless operation so as not to interfere with, interrupt,
or endanger surface and activity thereon, and minimise subsidence of surface, structures, and
utilities above and near pipeline.
vi. The Contractor shall be responsible for the selection of the appropriate excavation method.
vii. The Contractor shall furnish labour, equipment, material, and all requirements necessary to
complete pipe installation Works with the selected excavation method. The finished Works include
proper installation testing, restoration of underground utilities, and environmental protection and
restoration.
viii. Product pipes that are indicated in the Contract documents to be constructed “Open trench” are
not covered by this Specification.
ix. Any lengths of pipe indicated in the Project Documents to be constructed “in trench” shall be
constructed by trenchless methods at no additional cost, subject to the approval in writing of the
Engineer. The Contractor shall not be permitted to construct in trench any pipelines indicated to be
constructed by one of the aforementioned trenchless methods.
x. Strict adherence to all requirements of this Specification shall be maintained at all times and in all
circumstances which comply with the previously described scope.
Classification: Revision: 03
1.4. Definitions
i. Where definitions are not provided within this Specification they shall generally be those contained
in BS 6100.
ii. Definitions for tunnelling terms are contained in BS 6100: Part 3: Building and Civil Engineering
Vocabulary – Civil Engineering – General, Section 6.0 – Tunnels, Shafts and Caissons.
iii. All references to the Contractor in the following clauses of this Specification shall be deemed to
include the subcontractor.
iv. Client/Owner: Oman Wastewater Services Company (Haya Water) for whom the Works are to be
undertaken
v. Owner Representative/Engineer: The firm or company named in the Contract as appointed by
the Client to supervise and administer the Contract
vi. Consultant: The firm or company selected by the Client to prepare the Particular Specification (the
Contract Documents) for a given project
vii. Contractor: The company or organisation responsible for the construction of the Works and who
have entered into a Contract with the Client
viii. Site: The land allocated for the Work
ix. Project Documents: All documents associated with and applicable to the Contract
x. Particular Specification: The Specification associated with the Contract and prepared at the time
of the project by the Engineer specifically for that application
xi. Technical definitions related to this Specification are to be found within the appropriate technical
clauses in the document.
1.5. Abbreviations
ANSI American National Standards Institute
Classification: Revision: 03
ID Inside Diameter
IP Ingress Protection
MDF Medium-Density Fibreboard
PE Polyethylene
PJ Pipe Jacking
PVC Polyvinyl Chloride
Classification: Revision: 03
Units of Measurement
μm Micrometre
m Metre
mm Millimetre
MPa Megapascal
BS EN 681-1 Elastomeric seals. Material requirements for pipe joint seals used in
water and drainage applications. Vulcanised rubber.
BS EN 682 Elastomeric seals. Materials requirements for seals used in pipes and
fittings carrying gas and hydrocarbon fluids.
BS EN 14364 Plastics piping systems for drainage and sewerage with or without
pressure. Glass-reinforced thermosetting plastics (GRP) based on
unsaturated polyester resin (UP). Specification for pipes, fittings, and
joints.
Classification: Revision: 03
ASTM A 276 Standard specification for stainless steel bars and shapes
ASTM C 117 Standard test method for materials finer than 75 μm (No. 200) sieve
in mineral aggregates by washing
ASTM C 136 Standard test method for sieve analysis of fine and coarse
aggregates
ASTM C579 Standard test method for compressive strength of chemical resistant
mortars, grouts, monolithic surfacing, and polymer concretes
ASTM C 828 Standard test method for low pressure air test of vitrified clay pipe
lines
ASTM C 969 Standard practice for infiltration and exfiltration acceptance testing of
installed pre-cast concrete pipe sewer lines
ASTM C 1208 Standard specification for vitrified clay pipe and joints for use in
micro-tunnelling, slip-lining, pipe bursting, and tunnels
ASTM C 1244 Standard test method for concrete sewer manholes by the negative
air pressure (vacuum) test prior to backfill
ASTM D 638 Standard test method for tensile properties of plastics
ASTM D 3681 Test method for chemical resistance of fibreglass pipe in deflected
position
ASTM F 477 Specification for elastomeric seals (gaskets) for joining plastic pipe
ASTM F 1962 Standard guide for use of maxi horizontal directional drilling for
placement of polyethylene pipe or conduit under obstacles, including
river crossings
Classification: Revision: 03
AWWA C 207-7 Steel pipe flanges for waterworks service sizes 4 inch through 144
inch (100 through 3,600 mm)
AWWA C 600 Standard for installation of ductile-iron mains and their
appurtenances
AWWA C 605 Standard for underground installation of polyvinyl chloride (PVC) and
molecularly oriented polyvinyl chloride (PVCO) pressure pipe and
fittings
DIN 54815-1 and 2 Pipes Made of Filled Polyester Resin Moulding Materials
Classification: Revision: 03
2. General
The contractor is responsible to carry out related risk management and safety measures in
accordance to BTS Code of risk management BTS Specification, Section 107.2., and Haya Water
Safety Standards.
