You are on page 1of 7

Periodical Renewal from Km. 142/620 to Km.

159/280 of NH-26 for the year 2019-2020 in the


state of Odisha on EPC mode.

PROJECT FACILITIES

Authority’s Engineer EPC Contractor

Superintending Engineer, Shivam Condev Pvt. Ltd.


NH Circle, Sambalpur OU-522, ESPLANADE COMMERCIAL DEVELOPMENT,
RASULGARH,BHUBANESWAR-10

Design Consultant Safety Consultant


CRAPTS,
Plot no: 171, Bayababa Matha Lane,
Unit-9, Bhubaneswar
Odisha 751022
SK Associates
Madhusudan Nagar, Bhubaneswar,
Odisha

Proof Consultant

CRAPTS,
Plot no: 171, Bayababa Matha Lane,
Unit-9, Bhubaneswar
Odisha 751022
25

R12

GENERAL NOTES: DESIGN CONSULTANT: DRAWING TITLE:


AUTHORITY ENGINEER: PROOF CONSULTANT: SAFETY CONSULTANT: EPC CONTRACTOR: TYPICAL DETAIL OF
SK ASSOCIATE TRAFFIC SIGNS
1. THIS DRAWING AND INFORMATION CONTAINED HERE ARE STRICTLY
CONFIDENTIAL AND IS FOR USE BY RESTRICTED PERSONS ON THIS PROJECT 853/1431 , UNIT-IV DRAWN: DESIGN: CHECKED: APPROVED:
ONLY. NO PERSON ASSOCIATED WITH THIS PROJECT SHALL DIVULGE THIS
BHUBANESWAR-01 S. MISHRA S. BISWAL UK PANI

R R
INFORMATION TO ANY THIRD PERSON/PARTY IN ANY MANNER WHATSOEVER . SUPERINTENDING ENGINEER,
2. ALL DIMENSIONS ARE IN MILLIMETERS AND LEVELS IN METERS UNLESS NOTED
OTHERWISE.
NH CIRCLE, SAMBALPUR PROJECT: DATE: SCALE:
3. THIS DRAWING SHOULD BE READ IN CONJUNCTION WITH OTHER RELEVANT Periodical Renewal from Km. 142/620 to Km. 159/280 21/09/2020 HORIZONTAL =1:1000 VERTICAL =1:100
STRUCTURAL DRAWINGS AND ALL RELEVANT SECTIONS OF THE CENTRE FOR REASERCH AND PROFESSIONAL CENTRE FOR REASERCH AND PROFESSIONAL SHIVAM CONDEV PVT. LTD.
R00 21.09.2020 FOR APPROVAL of NH-26 for the year 2019-2020 in the state of
SPECIFICATIONS. TRAINING & SERVISES TRAINING & SERVISES OU-522, ESPLANADE COMMERCIAL DRAWING NO: REV: SIZE:
4. DISCREPANCY IN THE DRAWINGS IF ANY, SHALL BE BROUGHT TO THE NOTICE MAA GHARA, PLOT 171 (P) MAA GHARA, PLOT 171 (P) DEVELOPMENT,RASULGARH,BHUBANESWAR-10 Odisha on EPC mode.
CRAPTS/EPC/SCPL/NH-26/PF/01 R00 A3
REV. DATE DESCRIPTION OF THE AUTHORITY'S ENGINEER PRIOR TO CONSTRUCTION. UNIT 9(FLAT), BHUBANESWAR -22 UNIT 9(FLAT), BHUBANESWAR -22
WARNING SIGNS

70 70 70 70 70 70 70 70 70 70 70

900

900

900

900

900

900

900

900

900

900

900
Radius
45mm
W-4 W-5 W-6 W-14 W-16 W-19L W-19R W-21(a) W-21(b) W-22 W-23
Built up Area Cattle Crossing Cross Road Falling Rocks Gap in Median Left hand curve Right hand curve Major Road Ahead Major Road Ahead Men at Work Merging Traffic Ahead

70 70 70 70 70 70 70 70 70 70
70
900

900

900

900

900

900

900

900

900

900

900
Radius
45mm
W-24 W-25 W-27 W-28 W-29 W-30 W-31 W-32l W-36 W-38 W-39
Narrow Bridge Ahead Narrow Road Ahead Overhead Cables Pedestrian Crossing Playground Ahead Quay Side or Queues Likely ahead Reduced Road Widens Roundabout Rumble Strip
River Bank Carriageway

