CIVIL & STRUCTURAL ENGINEERING CONSULTANTS

DOCUMENT REVIEW REPORT (DRR)


(PRIVATE) LIMITED
No. 01, 33rd Lane, Bagatalle Rd., Colombo 03 DRR No. : 11
Tel : 94- 11 – 2501727
Fax : 94- 71 – 8802859
Email contact@csec.lk Date : 18/04/2022

Project : Proposed Condominium Development for South Beach Weligama Properties (Pvt) Ltd
Employer : South Beach Weligama Properties (Pvt) Ltd
Engineer : Global Project Management Consultants (Pvt) Ltd
Contractor : Buildmart Lanka (Pvt) Ltd.
To : Mr. Mihiru Perera (Contractor’s Representative) – Buildmart Lanka (Pvt) Ltd.

Contractor's Doc Ref. No. Rev Description Status * Expected Re-issue Date

Request for Material Approval for Waterproofing


SBW-RFMA-005.R1 0 B -
and Waterproofing Method Statement

Comments
• Sikabit T-1150 PG SA can be accepted as the waterproofing membrane for Roof slab and Basement slab.

• Fleximent 201 can be accepted as the waterproofing membrane for Bathrooms, Swimming Pool, Water Tanks and Lift Pit

• Sikaflex cannot be accepted as the joint sealant. The service temperature of the sealent shall be greater than 80oC and it

shall be UV stable.

• Certifications shall be provided by both installer and waterproof membrane manufacturer that the waterproofing systems

together with details and fitments are fit for purpose for the waterproofing works shown on drawings.

• Shop drawings shall be submitted, fully detailing the work and installations including details at Margins, Flashings,

Movement Joints, Outlets and Penetrations.

• Samples of each waterproofing material shall be provided for approval.

• A sample installation shall be carried out at a location chosen by the engineer and it shall be 10m 2 minimum completed with

jointing, sealing, flashing and ancillary work to demonstrate finished work.

• All work shall be carried out in a manner, which ensures that warranties of the installers are not restricted or voided.

• In the event of leak, water proofing company should be liable for the removal or reinstallation and related cost there of

screeds or any other layer that may have been laid over the water proofing.

Notes

From: Reviewed By:


Eng. Shiromal Fernando
Civil & Structural Engineering Consultants (Pvt) Ltd
772/A, Wijesinghe Mawatha, Madinnagoda, Rajagiriya
Tel: +94 11 268 3979
………………………………………..

* Status
A – Approved B – Approved with Comments C – Not Approved - Resubmit D – Rejected
®
Fleximent 201 Flexible Cementitious
Waterproofing Coating

032 - 019
Fleximent® 201 is a two-component, flexible cementitious Environmentally
Friendly Coating
waterproofing coating comprising of a proprietary synthetic
resin dispersion and a blend of selected cement mixed with
fillers. Once cured, the membrane allows entrapped water
vapour to escape but yet remain impermeable to water.

Fleximent® 201 is flexible, adheres to most surfaces and


fills hairline cracks. It has excellent resistance to wear,
weather, abrasion, aggressive soils and contaminated
ground water. Fleximent® 201 acts as an effective
waterproofing coating for floors, walls, water retaining
structures and planter boxes. It may be applied onto
surfaces in contact with potable water.

Fleximent® 201 may be applied to damp surfaces. It


contains no chlorine and salts that cause corrosion and
efflorescence and is resistant to frost and thawing salts.

Fleximent® 201 meets the requirements of British


Standard BS 6920:90 and Singapore Standard SS 375:94.

Protect freshly applied surfaces from strong sunlight and


Installation Procedures drying wind with a polyethylene sheet. Fleximent ® 201
once cured, should be covered by a protective screed as
Surfaces should be clean, free from honeycombs, voids, soon as possible. Care should be exercised to prevent
dirt, loose material, paint, oil, curing agents or other damage to the waterproofing during subsequent
contaminants. construction work prior to laying of the protection screed.

Prior to application, dampen the substrate with a brush or Fleximent® 201 should be applied in 2 coats at a coverage
roller. of 1.0 kg – 1.1 kg per sq.m. per coat for a final dry film
a. Pour Part A (liquid) into a clean container. thickness of approximately 1.2 mm.
b. Pour Part B (powder) slowly into Part A.
c. Mix with a low speed drill fitted with a purpose-made
paddle, ensuring the mix is homogeneous and
lump-free.