Classification: Revision: 03
3.1. Regulations
i. Contractor shall follow Haya Water HSE manual & procedures.
ii. The Contractor shall carry out all Works to the requirements outlined in all current appropriate
regulations and codes of practice as stated in the BTS Specification, Section 107.2.
iii. The following recognised documents shall form the basis for guidance and development of the
safety plan and site procedures:
a) BS 6164: Code of practice for safety in tunnelling in the construction industry
b) Pipe Jacking Association’s Guide to best practice for the installation of pipe jacks and micro
tunnels
Classification: Revision: 03
3.4.5. Plant
Appropriate training and certification shall be given to all operators of plant. This shall be carried
out only by staff competent in the use and hazards associated with the particular item of the plant
concerned.
Classification: Revision: 03
4. Quality Management
In general, the quality management system, Engineer’s agreement, site records, and as-built
records shall be in accordance with the BTS Specification, Section 108.
Any changes must be expressly approved by the Engineer. Approval of any aspect of any operation
covered by this Specification shall in no way relieve the Contractor of its ultimate responsibility for
the satisfactory completion of the Works authorised under the Contract.
The manufacturer’s premises and methods shall be open to inspection by the Engineer for the
purpose of checking the quality of manufacture. The Contractor shall ensure that all necessary
assistance is provided to the Engineer on each visit.
4.1. Warranty
i. The Contractor shall hand over the completed pipe system, including any protective coatings and
linings, free from defects in materials and workmanship, and guaranteed for the design life of the
structure.
ii. The Contractor shall furnish the Engineer with the manufacturer’s guarantee and warranty
certificates for all materials and components used.
iii. If the protective coating and lining system are found to be defective during the warranty period, the
manufacturer and Contractor shall replace or repair the protective coating and lining system to the
satisfaction of the Engineer at no cost to the Client and restart the guarantee.
4.2. Personnel
i. Key personnel, including the Site manager, foreman, shift bosses, surveyor, and engineering staff,
shall have had appropriate previous experience in similar Works. Details shall be submitted for
approval prior to appointed personnel taking up positions onsite. Machine operators shall have a
proven track record of a minimum of 5 years of experience in driving similar equipment in similar
ground conditions.
ii. For PJ and HDD operations, key operatives in each shift crew shall have appropriate prior
experience including documented evidence in their ability to supervise and train the crew in all
aspects of the pipe installation operation.
iii. A sufficient number of competent workers shall be on the Site at all times to ensure that the Works
are made in a timely and satisfactory manner. Adequate personnel for carrying out all phases of
the actual operation must be on the job site at the beginning of the Works.
Classification: Revision: 03
5. Submittals
The Contractor shall submit the followings for the approval of the Engineer:
5.1. Material
i. Third-party certified quality assurance and control program to BS EN ISO 9001.
ii. Pipe manufacturer’s reference sheets, Specification, and quality assurance certifications.
iii. Pipe manufacturer’s certification of pipe meeting or exceeding the required Specification.
iv. Before delivery of pipes, a certificate issued by the pipe manufacturer shall be provided to the
Engineer to confirm that the pipes comply in all respects with the relevant standards.
v. Before delivery of pipes, a Factory Acceptance Certificate (FAC) shall be submitted.
vi. Detailed information on all proposed drilling fluids, concrete mixes, additives, lubricants, and
conditioning agents. Submittals shall include material safety datasheets on each material, along
with a description of where the material will be used and its purpose in the construction process.
