LOADING SCHEDULE PT. BENS - ZST ( NAR ARB 5.500 - 5.

300 Kcal/Kg )
MV. TBA Stowage Plan 55,000 MT
Date
No Activities Jetty Remark 8,9,10 Nov 11-Nov-23 12-Nov-23 13-Nov-23 14-Nov-23 15-Nov-23 16-Nov-23 17-Nov-23 18-Nov-23 19-Nov-23 20-Nov-23 21-Nov-23 22-Nov-23 23-Nov-23 24-Nov-23 25-Nov-23 26-Nov-23 27-Nov-23 28-Nov-23 29-Nov-23
Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed
Stockpile
Cargo Ready Check Cargo and PSA in STOCKFILE
Payment Cargo DP 30% - 60% Loading in Barge - 10% Barge Sailling + Full Doc
BARGE
1 BARGE 1 Hasnur 7.500 MT Houling to jetty 7.500 MT TB / BG
2 BARGE 2 Talenta Bumi 7.500 MT Houling to jetty 7.500 MT TB / BG
3 BARGE 3 Hasnur 10.000 MT Houling to Jetty 10.000 MT TB / BG
4 BARGE 4 Talenta Bumi 7.500 MT Houling to Jetty 7.500 MT TB / BG
5 BARGE 5 Hasnur 7.500 MT Houling to Jetty 7.500 MT TB / BG
6 BARGE 6 Talenta Bumi 7.500 MT Houling to Jetty 7.500 MT TB / BG
7 BARGE 7 Hasnur 7.500 MT Houling to Jetty 7.500 MT TB / BG

MOTHER VESSEL MV Arrive to Taboneo


NOR Anchorage est. ETA
Stavedoring Draft Survey MV
MV. TBA
1 BARGE 1 Loading To MV 7.500 MT Sailing to MV 7.500 MT TB / BG
2 BARGE 2 Loading To MV 7.500 MT Sailing to MV 7.500 MT TB / BG
3 BARGE 3 Loading To MV 10.000 MT Sailing to MV 10.000 MT TB / BG
4 BARGE 4 Loading To MV 7.500 MT Sailing to MV 7.500 MT TB / BG
5 BARGE 5 Loading To MV 7.500 MT Sailing to MV 7.500 MT TB / BG
6 BARGE 6 Loading To MV 7.500 MT Sailing to MV 7.500 MT TB / BG
7 BARGE 7 Loading To MV 7.500 MT Sailing to MV 7.500 MT TB / BG
Mother Vessel sailing from Taboneo Anchorage Document MV est. ETD

Remark
1 Jetty Holyday Loading Port : STS Taboneo, Banjarmasin, South Kalimantan
2 Houling from stockpile to Jetty Discharging Port : Any Port(s), Mainland in China
3 Barge sailing from jetty to MV Surveyor Independent : Tribhakti Inspektama
4 Loading rate barge to Mother Vessel ± 8.000 - 9.000 MT/Day Main Surveyor : CCIC Indonesia
5 ETA Mother Vessel Jetty : Hasnur Group and Talenta Bumi
6 ETD Mother Vessel Laycan MV : November 20, 2023
7 Loading Barge at Jetty Latest Shipment MV : November 27, 2023
8 Barge berthing to Mother Vessel
9 Document MV