Fleximent® 201 may be applied by squeegee, roller or


brush to horizontal and vertical surfaces. Ensure that air is
not entrapped in the membrane. For joints and corners,
apply the slurry with a brush ensuring that areas are
worked and covered well. Allow curing to take place
completely before applying the second coat.
Specifications
Mix density 1300 kg/m3
protective screed

Mixed colour Grey cement sand render

Pot life @ 35ºC approx. 1 hour Fleximent 201

protective/bedding screed
Drying time 1 – 3 hours

Water penetration test 0, no water penetration (DIN 1048)

Crack bridging 2 mm (ASTM C836)

Hardness Shore A >50 (ASTM D2240)


Wet Area
Adhesion to substrate >1.0 N/mm2

Water vapour transmission <21 g/m2.d (ASTM E96-93)


Fleximent 201
Tensile strength >1.6 N/mm2 (ASTM D412)
protective/bedding screed
Elongation at break >150 % (ASTM D412)
discharge pipe

Health and Safety

Do not allow Fleximent® 201 to be contaminated by other


materials. Gloves and goggles should be worn. Any splashes to non-shrink grout

the skin or eye should be washed off with clean water. Store in Drain Outlet
cool and dry place.

e d for s,
Fleximent 201

p r o v o o m
al ap ng bathr r tank
cement sand render

t e r i
Ma proofi
e r o l , wate protective/bedding screed

wat ming p o
swim ft pit
li
and

Water-Retaining Structure

Note: The information provided in this brochure is based on current knowledge


and experience and does not infer any legally binding assurance or warranty,
expressed or implied. Intending purchasers should verify whether any changes to
specifications or applications or otherwise have been made since this literature
was issued.

Singapore
22nd March 2022

METHOD STATEMENT

PROJECT : PROPOSED SOUTH BEACH WELIGAMA CONDOMINIUM PROJECT

SUBJECT : WATERPROOFING OF BATHROOMS

THE PRODUCT:

Fleximent 201 is a two component cementitious flexible membrane. The product consists of
powder and liquid. The product is a brush application.

THE APPLICATION:
All plumbing must be completed and pressure tested (if necessary) prior to commencement of
the waterproofing. All voids created for installation of pipes, fitting etc must be filled and
1 completed

The cement mortars debris on the surface must be removed by main contractor. The surface is
then inspected to ascertain if there is foreign objects/honey combing in the surface. These areas
will be hacked and patched prior to waterproofing application by the main contractor.

For vertical brick/ block work, it must be plastered semi rough thin plaster, to a height of
300mm-1000mm from the finished floor level and 2100 mm high of shower area .Lay the fillet
minimum of 25mm X 25mm of cement sand is placed at the intersection of the vertical and the
2 horizontal.

The surface is then thoroughly cleaned. Once the surface preparation is completed, the surface
is wetted prior to application of the waterproofing. This is to promote capillary action of
product into substrate.

The two components that constitute the Fleximent 201 product are mixed to ensure proper
dispersion of the components. The first coat applied on the concrete substrate. On completion
of the first coat, allow for cure 4-3 hours then will undertake the second coat application over
the first coat. Edger’s will reinforce with polyester mat and will apply 3rd coat over the 2nd
coat at edger’s.

In areas where pipes/penetrations exists, the membrane will be extended either along the
surface of the pipe, if the pipe protrudes from the concrete surface or into the pipe if the pipe
is flushed with the concrete surface.

Allow product to cure minimum of 24 hours. The structure is then pond tested.( Minimum of
24 hr)

On pond test if there are no any defects is found. Then water will be removed and lay the
protection screed or tile bed.
1. Any uneven areas, defected areas and chiseled patches to be treated with an approved
epoxy resin based un-pigmented primer and to be leveled with a homogeneously mixed
approved 2-component epoxy mortar.
2. The detail at intersections shall be provided with sketches.
22nd March 2022

METHOD STATEMENT

PROJECT : PROPOSED CONDOMINIUM PROJECT AT WALIGAMA

SUBJECT : WATERPROOFING OF SWIMMING POOL WALL AND FLOOR

THE PRODUCT : Fleximent 201


a two component cementitious flexible membrane. The product consists of powder and
liquid. The product is a brush application.