All drilling fluids and lubricants shall be bio-degradable,
5.2. Equipment
i. Full details of selected trenchless method equipment.
ii. Plan at (1:50) scale showing working plant positions, spoil removal facilities, materials storage
facilities, shafts, drilling areas, fencing, offices, discharge lines, groundwater removal facilities and,
in general, all details related to the Site installation.
Classification: Revision: 03
Classification: Revision: 03
6. Materials Specifications
Materials shall be approved by the Engineer prior to execution.
6.1. General
Unless superseded by clauses herein, the jacking pipes shall comply with the requirements of
following Standard / Specifications:
a- Civil Section 04: Sewage and T.E Networks (AM-ENG-SS-02-04).
b- Mechanical Section 06: Pipes and Accessories (AM-ENG-SS-03-06).
c- BTS Specification Section 207
6.1.1. Design
a) The Contractor shall demonstrate that the jacking pipes are designed to resist all loads and
damage from the construction process and stages, including crushing of material due to load
transfer at the joint.
b) In addition of the previously described construction loads, jacking pipe wall thickness shall be
determined by the Contractor considering the following:
Final in-place loading: dead, live, and seismic loads; temperature gradient and
hydrostatic pressure (if used as a permanent lining)
Pipe stiffness requirements
Durability and reliability requirements
c) The proof-design shall be carried out using a design procedure in accordance with BS EN 1916
and complementary standard BS EN 5911-Part in case of RCC pipe and Pipe Jacking
Association’s “Guide to best practice for the installation of pipe jacks and microtunnels”. The
Deutscher Verein des Gas und Wasserfaches (DVGW) Technical Rules GW 312: “Static
Computation of Jacking Pipes”, or other published codes of practice and standards shall be
considered as complimentary reference.
In case of polymer concrete pipe or GRP pipe shall be referred to applicable standards
accordingly. Refer to Mechanical Section 06: Pipes and Accessories (AM-ENG-SS-03-06).
d) The Contractor shall submit all required design calculation for Engineer approval.
e) Jacking pipes shall be designed for 50 years of service life.
f) External pressure test pressure shall be 4 bar.
Classification: Revision: 03
c) Joint Tightness Test –As per applicable pipe standard and external pressure test for joint shall
be 4 bar.
Qualification test shall be repeated in case of change of design/ material as applicable.
Classification: Revision: 03
f) The packer, comprising several segments to form the 360 percent annulus, shall be firmly glued
to the socket end and in such manner as to be 15 mm inset from the intrados of the pipe. These
packers shall be fitted on either at the factory or onsite; however, it should be noted that in wet
weather conditions, suitable protection is required in cases of lengthy exposures.
6.6. Polyester resin concrete (PRC) Polymer Concrete Pipe (Polycrete Pipe)
a) Polymer concrete pipe shall be manufactured in accordance with ASTM D6783 and shall satisfy
requirements contained in Technical Standard Specification – Mechanical Section 6 – Piping
and Accessories (AM-ENG-SS-03-06).
b) Thickness of pipe shall be designed as per site required jacking pipe design.
Classification: Revision: 03
7.1. Delivery
Inspect materials delivered to the Site for damage. Unload and store materials as per
manufacturer’s Instruction manual. Store materials onsite in enclosures or under protective
covering appropriately. Store plastic material under cover out of direct sunlight. Do not store
materials directly on the ground. Keep the inside of pipes, fittings, and valves (if any) free of dirt,
dust and debris.
7.2. Handling
Pipes shall only be lifted onsite as per manufacturer’s Instruction manual. The lifting device shall
be fully tested and carry relevant certification. Pipes shall be stored in an orderly fashion in a
designated area, not more than three pipes high or as per manufacturer’s instruction manual and
on purpose-made timber supports. Store individual pieces and bundles with safe walking space
between to allow full view for inspection purposes.
Classification: Revision: 03
8. Execution
Trenchless pipeline shall be installed as per approved drawings and as per approved Quality Plan.
8.1. General:
8.1.1. Profiles and Topography
Contours, topography, and profiles of the ground as shown on the Contract Drawings are believed
to be reasonably correct, but are not guaranteed to be absolutely so, and are presented only as an
approximation. It is the Contractor's responsibility to verify all elevations required to successfully
complete the Works.
