5.5.17.4. Support two right rear catwalk sections and remove retaining pins.

5.5.17.5. Lower catwalks and pallet guides.

5.5.18. Deck extension.

5.5.18.1. The forward end of the loader may be configured to allow loader interface with
the lower lobes (bellies) of wide-body aircraft.

5.5.19. Type V platform.

5.5.19.1. Place pallet width switch in the OFF position.

5.5.19.2. Rotate all convey module latch handles inline with deck.

5.5.19.3. This allows convey modules to raise high enough to make contact with platform.
The platform is higher due to the skid plates underneath.

5.5.20. Shipment preparation.

5.5.20.1. Remove ladder and support arm. Stow on rear of deck. Do not place the ladder
on the convey module.

5.5.20.2. Rotate all roller trays adjacent to the cab. Leave the tray directly right of the cab
out.

5.5.20.3. Unscrew hinged weldment locking bolt. Located beneath the roller tray next to
the cab. Unscrew the bolt completely. Replace the roller tray.

5.5.20.4. Lift the hinged weldment, fold it over onto the deck.

5.5.20.5. Remove cab retaining pin. Carefully push the cab inward and reinstall the
retaining pin. Note: Do NOT force the cab inboard. Investigate any resistance.

5.5.20.6. Remove walk deck/handrail retaining pins.

5.5.20.7. Rotate sections on to the top of the deck. Watch the clearance behind the cab.
The catwalk section behind the cab must be removed for transport on C-130.

5.5.20.8. Replace all of the pins for storage.

5.5.20.9. Air Shipment.

5.5.20.9.1. Rotate airportability latch counterclockwise.