MATERIAL
NO. DESCRIPTION LABOR COST TOTAL
COST
9
10 CEILING, ELECTRICAL, PLUMBING (ROUGH-INS)
11 SCAFFOLDINGS/STAGING 140980.0 49,343.00 190,323.00
SUB-TOTAL 140,980.00 11,142,600.00 11,142,600.00
SUMMARY OF ESTIMATES:
NO. DESCRIPTION TOTAL COST
1 MATERIAL COST PHP 140,980.00
2 LABOR COST PHP 11,142,600.00
3 ENGINEERING SUPERVISION
4 CONTRACTOR'S PROFIT
5 GRAND TOTAL PHP 11,283,580.00