8.1.2. Alignment Set-Out
i. The Contractor shall submit a method statement for setting out and controlling the alignment of the
tunnels and shafts for agreement by the Engineer prior to commencement of Works. Adequate
opportunity for checking of the survey and setting out shall be given to the Engineer.
ii. Details of all setting out readings and calculations shall be maintained at the Site and be set out in
a clear and orderly fashion to allow for ease of checking. The Contractor shall provide all necessary
lines and levels together with all necessary equipment to enable the Works to be constructed to
the required tolerances. The setting out lines and levels shall be carefully preserved and, where
necessary, replaced, throughout the period for which they are required.
iii. The primary setting out system shall be used for the main control of the excavation, tunnel lining,
and shafts, including checking and recording of the “as-built” position of the lining at intervals.
8.1.3. Ground Levels
The Contractor shall record ground levels prior to commencement of pipe installation Works.
Reliable benchmarks and reference stations shall be established. The locations of these shall be
agreed upon with the Engineer. Four reference stations shall be set around each shaft. Levels shall
be taken along the centre of the pipeline and the offsets of 5 and 10 m at each side of the pipeline
at 15 m intervals between shafts at locations as shown on the Drawings or approved by the
Engineer.
8.1.4. Survey and Setting Out
Shall comply with the BTS Specification Section 330.
8.1.5. Existing Vegetation and Structures
The Contractor shall be responsible for the preservation of all existing trees, plants, and other
vegetation that are to remain within or adjacent to the construction site and shall also be responsible
for protecting existing concrete curb, fence, utilities, and other structures that are located within or
adjacent to the construction site.
Classification: Revision: 03
ii. The Contractor shall use or propose a tunnel excavation machine with a different excavation mode.
In such case, the Contractor shall demonstrate to the Engineer that the alternative mode can suit
the project’s ground conditions and groundwater pressure, optimise face support during
excavation, and minimise possible ground settlement. The proposed method shall comply with BTS
Specification Chapter 3 – Methods.
iii. The tunnel excavation machine shall be equipped with a cutting wheel suitable for the expected
ground conditions.
8.2.1.2. Guidance System
The Contractor is solely responsible to select equipment and to guarantee the final Works are within
the accuracy and tolerances per BTS Specification Section 328.
8.2.1.3. Inter-jacks
i. Design of Inter-jacks: Inter-jack stations shall be designed to provide sufficient jacking force to
overcome the frictional resistance to pipe motion over the distance between them. Interjack stations
shall have sufficient capacity to overcome the envisaged forces during the tunnelling operation.
The seal shall be adjustable to avoid groundwater and bentonite leakages into the pipe jack. It shall
be capable of withstanding working pressures in excess of 4 bar or as required by the pipe jack
system. The envisaged number of intermediate jacking stations shall be agreed with the Engineer
in advance of the commencement of PJ operation.
ii. Operation of Interjacks: Hydraulic power to operate the interjack stations shall be designed in order
to minimise hose lengths and subsequent power losses.
iii. On completion of tunnelling operations, all interjack cylinders and seal assemblies shall be
removed. The exposed steelwork shall be cleaned and treated with epoxy paint, and the pipes shall
be closed to eliminate the gap. The adjustable interjack sealing systems shall be manufactured to
facilitate easy removal by hand within the tunnel.
8.2.2. Fluids Systems
8.2.2.1. Slurry System Design
i. The slurry system shall be designed to be capable of functioning with bentonite slurry where
required as a support medium. The slurry circuit shall be designed for a minimum flow rate that is
capable of transporting all the excavated material during the tunnelling machine advancing. The
slurry circuit shall include flowmeters on both feed and discharge lines.
ii. Automatic valves shall be included at the shaft top to allow for immediate closure by the operator
in the event of burst system hoses.
iii. The separation plant shall be sized to be 25 percent over capacity to account for any possible flow
surges within the slurry circuit.
8.2.2.2. Slurry System Operation
All controls and indicators for running the slurry system shall be available at the tunnelling machine
operator's console. A telephone system shall be installed to allow direct communication between
the tunnelling machine and the separation plant.