70 70 70 70 70 70 70 70 70 70
70
900

900

900

900

900

900

900

900

900

900

900
Radius
45mm
W-41 W-43 W-44 W-47 W-48a W-48b W-50a W-50b W-52 W-54 W-60
School Ahead Side Road Right Side Road Left Speed Breaker Staggered Staggered Steep Ascent Steep Descent T-Intersection Traffic Signals Y-Intercestion
intersection intersection

70 70
900

900
Radius
45mm
W-60L W-60R
Y-Intersection Y-Intersection

Notes :
1. ALL THE DIMENSIONS ARE IN MILLIMETER UNLESS SPECIFIED
2. RETROREFLECTORISED SHEETING SHALL BE CONFORMING TO ASTM D-4957-2001/
(TYPE VIII AND TYPE IX).
3. SIGNS SHALL BE ERECTED AS PER DRAWING NO. AGICL/216001/H/MD-MS-0016
4. COLOUR, DIMENSIONS OF SIGNS & LETTERS SHALL BE AS PER IRC-67

GENERAL NOTES: DESIGN CONSULTANT: DRAWING TITLE:


AUTHORITY ENGINEER: PROOF CONSULTANT: SAFETY CONSULTANT: EPC CONTRACTOR:
TYPICAL DETAIL SIGN BOARD
1. THIS DRAWING AND INFORMATION CONTAINED HERE ARE STRICTLY SK ASSOCIATE
CONFIDENTIAL AND IS FOR USE BY RESTRICTED PERSONS ON THIS PROJECT 853/1431 , UNIT-IV DRAWN: DESIGN: CHECKED: APPROVED:
ONLY. NO PERSON ASSOCIATED WITH THIS PROJECT SHALL DIVULGE THIS
BHUBANESWAR-01 S. MISHRA S. BISWAL UK PANI

R R
INFORMATION TO ANY THIRD PERSON/PARTY IN ANY MANNER WHATSOEVER . SUPERINTENDING ENGINEER,
2. ALL DIMENSIONS ARE IN MILLIMETERS AND LEVELS IN METERS UNLESS NOTED
OTHERWISE.
NH CIRCLE, SAMBALPUR PROJECT: DATE: SCALE:
3. THIS DRAWING SHOULD BE READ IN CONJUNCTION WITH OTHER RELEVANT Periodical Renewal from Km. 142/620 to Km. 159/280 21/09/2020 HORIZONTAL =1:1000 VERTICAL =1:100
STRUCTURAL DRAWINGS AND ALL RELEVANT SECTIONS OF THE CENTRE FOR REASERCH AND PROFESSIONAL CENTRE FOR REASERCH AND PROFESSIONAL SHIVAM CONDEV PVT. LTD.
R00 21.09.2020 FOR APPROVAL of NH-26 for the year 2019-2020 in the state of
SPECIFICATIONS. TRAINING & SERVISES TRAINING & SERVISES OU-522, ESPLANADE COMMERCIAL DRAWING NO: REV: SIZE:
4. DISCREPANCY IN THE DRAWINGS IF ANY, SHALL BE BROUGHT TO THE NOTICE MAA GHARA, PLOT 171 (P) MAA GHARA, PLOT 171 (P) DEVELOPMENT,RASULGARH,BHUBANESWAR-10 Odisha on EPC mode.
CRAPTS/EPC/SCPL/NH-26/PF/02 R00 A3
REV. DATE DESCRIPTION OF THE AUTHORITY'S ENGINEER PRIOR TO CONSTRUCTION. UNIT 9(FLAT), BHUBANESWAR -22 UNIT 9(FLAT), BHUBANESWAR -22
FACILITY INFORMATION SIGNS
450 450 450 450 450 450 450

600

600

600

600

600

600
600
500m 500m 1km

I2-0 I2-1 I2-2 I2-3 I2-4 I2-5 I2-6


Eating Place Filling Station First Aid Post Hospital Light Refreshment Public Telephone Resting place

OTHER USEFUL INFORMATION SIGNS


450 450 450 450 450 450
750
450
600

600

600

600

600

600

900

600
I3-4 I3-30 I3-36 I3-37 I3-32 I3-35 I5-0
Bus Stop Police Station Toll Road Ahead U-turn Ahead Repair Facility Toilet Chevron

