You are on page 1of 7

GENERAL NOTES

Reinforcement & Numeration detail Drawing of Staff Quarters ( Block No.-1) ,(Block No.-2) & CWT at Dummi

JOB NO:-181220DUM LOCATION :- DUMMI

NR Approval 27-04-23 Noor Consultant Noor Consultant Er. Munish


02
Sharma

Approval 17-03-23 Noor Consultant Noor Consultant Er. Munish


01 NR
Sharma

NR Approval 16-02-23 Noor Consultant Noor Consultant Er. Munish


00
Sharma

REV TYPE DESCRIPTION DATE DESIGNED DRAWN CHECKED


NO.
REVISIONS
Design, Build, Operate (DBO) contract for water supply for
PROJECT:-
shimla from river Satlej.

CLIENT:- Shimla Jal Prabandhan Nigam Limited (SJPNL)

IVA CONSULTANT:- TATA CONSULTING ENGINEERS LIMITED

OPERATOR:- LCC SAI KSIPL JV

NAME SIGN DATE SCALE:- N.T.S SHEET 1 OF 7


DSGN Noor Consultant 27-04-23
TITLE-:
DRWN Noor Consultant 27-04-23
Reinforcement & Numeration detail Drawing
CHKD Er. Munish Sharma 27-04-23 of Staff Quarters ( Block No.-1) ,(Block No.-2)
& CWT at Dummi

SIZE REV
DRAWING NO.-SJPNL-DUM-CV-DWG-SQ-CWT-NR-2020
A1 02

RELEASED FOR:- PRELIMINARY GFC INFORMATION

APPROVAL ABD
GENERAL NOTES
Reinforcement & Numeration detail Drawing of Staff Quarters ( Block No.-1) ,(Block No.-2) & CWT at Dummi

JOB NO:-181220DUM LOCATION :- DUMMI

NR Approval 27-04-23 Noor Consultant Noor Consultant Er. Munish


02
Sharma

Approval 17-03-23 Noor Consultant Noor Consultant Er. Munish


01 NR
Sharma

NR Approval 16-02-23 Noor Consultant Noor Consultant Er. Munish


00
Sharma

REV TYPE DESCRIPTION DATE DESIGNED DRAWN CHECKED


NO.
REVISIONS
Design, Build, Operate (DBO) contract for water supply for
PROJECT:-
shimla from river Satlej.

CLIENT:- Shimla Jal Prabandhan Nigam Limited (SJPNL)

IVA CONSULTANT:- TATA CONSULTING ENGINEERS LIMITED

OPERATOR:- LCC SAI KSIPL JV

NAME SIGN DATE SCALE:- N.T.S SHEET 2 OF 7


DSGN Noor Consultant 27-04-23
TITLE-:
DRWN Noor Consultant 27-04-23
Reinforcement & Numeration detail Drawing
CHKD Er. Munish Sharma 27-04-23 of Staff Quarters ( Block No.-1) ,(Block No.-2)
& CWT at Dummi

SIZE REV
DRAWING NO.-SJPNL-DUM-CV-DWG-SQ-CWT-NR-2020
A1 02

RELEASED FOR:- PRELIMINARY GFC INFORMATION

APPROVAL ABD
GENERAL NOTES
Reinforcement & Numeration detail Drawing of Staff Quarters ( Block No.-1) ,(Block No.-2) & CWT at Dummi

JOB NO:-181220DUM LOCATION :- DUMMI

NR Approval 27-04-23 Noor Consultant Noor Consultant Er. Munish


02
Sharma

Approval 17-03-23 Noor Consultant Noor Consultant Er. Munish


01 NR
Sharma

NR Approval 16-02-23 Noor Consultant Noor Consultant Er. Munish


00
Sharma

REV TYPE DESCRIPTION DATE DESIGNED DRAWN CHECKED


NO.
REVISIONS
Design, Build, Operate (DBO) contract for water supply for
PROJECT:-
shimla from river Satlej.

CLIENT:- Shimla Jal Prabandhan Nigam Limited (SJPNL)

IVA CONSULTANT:- TATA CONSULTING ENGINEERS LIMITED

OPERATOR:- LCC SAI KSIPL JV

NAME SIGN DATE SCALE:- N.T.S SHEET 3 OF 7


DSGN Noor Consultant 27-04-23
TITLE-:
DRWN Noor Consultant 27-04-23
Reinforcement & Numeration detail Drawing
CHKD Er. Munish Sharma 27-04-23 of Staff Quarters ( Block No.-1) ,(Block No.-2)
& CWT at Dummi

SIZE REV
DRAWING NO.-SJPNL-DUM-CV-DWG-SQ-CWT-NR-2020
A1 02

RELEASED FOR:- PRELIMINARY GFC INFORMATION

APPROVAL ABD
Reinforcement & Numeration detail Drawing of Staff Quarters ( Block No.-1) ,(Block No.-2) & CWT at Dummi GENERAL NOTES

JOB NO:-181220DUM LOCATION :- DUMMI

NR Approval 27-04-23 Noor Consultant Noor Consultant Er. Munish


02
Sharma

Approval 17-03-23 Noor Consultant Noor Consultant Er. Munish


01 NR
Sharma

NR Approval 16-02-23 Noor Consultant Noor Consultant Er. Munish


00
Sharma

REV TYPE DESCRIPTION DATE DESIGNED DRAWN CHECKED


NO.
REVISIONS
Design, Build, Operate (DBO) contract for water supply for
PROJECT:-
shimla from river Satlej.