8.2.2.3. Bentonite Lubrication System – Design
i. The equipment shall be automatic or manual bentonite injection system to enable both the
lubrication of the pipe wall and the support of loose ground to be maintained. The system shall be
such that the annulus around the pipe is kept full of lubricant at all times including periods of
downtime.
Classification: Revision: 03
ii. Injection of bentonite shall be at a minimum of three points spaced equally around the pipe wall
and at centres not exceeding 15 m along the pipe line.
iii. Lubrication holes shall be as specified in previous Clauses 3.1.1.1 - iii.
iv. All formed holes in a GRP inner pipe shall be repaired on completion of the installation of the pipe
by skilled craftsmen in accordance with the GRP pipe manufacturer’s recommendations.
Documentation shall be provided of the successful use of the proposed system on other pipe
jacking projects.
v. The frequency and duration of injection at any given point shall be programmable and controlled
from the tunnelling machine operator's console. The point of operation and system pressure shall
be displayed to the operator.
vi. Any lubrication bentonite in the annulus shall be replaced by contact grout after completion of the
Works. Upon completion of grouting, the plugs shall be covered with a material similar to that of
the jacking pipes.
vii. The contact grout shall be cementitious and shall contain bentonite with a 7-day unconfined
compressive strength of at least 1.5 MPa and shrinkage less than 5 percent. Sand shall be added
to the mix for voids larger than 50 mm. The mix design shall be submitted to the Engineer for
approval.
8.2.2.4. Bentonite Lubrication System – Operation
The system shall be used continuously whilst pipe advance is taking place.
8.2.3. Pipe Jacking – Execution
8.2.3.1. General
The PJ operation shall comply with the requirements of BTS Specification Section 319 and the
additional, substitute, and amended clauses herein.
8.2.4. Surface Operations
8.2.4.1. Site Compound
Where practical, the whole of the working area for each working shaft shall be enclosed by a 2 m
high secure fence or hoarding. Watchmen shall be employed during times when Works are not in
progress. Adequate lighting and warning notices shall be provided around the Site. Suitable
drainage and desilting tanks shall be provided to cater both with surface and underground water.
The shaft top shall be secured with a robust barrier around its perimeter to a minimum height of 1.2
m. Jacking pipes shall be stored clear of water, and excavated material and shall not be used for
storing plants and equipment.
8.2.4.2. Electrical Equipment
All electrical equipment shall be appropriately Ingress Protection (IP) rated for its intended
underground use. It shall be installed and maintained by a suitably qualified electrician.
8.2.4.3. Lighting
Tunnels requiring man-access, even on an occasional basis, shall be adequately lit by a lighting
system complying with the relevant clauses of BS 6164, Section 17. Unshaded lights shall not be
used below ground.
8.2.4.4. Ventilation
Ventilation during construction for all accessible tunnels shall comply with the relevant
recommendations of BS 6164, Section 15. The Contractor shall supply and maintain a fresh air
supply to all places underground where Works are being carried out.
Classification: Revision: 03
Classification: Revision: 03
particular, include all requirements for the safe launching of the tunnelling machine assembly and
for safe working of the operating crew. The shaft invert shall be cast at such level and in such
manner as to facilitate the installation and operational needs of the jacking frame and ancillary
equipment to be installed in the shaft bottom. A sump pit shall be incorporated in the shaft bottom
for the installation of submersible pumping equipment. The size of the sump shall be adequate for
the depth of the shaft and ingress volume of water, in addition to any requirements for pumping
during jacking operations, and shall include the facility of a standby pump.
8.2.6. Work in Compressed Air
8.2.6.1. General Requirements
i. Provisions shall be made on the tunnelling machine to facilitate entry into the face of the machine
under compressed air for inspections and maintenance if specified for the project. These provisions
shall comply in all respects with all relevant statutory regulations governing provision of Works in
compressed air. The airlocks and other equipment fitted to the machine shall comply with the
relevant section of BTS Specification, Section 401.
ii. All equipment and personnel necessary to perform such interventions for inspection or
maintenance shall be available throughout the PJ operations. The Contractor shall submit details
of the compressed air installation for the Engineer’s approval, along with details of the qualifications
and previous experience of lock attendants, medical lock attendants, compressor attendants, and
supervisory staff. The installed capacity of the compressed air supply plant to be provided shall be
agreed upon with the Engineer after inspection of the available site investigation information. In
highly permeable ground where air losses might be excessive, arrangements shall be made to
inject thick bentonite slurry into the face prior to an intervention to form a cake on the exposed face
in order to limit air loss.