REGULATORY SIGNS

Stop & Giveway Signs Prohibitory Signs SPEED LIMIT & VEHICLE CONTROL SIGNS
30

70

GIVE
900

900

900

900
80 65 50 40

600

600

600

600
900

900

WAY

R4-5a R4-5a R4-5a R4-5a


R2-10R R2-12 R2-I3 R2-19
Right turn One Way Overtaking Maximum Speed limit Maximum Speed limit Maximum Speed limit Maximum Speed limit
R1-1 R1-2 U-turn
STOP GIVE WAY Prohibited Prohibited Prohibited

COMPULSORY DIRECTION CONTROL & OTHER SIGNS NO PARKING & STOPPING SIGNS
600

600

600

600
R6-6 R6-10 R3-1 R3-2
Compulsory Keep Left Pass either side No Parking No Parking and
No Stopping
Notes :
1. ALL THE DIMENSIONS ARE IN MILLIMETRE UNLESS OTHERWISE SPECIFIED
2. RETROREFLECTORISED SHEETING SHALL BE CONFORMING TO ASTM D-4957-2001/
(TYPE VIII AND TYPE IX).
3. SIGNS SHALL BE ERECTED AS PER DRAWING NO. AGICL/216002/H/MD-MS-0016 E:\miyanmar project\1ST PHASE DATA\New
folder\MX\7.6.20\Cross Sections (23.06.2020)\Cross
Sections (23.06.2020)\design director.jpg

4. COLOUR, DIMENSIONS OF SIGNS & LETTERS SHALL BE WRITTEN AS PER IRC:67


5. NAME OF THE PLACES SHALL BE WRITTEN IN BOTH ENGLISH AND LOCAL LANGUAGE

GENERAL NOTES: DESIGN CONSULTANT: DRAWING TITLE:


AUTHORITY ENGINEER: PROOF CONSULTANT: SAFETY CONSULTANT: EPC CONTRACTOR:
TYPICAL DETAIL SIGN BOARD
1. THIS DRAWING AND INFORMATION CONTAINED HERE ARE STRICTLY SK ASSOCIATE
CONFIDENTIAL AND IS FOR USE BY RESTRICTED PERSONS ON THIS PROJECT 853/1431 , UNIT-IV DRAWN: DESIGN: CHECKED: APPROVED:
ONLY. NO PERSON ASSOCIATED WITH THIS PROJECT SHALL DIVULGE THIS
BHUBANESWAR-01 S. MISHRA S. BISWAL UK PANI

R R
INFORMATION TO ANY THIRD PERSON/PARTY IN ANY MANNER WHATSOEVER . SUPERINTENDING ENGINEER,
2. ALL DIMENSIONS ARE IN MILLIMETERS AND LEVELS IN METERS UNLESS NOTED
OTHERWISE.
NH CIRCLE, SAMBALPUR PROJECT: DATE: SCALE:
3. THIS DRAWING SHOULD BE READ IN CONJUNCTION WITH OTHER RELEVANT Periodical Renewal from Km. 142/620 to Km. 159/280 21/09/2020 HORIZONTAL =1:1000 VERTICAL =1:100
STRUCTURAL DRAWINGS AND ALL RELEVANT SECTIONS OF THE CENTRE FOR REASERCH AND PROFESSIONAL CENTRE FOR REASERCH AND PROFESSIONAL SHIVAM CONDEV PVT. LTD.
R00 21.09.2020 FOR APPROVAL of NH-26 for the year 2019-2020 in the state of
SPECIFICATIONS. TRAINING & SERVISES TRAINING & SERVISES OU-522, ESPLANADE COMMERCIAL DRAWING NO: REV: SIZE:
4. DISCREPANCY IN THE DRAWINGS IF ANY, SHALL BE BROUGHT TO THE NOTICE MAA GHARA, PLOT 171 (P) MAA GHARA, PLOT 171 (P) DEVELOPMENT,RASULGARH,BHUBANESWAR-10 Odisha on EPC mode.
CRAPTS/EPC/SCPL/NH-26/PF/03 R00 A3
REV. DATE DESCRIPTION OF THE AUTHORITY'S ENGINEER PRIOR TO CONSTRUCTION. UNIT 9(FLAT), BHUBANESWAR -22 UNIT 9(FLAT), BHUBANESWAR -22
INFORAMATORY SIGNS
DIRECTION & PLACE IDENTIFICATION SIGNS