APPLICATION.
All plumbing must be completed and pressure tested (if necessary) prior to commencement of
the waterproofing. All voids created for installation of pipes, fitting etc must be filled and
completed

The cement mortars debris on the surface must be removed by main contractor. The surface is
then inspected to ascertain if there is foreign objects/honey combing in the surface. These areas
1 will be hacked and patched prior to waterproofing application by the main contractor.

The product is applied directly on structural concrete. Therefore existing cement sand moter,
on the surface must be removed. The surface is then inspected. If honeycombing exists in, they
will be hacked and patched with grout 280 repairer mortar.

If any water leeks are exists will seal with mortar fast

The surface is then thoroughly cleaned. Once the surface preparation is completed, the surface
is wetted prior to application of the waterproofing. This is to promote capillary action of
product into substrate.

Fleximent 201 powder and liquid are mixed with a mechanical mixer to ensure proper
dispersion of the components. The first coat applied on the concrete substrate. And allow it to
cure for 3-4 hours.

Then second coat application is undertaken over the first coat

Construction joint’s will reinforce with polyester mat and will apply 3rd coat over the 2nd
coat.

In areas where pipes/penetrations exists, the membrane will be extended either along the
surface of the pipe, if the pipe protrudes from the concrete surface or into the pipe if the pipe
is flushed with the concrete surface (finishing level)

Allow product to cure minimum of 24 hours. The structure is then pond tested.( Minimum of
48 hr)
On pond test if there are no any defects is found. Then water will remove and will be protected
with cement sand screed or tile bed.
1. Any uneven areas, defected areas and chiseled patches to be treated with an approved
epoxy resin based un-pigmented primer and to be leveled with a homogeneously mixed
approved 2-component epoxy mortar.
22nd March 2022

METHOD STATEMENT

PROJECT : PROPOSED SOUTH BEACH WELIGAMA CONDOMINIUM PROJECT

SUBJECT : WATERPROOFING OF WATER TANK/ LIFT WELL

THE PRODUCT: Fleximent 201


A two component cementitious flexible membrane. The product consists of powder and
liquid. The product is a brush application.

THE APPLICATION:
All plumbing must be completed and pressure tested prior to commencement of the
waterproofing. All voids created for installation of pipes, fitting etc must be filled and
completed
1
The cement mortars debris on the surface must be removed by main contractor. The surface is
then inspected to ascertain if there is foreign objects/honey combing in the surface. These areas
will be hacked and patched prior to waterproofing application by the main contractor.

The surface is then thoroughly cleaned. Once the surface preparation is completed, the surface
is wetted prior to application of the waterproofing. This is to promote capillary action of
product into substrate.

Lay the fillet minimum of 25mm X 25mm of cement sand is placed at the intersection of the
vertical and the horizontal. (This is to be undertaken by main contractor.)
2
The surface is then thoroughly cleaned. Once the surface preparation is completed, the surface
is wetted prior to application of the waterproofing. This is to promote capillary action of
product into substrate.

The two components that constitute the Fleximent 201 product are mixed to ensure proper
dispersion of the components. The first coat applied on the concrete substrate. On completion
of the first coat, allow product to get cure for 5-6 hours then second coat application is
undertaken over the first coat. Edger’s will reinforce with polyester mat and will apply 3 rd
coat over the 2nd coat.

In areas where pipes/penetrations exists, the membrane will be extended either along the
surface of the pipe, if the pipe protrudes from the concrete surface or into the pipe if the pipe
is flushed with the concrete surface.
Allow product to cure minimum of 24 hours. The structure is then pond tested.( Minimum of
24 hr)
On pond test if there are no any defects is found. The areas may be protected with a cement
sand mortar by main contractor.

1. Any uneven areas, defected areas and chiseled patches to be treated with an approved
epoxy resin based un-pigmented primer and to be leveled with a homogeneously mixed
approved 2-component epoxy mortar.
2. The detail at intersections shall be provided with sketches.