Classification: Revision: 03
iii. For use at pressures above 1 bar, the lock should be fitted with seating for the persons being
decompressed.
iv. Where the working pressure is above 0.7 bar, a medical lock shall be provided which shall be
manned by a medical lock attendant whenever Works in compressed air are in progress and for
24 hours afterwards.
8.2.6.4. Air Quality
i. If necessary, the quality of the compressed air supplied to the working chamber shall be improved
by coolers and filters to ensure compliance with the specified requirements. The supply of
compressed air to the working chamber shall be sufficient to ensure that the level of any
contaminant shall not exceed 10 percent of the short-term exposure level when measured at
atmospheric pressure.
ii. Air quality should be monitored at least once per day.
8.2.6.5. Medical Supervision
i. The Contractor shall appoint a registered medical practitioner experienced in compressed air
Works to advise on decompression methods to be adopted and on all other aspects of health
relating to the Works in compressed air.
ii. All employees shall be medically examined prior to working in compressed air.
iii. Records shall kept of all medical examinations and details of each compressed air exposure
including working pressure, working time, decompression procedures, and other related
information. No person shall be allowed to work in compressed air if the Contractor has reason to
suspect that person is under the influence of drink or drugs such that his capacity is impaired.
8.2.6.6. Operational Requirements
i. No one shall be allowed to enter the compressed air working chamber alone.
ii. An experienced lock attendant shall be on duty at the free air side of the air lock at all times when
there are persons in the compressed air working chamber.
iii. All valves gauges and controls at the lock attendant’s station shall be clearly marked with their
function and method of operation.
iv. Smoking shall be banned in compressed air, and no person shall take smoking materials into
compressed air.
v. As far as is practicable, no combustible material shall be taken into the air locks and or the working
chamber.
vi. The use of burning or welding equipment should be strictly limited and shall be subject to a permit
to work system.
vii. Fire extinguishers shall be provided in the air locks and the working chamber whenever Works in
compressed air are in progress.
8.2.7. Tunnel Services
The installation of all tunnel services shall be progressively carried out as the Works proceed.
Services shall be supported on purpose-made brackets bolted to the pipe wall. Electric cables shall
be hung on the opposite side of the pipes to any water lines. Slurry lines shall be mounted on blocks
in the invert to facilitate access in case of blockage or leakage. On pipe jacks larger than 2 m
internal diameter and longer than 100 m, a 450 mm gauge track, or similar such device, shall be
provided to facilitate movement of men and equipment in the tunnel. Care shall be taken not to
Classification: Revision: 03
damage the pipes during the installation and handling of services in the tunnel. All fixings shall
subsequently be removed, and the holes plugged with a suitable mortar.
8.2.8. Settlement, Surface Heave Monitoring, and Existing Structures
i. Works zone of influence is defined as the distance in plan from the centreline of the Works equal
to the depth to invert of that part of the Works below ground level. This distance shall be agreed
upon with the Engineer prior to commencing the Works.
ii. The Contractor shall carry out a survey on all buildings and structures located within the zone of
influence.
iii. The Contractor shall take all care and necessary precautions to protect existing structures, utilities,
and services in planning and execution of the Works. Any damage to adjacent properties that are
not part of these Works shall be repaired and, the properties shall be restored to their original
condition at the Contractor’s expense.
iv. The Contractor shall be responsible for the identification and protection of services where these
are crossed by construction activities.
v. The Client shall be notified immediately of all services encountered during the progress of the
Works. The services shall be marked on the “As-Built” drawings by the Contractor.
vi. Where crossing of roadways and railways are involved, the Contractor shall be required to record
and report any ground settlement to the satisfaction of the controlling agencies.
vii. The Contractor shall monitor ground settlement or heave of existing buildings and structures
located within the Works zone of influence.