XXXXX XXXX XXXX XXXX


KESINGA KESINGA CUTTACK CUTTACK XXXXXX
XXXX XXXX BHUBANESWAR
XXX XXXX
BHAWANIPATNA BYPASS BHUBANESWAR KESINGA KESINGA SAMBALPUR
I1-0 I1-0R I1-0L XXXX XXXX XXXX
Advance Direction/Destination Sign Advance Direction/Destination Sign
Advance Direction/Destination Sign KHURDA
I1-1 I1-2
Advance Direction/Destination Sign Map type advance direction sign

XXXXXX XXXX
XX
BHUBANESWAR KHURDA XXX
KESINGA SAMBALPUR XXXX XX TRUCK
CUTTACK KESINGA LAYBYE TOLL BOOTH AHEAD
XXXX XXXX I1-8
I1-6 I1-7
XXXX XX Place identification sign Truck Lay Bye Toll booth Ahead

BHAWANIPATNA
I1-3 I1-5
Map type advance direction sign Reassurance sign ROUTE MARKER SIGN HAZARD MARKER SIGNS
on rotary intersection

NH
XXX XXX
2 HZ-2 HZ-3

KESINGA KHURDA WEIGHT BRIDGE AHEAD


HZ-1L HZ-1R

I1-4R I1-4L I1-9


Direction sign Direction sign Weigh Bridge Ahead

Notes :
1. ALL THE DIMENSIONS ARE IN MILLIMETRE UNLESS OTHERWISE SPECIFIED
2. ALL ROAD SIGNS SHALL BE WITH HIGH INTENSITY MICRO PRISMATIC GRADE SHEETING. I8-1
(TYPE IV) AS PER ASTM STANDARD.
3. SIGNS SHALL BE ERECTED AS PER DRAWING NO. AGICL/216001/H/MD-MS-0016
National Highway
Route Marker Sign
4. NAME OF THE PLACES SHALL BE WRITTEN IN BOTH ENGLISH AND LOCAL LANGUAGE
5. COLOUR, DIMENSIONS OF SIGNS & LETTER SHALL BE AS PER IRC:67
6. XXXX = LOCAL LANGUAGE

GENERAL NOTES: DESIGN CONSULTANT: DRAWING TITLE:


AUTHORITY ENGINEER: PROOF CONSULTANT: SAFETY CONSULTANT: EPC CONTRACTOR:
TYPICAL DETAIL SIGN BOARD
1. THIS DRAWING AND INFORMATION CONTAINED HERE ARE STRICTLY SK ASSOCIATE
CONFIDENTIAL AND IS FOR USE BY RESTRICTED PERSONS ON THIS PROJECT 853/1431 , UNIT-IV DRAWN: DESIGN: CHECKED: APPROVED:
ONLY. NO PERSON ASSOCIATED WITH THIS PROJECT SHALL DIVULGE THIS
BHUBANESWAR-01 S. MISHRA S. BISWAL UK PANI

R R
INFORMATION TO ANY THIRD PERSON/PARTY IN ANY MANNER WHATSOEVER . SUPERINTENDING ENGINEER,
2. ALL DIMENSIONS ARE IN MILLIMETERS AND LEVELS IN METERS UNLESS NOTED
OTHERWISE.
NH CIRCLE, SAMBALPUR PROJECT: DATE: SCALE:
3. THIS DRAWING SHOULD BE READ IN CONJUNCTION WITH OTHER RELEVANT Periodical Renewal from Km. 142/620 to Km. 159/280 21/09/2020 HORIZONTAL =1:1000 VERTICAL =1:100
STRUCTURAL DRAWINGS AND ALL RELEVANT SECTIONS OF THE CENTRE FOR REASERCH AND PROFESSIONAL CENTRE FOR REASERCH AND PROFESSIONAL SHIVAM CONDEV PVT. LTD.
R00 21.09.2020 FOR APPROVAL of NH-26 for the year 2019-2020 in the state of
SPECIFICATIONS. TRAINING & SERVISES TRAINING & SERVISES OU-522, ESPLANADE COMMERCIAL DRAWING NO: REV: SIZE:
4. DISCREPANCY IN THE DRAWINGS IF ANY, SHALL BE BROUGHT TO THE NOTICE MAA GHARA, PLOT 171 (P) MAA GHARA, PLOT 171 (P) DEVELOPMENT,RASULGARH,BHUBANESWAR-10 Odisha on EPC mode.
CRAPTS/EPC/SCPL/NH-26/PF/04 R00 A3
REV. DATE DESCRIPTION OF THE AUTHORITY'S ENGINEER PRIOR TO CONSTRUCTION. UNIT 9(FLAT), BHUBANESWAR -22 UNIT 9(FLAT), BHUBANESWAR -22
DETAILS OF CENTRE LINE
DETAILS OF EDGE LINE MARKING

