You are on page 1of 1

PT.

ACTER TECHNOLOGY INDONESIA


Engineering Report
Project : PT. HON CHUAN INDONESIA
Location : NGORO - JAWA TIMUR Date: November 17, 2023
Construction Schedule Track List
Estimate Actual Total Completed Today
Contractor Construction Item Estimated Work Time Remark
Manpower Manpower Amount Amount Amount
INJECTION AREA
PT.ACTER
TECHNOLOGY Install Terpaulin for Cover Area 3 1st Day
INDONESIA
PT.ACTER
Remove Existing AC Package CMP 06 (
TECHNOLOGY
including ducting & pipe )
3 1st Day after install terpaulin
INDONESIA
PT.ACTER
TECHNOLOGY Fabrication Support 2 1st Day
INDONESIA
PT.ACTER
TECHNOLOGY Install New AC Package CMP 06 3 2nd Day
INDONESIA
PT.ACTER
Remove Existing Pipe 2,5 inch ( after
TECHNOLOGY
gate valve ) & Fabrication Ducting
2 2nd Day
INDONESIA
PT.ACTER
Modification & Install Pipe ( 2.5 inch & 2
TECHNOLOGY
inch ) - including fitting & accessories
2 3rd Day
INDONESIA
PT.ACTER
Modification & Install Ducting (L=500 mm
TECHNOLOGY
, W=500 mm) - including insulation
2 3rd Day
INDONESIA
PT.ACTER
TECHNOLOGY Painting pipes & Test Commisionig 1 3rd Day
INDONESIA

Material on site track List

Contractor Equipment & Material Unit Amount Estimate on site Date Actual on site Date Situation
PT.ACTER
TECHNOLOGY Pipe galvanize 2 inch Stick 1 22-Nov-23 On Process
INDONESIA
PT.ACTER
TECHNOLOGY Fitting ( Elbow , Flange , etc ) Lot 1 22-Nov-23 On Process
INDONESIA
PT.ACTER
TECHNOLOGY Angle 40 x 40 mm Stick 1 22-Nov-23 On Process
INDONESIA
PT.ACTER
TECHNOLOGY Zinc BJLS Lot 1 22-Nov-23 On Process
INDONESIA
PT.ACTER Accessories ( Bolt , Nuts ,Screw, etc
TECHNOLOGY Lot 1 22-Nov-23 On Process
INDONESIA )
PT.HON CHUAN INDONESIA PT.ACTER TECHNOLOGY INDONESIA