Classification: Revision: 03
Classification: Revision: 03
and push 3 m (10-foot) minimum hollow drill sections into the hole being created by the boring
head. The drill sections shall be made of high strength S-grade steel. Drill end fittings shall
permit rapid make-up of the drill sections, whilst meeting the torque, pressure, and lineal load
requirements of the system. The boring head itself shall be capable of housing a probe used
by the Magnetic Guidance System (MGS) to determine tool depth and location from surface
and to orient the head for steering. The MGS shall have a minimum accuracy of plus or minus
2 percent of the vertical depth. The drilling equipment must be fitted with a permanent alarm
system capable of detecting an electric current. The system shall have an audible alarm to
warn the operator when the drill head nears electrified cables. The drilling equipment shall be
grounded, protected, and operated in accordance with manufacturer’s requirements for electric
strike safety. The control console shall contain a calibrated display of inclination, azimuth, tool
face location, mud pump rates, and torque pressures. The down hole steering system accuracy
shall be plus or minus 1 percent of the horizontal bore length such that the difference between
actual depth and machine calculated depth is not more than 1 foot per 100 feet.
c) Restrictions: Other devices or utility placement systems for providing horizontal thrust other
than those previously defined in the preceding sections shall not be used unless approved by
the Engineer prior to commencement of the Works. The proposed device or system shall be
evaluated prior to approval or rejection on its potential ability to complete the pipe placement
satisfactorily without undue stoppage and to maintain line and grade within the tolerances
prescribed by the particular condition of the project. Water sluicing methods, jetting with
compressed air, or boring or tunnelling devices with vibrating type heads that do not provide
positive control of the line and grade shall not be allowed.
8.3.3.3. Spoils Equipment
The cutting fluid removal system shall include a self-contained vacuum truck which has sufficient
vacuum and tank capacity to remove excess cutting fluid mixture and cuttings from the project site
as required or as directed by Haya Water. Spoils are not to be discharged into sewers or storm
drains. The Contractor shall contain all drilling and pipe lubricating mud by taking special measures
to prevent run-off onto adjacent properties or waterways, or both. All surplus drilling and pipe
lubricating mud shall be removed from the Site and properly disposed of by the Contractor at no
cost to the Client. The Contractor shall also be responsible for all required erosion control measures
at no cost to the Client.
8.3.3.4. Magnetic Guidance System (MGS)
i. An MGS shall consist of a probe and a tracker that is capable of monitoring the location of the drill
head during the drilling operation. The tracker shall be capable of tracking at all depths up to 100
feet and in any soil condition, including hard rock. It shall enable the driller to guide the drill head
by providing immediate information on the tool face, azimuth (horizontal direction), and inclination
(vertical direction). The tracker shall be accurate to plus or minus 2 percent of the vertical depth of
the borehole at sensing position at depths up to 100 feet. Ferrous materials shall not influence or
affect the MGS readings or accuracy.
ii. Components: The Contractor shall supply all components and materials to install, operate, and
maintain the MGS. This shall include, but is not limited to the following:
a) MGS probe and interface
b) Computer, printer, and software
c) Direct current (DC) power source, current control box, and coil/tracking wire
iii. The MGS shall be a Tensor TruTracker MGS, or other licensed and industry approved wire
guidance system. The Contractor is required to obtain approval from the Engineer for the
equipment to be used. The Contractor is responsible for supplying all required information
regarding the equipment and method to be used on the project. Works shall not commence until
Classification: Revision: 03
approval is obtained from the Engineer. The Contractor is responsible for setting up and operating
the MGS using personnel experienced with this system. “A Walkover” tracking systems shall not
be used, except as approved by the Engineer. The Contractor shall provide the Engineer with
current calibration certification of MGS in accordance with the manufacturer’s Specification.
8.3.3.5. Boring Tool
The boring tool (jetting head or mud motor) shall have steering capability and an electronic tool
detection system. The position of the tool during operation shall be capable of being determined
accurately, horizontally within 1 percent of the horizontal distance of the borehole and vertically
within 2 percent of the vertical depths of the borehole. The boring tool shall have a nominal steering
radius of 9 m (30 feet).