BEYOND INTERSECTIONS

PEDESTRIAN CROSSING

AT INTERSECTIONS SIZE OF LETTERS

DIRECTIONAL ARROWS

DETAILS AT CURVES
DETAILS AT SHARP CURVES
(NO-OVERTAKING ZONE)

NOTE:

DIAGONAL MARKINGS PEDESTRIAN CROSSING

GENERAL NOTES: DESIGN CONSULTANT: DRAWING TITLE:


AUTHORITY ENGINEER: PROOF CONSULTANT: SAFETY CONSULTANT: EPC CONTRACTOR: TYPICAL DETAIL OF
1. THIS DRAWING AND INFORMATION CONTAINED HERE ARE STRICTLY SK ASSOCIATE PAVEMENT MARKING
CONFIDENTIAL AND IS FOR USE BY RESTRICTED PERSONS ON THIS PROJECT 853/1431 , UNIT-IV DRAWN: DESIGN: CHECKED: APPROVED:
ONLY. NO PERSON ASSOCIATED WITH THIS PROJECT SHALL DIVULGE THIS
BHUBANESWAR-01 S. MISHRA S. BISWAL UK PANI

R R
INFORMATION TO ANY THIRD PERSON/PARTY IN ANY MANNER WHATSOEVER . SUPERINTENDING ENGINEER,
2. ALL DIMENSIONS ARE IN MILLIMETERS AND LEVELS IN METERS UNLESS NOTED
OTHERWISE.
NH CIRCLE, SAMBALPUR PROJECT: DATE: SCALE:
3. THIS DRAWING SHOULD BE READ IN CONJUNCTION WITH OTHER RELEVANT Periodical Renewal from Km. 142/620 to Km. 159/280 21/09/2020 HORIZONTAL =1:1000 VERTICAL =1:100
STRUCTURAL DRAWINGS AND ALL RELEVANT SECTIONS OF THE CENTRE FOR REASERCH AND PROFESSIONAL CENTRE FOR REASERCH AND PROFESSIONAL SHIVAM CONDEV PVT. LTD.
R00 21.09.2020 FOR APPROVAL of NH-26 for the year 2019-2020 in the state of
SPECIFICATIONS. TRAINING & SERVISES TRAINING & SERVISES OU-522, ESPLANADE COMMERCIAL DRAWING NO: REV: SIZE:
4. DISCREPANCY IN THE DRAWINGS IF ANY, SHALL BE BROUGHT TO THE NOTICE MAA GHARA, PLOT 171 (P) MAA GHARA, PLOT 171 (P) DEVELOPMENT,RASULGARH,BHUBANESWAR-10 Odisha on EPC mode.
CRAPTS/EPC/SCPL/NH-26/PF/05 R00 A3
REV. DATE DESCRIPTION OF THE AUTHORITY'S ENGINEER PRIOR TO CONSTRUCTION. UNIT 9(FLAT), BHUBANESWAR -22 UNIT 9(FLAT), BHUBANESWAR -22
ROADWAY TABLE FOR RECOMMENDED SPACING FOR ROADWAY

15cm
CARRIAGE WAY
DELINEATORS ON HORIZONTAL CURVES
WHITE ROUND REFLECTOR
RADIUS OF CURVE SPACING ON CURVE, S 7.5cm DIA.

