1. Top Davit pipe not fabricated.

--> Under fabrication (Non Pressure part will not


hold PWHT). Ok. Noted. FF shall offer the same upon completion.
FF Response : Will offer After completion
2. Elevation of Pipe support – 91602-C-05-01 (-8mm).-Comment Closed. PEG
Engineering confirmed and accepted.
3. Elevation of Pipe support – 91602-C-05-09 (-7mm).- Comment Closed. PEG
Engineering confirmed and accepted.
4. Elevation of Pipe support – 91602-C-05-02B (-7mm).- Comment Closed. PEG
Engineering confirmed and accepted.
5. Pipe support – 91602-C-05-19 have not welded. Comment Closed. Welding
completed. The same inspected and accepted.
6. Electrical support- 91602-C-05-E03-2 have not welded.- Comment
Closed. PEG Engineering confirmed and accepted.
7. Elevation of Electrical support- 91602-C-05-E10 (-50mm).- Comment
Closed. PEG Engineering confirmed and accepted. FF will update in the
drawing and to be submitted for approval as agreed.
FF Response: Noted
8. Instrument support- 91602-C-05-I13 have not welded ( To be Confirm with
PEG ENGG)- Comment Closed. Welding completed. The same inspected and
accepted.
9. Electrical support- 91602-C-05-E18 have not welded.- Comment
Closed. Welding completed. The same inspected and accepted.
10. Elevation of Electrical support- 91602-C-05-E19 (-8mm).- Comment
Closed. PEG Engineering confirmed and accepted.
11. Platform support #1 have not welded.- Comment Closed. Welding completed.
The same inspected and accepted.
12. Ladder# 1 Sliding support have not welded.- Comment Closed. Welding
completed. The same inspected and accepted.
13. Visual comments to be rectified and re offer.- Comment Closed. Weld visual
from inside to be offered after rectification. MPI to be completed. FF Response:
MPI completed and visual points cleared by FF QC. PEG inspector can verify
during Verification of Thermocouple location
14. Trial assembly of platform and ladder to be offered.- Will be carried out later
stage. Noted.
15. Some of the Pipe supports cleat welds comes on the pad welding itself.
Comment Closed. FF to explain, How it was closed.FF response :In discussion
with PEG Engg, Will be updated by 29th COB before release for PWHT
16. Final Material traceability record to be provided for review.-Ready for
Review. Noted. PEG will review the same in next visit and address if any
concerns.FF RESPONSE: NOTED CAN BE VERIFIED
17. Final weld traceability along with all NDE reports to be provided review.- Ready
for Review. Noted. PEG will review the same in next visit and address if any
concerns. FF RESPONSE: NOTED CAN BE VERIFIED
18. Pneumatic test to be offered for RF Pads.- Comment Closed. Noted.
19. Trial assembly of Trays done in wrong position. Tray valves should come on
top position and stiffener supports should come in bottom position. But,
Position of Tray valves and stiffeners supports interchanged. Anyhow, the
same shall be taken care during final installation.-Will be taken care during final
assembly. Noted. It is Ferrofab responsibility. FF response: Noted FF will take
care during final assembly
20. Trial assembly of Gauge plate along with skirt base ring to be offered.-
Comment Closed. Not yet offered. FF response Trail Assembly done and
ready PEG inspector can verify during Verification of Thermocouple location

21. Elevation of LD#4 sliding support (-7mm) from fixed support.- Comment
Closed. PEG Engineering confirmed and accepted.
22. LD#1 fixed support have not welded.- Comment Closed. Welding completed.
The same inspected and accepted.