RISK ASSESSMENT Risk Assessment No: 03

Name of the Aspect: Using Disc Cutters and Abrasive Wheels Revision No 01
Project Name: Issue date
Assessed By: Risk/Impact Assessment committee Page No Page 218
of 5
Activity Hazard Risk Legal N/ AL L S R1 Control measures L S R2 Action by Remarks
reference A/
E/

Using Disc Entanglement Cuts, eye Ministerial N yes 4 4 16 ➢ Impart Training on use of abrasive wheel 1 5 5 Plant
Order 32
Cutters and of body part injuries, operation. Manager
Article
abrasive during abrasions 1,9,11,12,1 ➢ Cutting disk and machine properly tested
wheels operation. injury to 3 and inspected regularly maintained
➢ Hold the object firmly before start cutting Supervisor
Ejection of finger and
➢ Protective guard shall be fixed in machine (Foreman,
particles and other body rotation parts area charge hand)
even cutting parts. ➢ Display authorized persons list at the
disk flyoff workplace/stores to avoid unauthorized
operation as far as possible.
➢ Avoid loose clothing during operation.
➢ Maintain the safe distance from the
rotating part.
➢ Tool rests must be secured and maintain
at least 3mm gap between tool rest and
the wheel.
➢ Proper housekeeping must be maintained
near the working area.
➢ Ensure adequate & proper illumination.
➢ Display of warning sign boards and
notices.
➢ PPE (Hard hat, safety shoe, goggles, hand
gloves, nose mask) must be worn.
Using Disc Wheel Major Ministerial N yes 4 5 20 ➢ Selection of wheel: 1 5 5
Order 32
Cutters and breakage/flyin Injury/Eye Article
• Ensure wheel RPM is always more Plant
abrasive g particles injury, cut 1,9,11,12,1 than the spindle RPM. Manager
wheels from Abrasive injury, 3 • Select the right wheel for the right
wheel. fracture, job.
➢ Visually inspect the spindle and wheel
218
RISK ASSESSMENT Risk Assessment No: 03
Name of the Aspect: Using Disc Cutters and Abrasive Wheels Revision No 01
Project Name: Issue date
Assessed By: Risk/Impact Assessment committee Page No Page 219
of 5
Activity Hazard Risk Legal N/ AL L S R1 Control measures L S R2 Action by Remarks
reference A/
E/

Material prior to use. Supervisor


damage ➢ The guard must be securely attached to (Foreman,
the body of machine. charge
➢ Abrasive wheel should only be mounted hand)
by a competent person.
➢ When starting a new wheel, operator shall
stand at the side until it reaches speed.
Correct any abnormalities noted.

➢ Remove nails, bolts if any observed in the


wooden job before cutting.
➢ Change the wheel when it reaches the
wear limit.
➢ Side surface of the wheel must not be
used for the grinding purpose.
➢ Don’t exert excess pressure on the
machine.
➢ Stability of machine shall be ensured for
any vibration during operation.
➢ Follow abrasive wheel speed limitations
according to manufacturer’s instructions.
Using Disc Fire/spark Fatal/ major Fire N yes 4 5 20 ➢ Remove any storage of the flammable 1 5 5 Plant
Protection,
Cutters and Injury to materials away from vicinity of operation Manager
prevention,
abrasive person emergency of disc cutters.
wheels Property control ➢ Hot work Permit system must be followed
regulation while working nearby the flammable area. Supervisor
damage and fire
➢ Provide the barrier to arrest the flying of (Foreman,
prevention
program. spark. charge hand)
219
RISK ASSESSMENT Risk Assessment No: 03
Name of the Aspect: Using Disc Cutters and Abrasive Wheels Revision No 01
Project Name: Issue date
Assessed By: Risk/Impact Assessment committee Page No Page 220
of 5
Activity Hazard Risk Legal N/ AL L S R1 Control measures L S R2 Action by Remarks
reference A/
E/

CH 5 DM ➢ Provide & maintain adequate required


fire extinguishers.
Using Disc Dust Lung related Local law N yes 5 5 25 ➢ Local Exhaust ventilation must be 2 2 4
16 section 6
Cutters and health arranged in the confined space. Plant
article 14
abrasive problems, ➢ Purchase Grinding/Cutting machine with Manager
wheels Property dust collection system.
➢ Ensure the proper Ventilation at the
damage.
workplace. Supervisor
➢ Prefer wet cutting wherever possible. (Foreman,
➢ Use of necessary nose mask and eye charge hand)
protection during process of activity.
➢ Cover the vulnerable areas/places by
providing protective covers.

Using Disc Noise Stress/raised Control of N yes 5 5 25 ➢ Do preventive maintenance of power 1 5 5


noise
Cutters and heart rate, tools. Plant
4.12.1.3 Dm
abrasive irritability, ➢ Ensure job rotation in the adequate Manager
wheels Hearing loss. interval.
➢ Use hearing protection device such as ear
Plugs/Muffs persons exposed. Supervisor
(Foreman,
charge hand)

Using Disc Electricity Electrical Refer to power tools Risk Assessment


safety CH
Cutters and 16 DM
abrasive
wheels

220
RISK ASSESSMENT Risk Assessment No: 03
Name of the Aspect: Using Disc Cutters and Abrasive Wheels Revision No 01
Project Name: Issue date
Assessed By: Risk/Impact Assessment committee Page No Page 221
of 5
Activity Hazard Risk Legal N/ AL L S R1 Control measures L S R2 Action by Remarks
reference A/
E/

Signature: ___________ Signature: ___________

Name: Name:

Designation: HSE Manager/Officer Designation:

Probability (Likelihood) Severity Risk Matrix Risk Rating


Methodology:
Risk Likelihood Low 1-5
Very unlikely 1 Negligible 1
Rating 1. Identify Hazards
1 2 3 4 5 2. List Hazard Effects (Risk event)
Unlikely 2 First-aid injury 2 1 1 2 3 4 5 3. Calculate initial risk factor
Severity

2 2 4 6 8 10 6-14 i.e. probability x severity


Medium 4. Decide Control measures
3 3 6 9 12 15
Likely 3 Minor injury 3 5. Calculate residual risk factor
4 4 8 12 16 20 6. Evaluate acceptability of risk

221
RISK ASSESSMENT Risk Assessment No: 03
Name of the Aspect: Using Disc Cutters and Abrasive Wheels Revision No 01
Project Name: Issue date
Assessed By: Risk/Impact Assessment committee Page No Page 222
of 5
Activity Hazard Risk Legal N/ AL L S R1 Control measures L S R2 Action by Remarks
reference A/
E/

Very likely 4 Major 4 5 5 10 15 20 25 and act accordingly.


High 15-25

Certain or Imminent 5 Fatality 5

Legend:
N: Normal A: Abnormal E: Emergency
AL: Applicability of legal requirements
L: Likelihood R1: Initial Risk Rate
S: Severity R2: Residual Risk Rate