15cm
(METERS) (METERS)

6S
30 6

15cm
ABOUT 80-100cm
50 8

15cm
PRINTED BLACK AND WHITE
100 12 STRIPS 15cm WIDE

200 20

3S
END OF CURVE
300 25
1.8S X S
SEE NOTE 1 100mm Ø RCC M20
400 30

500 35
2S
S

600 38
S

30cm
BEGINNING OF CURVE 700 42
S

S RAISED METAL ROAD STUD


S
S 800 45
S 1.8S
SEE NOTES 2 & 3

10cm
900 48 FOUNDATION IN RCC M15

1.8S 3S 6S
1000 50 20cm

ROADWAY DELINEATOR SPACING ON CURVES DELINEATOR WITH CIRULAR REFLECTOR


A2 SIZE SCALE 1:10
A3 SIZE SCALE 1:15

1.5M EARTHEN SHOULDER

10M CARRIAGE WAY

6M E
6M ZON
KI NG
6M RTA
OVE
6M NO
6M

9M

CT IGN
N
SE ARN
IO
W
M
18

N
C TIO
SE
AL
RM
M
18

NO
ROAD STUDS ARRANGEMENT
SCALE-N.T.S
Notes :
1. ALL DIMENSIONS ARE IN MILLIMETRE UNLESS SPECIFIED.
2. ADJUST DISTANCE 'X' SUITABLY SO THAT THE LAST ROADWAY DELINEATOR
IS AT THE END OF THE CURVE.
3. INSTALL ALL DELINEATORS AT EDGE OF THE ROADWAY PERPENDICULAR TO
THE ONCOMING TRAFFIC.
4. SEE TABLE1 FOR VALUE OF 'S' i.e. SPACING OF DELINEATORS ON THE CURVE.
5. THE SPACING OF FIRST, SECOND & THIRD DELINEATORS ON THE APPROACHES
SHALL BE 1.85S, 3S & 6S RESPECTIVELY BUT NOT EXCEEDING 50m.
6. ROAD STUD SHALL BE AS PER MANUFACTURES SPECIFICATION.

GENERAL NOTES: DESIGN CONSULTANT: DRAWING TITLE:


AUTHORITY ENGINEER: PROOF CONSULTANT: SAFETY CONSULTANT: EPC CONTRACTOR:
TYPICAL DETAIL OF
1. THIS DRAWING AND INFORMATION CONTAINED HERE ARE STRICTLY SK ASSOCIATE ROAD DELINEATOR
CONFIDENTIAL AND IS FOR USE BY RESTRICTED PERSONS ON THIS PROJECT 853/1431 , UNIT-IV DRAWN: DESIGN: CHECKED: APPROVED:
ONLY. NO PERSON ASSOCIATED WITH THIS PROJECT SHALL DIVULGE THIS
BHUBANESWAR-01 S. MISHRA S. BISWAL UK PANI

R R
INFORMATION TO ANY THIRD PERSON/PARTY IN ANY MANNER WHATSOEVER . SUPERINTENDING ENGINEER,
2. ALL DIMENSIONS ARE IN MILLIMETERS AND LEVELS IN METERS UNLESS NOTED
OTHERWISE.
NH CIRCLE, SAMBALPUR PROJECT: DATE: SCALE:
3. THIS DRAWING SHOULD BE READ IN CONJUNCTION WITH OTHER RELEVANT Periodical Renewal from Km. 142/620 to Km. 159/280 21/09/2020 HORIZONTAL =1:1000 VERTICAL =1:100
STRUCTURAL DRAWINGS AND ALL RELEVANT SECTIONS OF THE CENTRE FOR REASERCH AND PROFESSIONAL CENTRE FOR REASERCH AND PROFESSIONAL SHIVAM CONDEV PVT. LTD.
R00 21.09.2020 FOR APPROVAL of NH-26 for the year 2019-2020 in the state of
SPECIFICATIONS. TRAINING & SERVISES TRAINING & SERVISES OU-522, ESPLANADE COMMERCIAL DRAWING NO: REV: SIZE:
4. DISCREPANCY IN THE DRAWINGS IF ANY, SHALL BE BROUGHT TO THE NOTICE MAA GHARA, PLOT 171 (P) MAA GHARA, PLOT 171 (P) DEVELOPMENT,RASULGARH,BHUBANESWAR-10 Odisha on EPC mode.
CRAPTS/EPC/SCPL/NH-26/PF/06 R00 A3
REV. DATE DESCRIPTION OF THE AUTHORITY'S ENGINEER PRIOR TO CONSTRUCTION. UNIT 9(FLAT), BHUBANESWAR -22 UNIT 9(FLAT), BHUBANESWAR -22

You might also like