8.3.4. Drilling fluids
8.3.4.1. Slurry Selection
The Contractor assumes all liability for environmental damage and clean-up due to inadvertent
discharges of slurry or other causes. Slurry materials shall be selected based on the soil conditions
encountered to minimise the risk of mud returns.
8.3.4.2. Drilling Fluids Viscosity
A mixture of Bentonite drilling clay, project-specific cutting fluid additives, and potable water is to
be used as the cutting fluid (Mud) and over ream hole filler for the directional bore. The drilling fluid
mixture used shall have an optimum viscosity to best fit the soil conditions encountered, as
recommended by the drilling mud and fluid additive manufacturer, and as approved by the
Engineer.
8.3.4.3. Drilling Fluids in Granular Ground
Where sandy or granular materials are encountered, a cement slurry or polymer supplement shall
be considered for added strength and stability of the bore and over ream hole.
8.3.4.4. Additions to Drilling Fluids
No chemicals or polymer surfactant shall be used in the drilling fluid without the written consent of
the Engineer, and after a determination is made that the chemicals to be added are not harmful or
corrosive to the facility and are environmentally safe. Clay must be totally inert and contain no risk
to the environment.
8.3.4.5. Material Safety Data Sheets
Provide the Engineer and have onsite at all times the Material Safety Data Sheets (MSDS) for all
drilling compounds and chemicals.
Classification: Revision: 03
Water to provide inspection personnel at such times, as appropriate, without causing undue
hardship by reason of delay to the Contractor.
ii. If the Contractor fails to begin the directional bore at the agreed upon time, the Engineer shall
establish the next mutually convenient time to begin. To avoid undue hardship to either party,
reasonable and mutual co-operation should be exercised where starting times are concerned. If
one party fails to meet the agreed upon schedule, the other party is expected to consider a delayed
start if the installation cannot be completed during normal working hours.
8.4.2. Work Stoppage
If equipment should break down or other unforeseen stoppages occur, and forward motion of the
directional cutting head is halted at any time other than for reasons planned in advance (for
example, addition of drill stems), the boring path shall be filled with a proper material immediately,
or as directed by the Engineer, in order to avoid deterioration or collapse of the hole.
8.4.3. Receiving Exit and Access Pits
The Contractor shall take all necessary action to ensure the safety of the Works and shall ensure
compliance with the pre-approved Safety Management Plan requirements at all times. The sizes
of all excavations shall conform to the following:
a) Pits shall be of the minimum possible size commensurate with safe working practices and
located at the maintenance holes. The Contractor shall select the size and provide the details
of all pits.
b) Every face of any excavation that exceeds a depth of 1.2 m shall be supported or contained by
shoring unless the face is cut back to a safe slope.
c) The shoring of the excavation shall be braced as the excavation progresses, and where a
mechanical digger is used, the shoring shall be kept as close as practicable to the excavator.
d) All necessary measures must be taken to ensure that excavations are left in a safe condition,
including the erection of suitable hard barricades, warning signs, and hazard lights.
e) The earthworks shall be set out in accordance with the TSS Civil Section 02 Earthworks
Excavation requirements and the Drawings.
f) The Contractor shall inspect the Site, and verify all existing levels, survey control points, and
set-out points shown on the Drawings, before commencing the earthworks.
g) All excavations shall be made to the depth and extent as shown on the Drawings with proper
allowance for fill, additional cover (where required), and formwork. The excavations shall be
kept free and clear of loose materials, water, and rubbish. Should excavation to the nominated
depth reveal unstable or unsuitable ground, the Contractor shall immediately notify the Client.
8.4.4. Closing of Pits
After satisfactory completing all testing and all equipment and excavated materials for the HDD
operations have been removed, the Contractor shall prepare the bottom of all pits to the same
Specification as required for the pipe foundation. The Contractor shall remove all loose and
disturbed materials below pipe grade to the undisturbed earth level and shall re-compact the
materials to as close to the original condition as possible.
Classification: Revision: 03
9. As-Built Drawings
The Contractor shall submit a complete set of as-built drawings properly dated and marked or noted
with up-to-date as-built conditions. As-built drawings shall be maintained at the construction site for
recording as-built conditions and updated regularly. The Contractor shall submit the updated as-
built drawings to the Engineer each week. Nos of copies shall be as per Haya Water Document
control procedure.