CLIENT:- Shimla Jal Prabandhan Nigam Limited (SJPNL)

IVA CONSULTANT:- TATA CONSULTING ENGINEERS LIMITED

OPERATOR:- LCC SAI KSIPL JV

NAME SIGN DATE SCALE:- N.T.S SHEET 4 OF 7


DSGN Noor Consultant 27-04-23
TITLE-:
DRWN Noor Consultant 27-04-23
Reinforcement & Numeration detail Drawing
CHKD Er. Munish Sharma 27-04-23 of Staff Quarters ( Block No.-1) ,(Block No.-2)
& CWT at Dummi

SIZE REV
DRAWING NO.-SJPNL-DUM-CV-DWG-SQ-CWT-NR-2020
A1 02

RELEASED FOR:- PRELIMINARY GFC INFORMATION

APPROVAL ABD
GENERAL NOTES
Reinforcement & Numeration detail Drawing of Staff Quarters ( Block No.-1) ,(Block No.-2) & CWT at Dummi

JOB NO:-181220DUM LOCATION :- DUMMI

NR Approval 27-04-23 Noor Consultant Noor Consultant Er. Munish


02
Sharma

NR Approval 17-03-23 Noor Consultant Noor Consultant Er. Munish


01
Sharma

Approval 16-02-23 Noor Consultant Noor Consultant Er. Munish


00 NR
Sharma

REV TYPE DESCRIPTION DATE DESIGNED DRAWN CHECKED


NO.
REVISIONS
Design, Build, Operate (DBO) contract for water supply for
PROJECT:-
shimla from river Satlej.

CLIENT:- Shimla Jal Prabandhan Nigam Limited (SJPNL)

IVA CONSULTANT:- TATA CONSULTING ENGINEERS LIMITED

OPERATOR:- LCC SAI KSIPL JV

NAME SIGN DATE SCALE:- N.T.S SHEET 5 OF 7


DSGN Noor Consultant 27-04-23
TITLE-:
DRWN Noor Consultant 27-04-23
Reinforcement & Numeration detail Drawing
CHKD Er. Munish Sharma 27-04-23 of Staff Quarters ( Block No.-1) ,(Block No.-2)
& CWT at Dummi

SIZE REV
DRAWING NO.-SJPNL-DUM-CV-DWG-SQ-CWT-NR-2020
A1 02

RELEASED FOR:- PRELIMINARY GFC INFORMATION

APPROVAL ABD
GENERAL NOTES
Reinforcement & Numeration detail Drawing of Staff Quarters ( Block No.-1) ,(Block No.-2) & CWT at Dummi

JOB NO:-181220DUM LOCATION :- DUMMI

NR Approval 27-04-23 Noor Consultant Noor Consultant Er. Munish


02
Sharma

Approval 17-03-23 Noor Consultant Noor Consultant Er. Munish


01 NR
Sharma

NR Approval 16-02-23 Noor Consultant Noor Consultant Er. Munish


00
Sharma

REV TYPE DESCRIPTION DATE DESIGNED DRAWN CHECKED


NO.
REVISIONS
Design, Build, Operate (DBO) contract for water supply for
PROJECT:-
shimla from river Satlej.

CLIENT:- Shimla Jal Prabandhan Nigam Limited (SJPNL)

IVA CONSULTANT:- TATA CONSULTING ENGINEERS LIMITED

OPERATOR:- LCC SAI KSIPL JV

NAME SIGN DATE SCALE:- N.T.S SHEET 6 OF 7


DSGN Noor Consultant 27-04-23
TITLE-:
DRWN Noor Consultant 27-04-23
Reinforcement & Numeration detail Drawing
CHKD Er. Munish Sharma 27-04-23 of Staff Quarters ( Block No.-1) ,(Block No.-2)
& CWT at Dummi

SIZE REV
DRAWING NO.-SJPNL-DUM-CV-DWG-SQ-CWT-NR-2020
A1 02

RELEASED FOR:- PRELIMINARY GFC INFORMATION

APPROVAL ABD
GENERAL NOTES
Reinforcement & Numeration detail Drawing of Staff Quarters ( Block No.-1) ,(Block No.-2) & CWT at Dummi

JOB NO:-181220DUM LOCATION :- DUMMI

NR Approval 27-04-23 Noor Consultant Noor Consultant Er. Munish


02
Sharma

Approval 17-03-23 Noor Consultant Noor Consultant Er. Munish


01 NR
Sharma

NR Approval 16-02-23 Noor Consultant Noor Consultant Er. Munish


00
Sharma

REV TYPE DESCRIPTION DATE DESIGNED DRAWN CHECKED


NO.
REVISIONS
Design, Build, Operate (DBO) contract for water supply for
PROJECT:-
shimla from river Satlej.

CLIENT:- Shimla Jal Prabandhan Nigam Limited (SJPNL)

IVA CONSULTANT:- TATA CONSULTING ENGINEERS LIMITED

OPERATOR:- LCC SAI KSIPL JV

NAME SIGN DATE SCALE:- N.T.S SHEET 7 OF 7


DSGN Noor Consultant 27-04-23
TITLE-:
DRWN Noor Consultant 27-04-23
Reinforcement & Numeration detail Drawing
CHKD Er. Munish Sharma 27-04-23 of Staff Quarters ( Block No.-1) ,(Block No.-2)
& CWT at Dummi

SIZE REV
DRAWING NO.-SJPNL-DUM-CV-DWG-SQ-CWT-NR-2020
A1 02

RELEASED FOR:- PRELIMINARY GFC INFORMATION

APPROVAL ABD