Professional Documents
Culture Documents
net/publication/260366425
CITATIONS READS
0 2,322
3 authors:
P. B. Deolalikar
SEE PROFILE
All content following this page was uploaded by V. V. Bhosekar on 24 April 2017.
ABSTRACT
Spillways of high head dams are susceptible to cavitation damage due to surface
deformities and high velocity. Aeration is the most effective method for mitigating
to refer the existing designs while designing an aeration system for a dam. This
paper highlights the details of aerators for five major projects in India viz. Sardar
Sarovar, Tehri, Indirasagar, Karjan and Chamera Stage I. This data would be of
Key words:
INTRODUCTION
At independence, in 1947, there were fewer than 300 large dams in India. By
the year 2000 the number had grown to over 4000, more than half of them built
between 1971 and 1989. India ranks third in the world in dam building, after US and
China. Spillway is an important structure of the dam. In many dams heights are in
excess of 100 m leading to velocities exceeding 30 m/s. Thus, the spillways for these
surfaces are created due to separation of high velocity flows leading to cavitation
Therefore, aerators are provided to supply the air underneath the flow along the
the two to lift the jet from the floor and an aeration duct to supply the air in the cavity
so created below the jet. A groove is used in conjunction with an upstream ramp and
/or a downstream offset or step, so that the bottom spray of the high velocity jet does
not impact within the confines of the groove and thereby some of its air conductance
capacity. Continuity of airflow in the duct requires a continuous supply of air to the
space beneath the nappe. The head losses in the side duct together with the
pressure change caused by the velocity change in the main duct result in the space
under the nappe being at a variable sub atmospheric pressure. The aerator
geometry produces a jet which lifts the water nappe from the floor. The nappe
reattaches on the downstream creating a cavity just downstream of the aerator. This
cavity is connected to the air supply system. The size of cavity is a function of the
incoming Froude number and depends on the geometry of the aerator. A typical
curve for a Froude no. is shown in Fig.1. The area of air supplying duct also controls
the air supply. Various curves for increasing duct area are also shown in Fig. 1. The
intersection of the two curves is the solution or the working point of an aerator
geometry and air supply system. Estimation of cavity sub pressure a priori is difficult.
work. Thus, the functioning of the aerator is the combination of aerator demand
designer always takes recourse to the existing designs of the aerator in planning.
The feedback from the prototype performance suggests the changes to be made in
the future design. Thus, access to the data of the existing aerator geometries gains
importance. This paper highlights the design features of the existing aerators on the
The design of each of the aerator is different depending on the site conditions.
Sardar Sarovar Project is located on river Narmada in the state of Gujarat. This is
the terminal structure in the Narmada Basin Development Scheme. The project
consists of a 163 m high and 1210 m long concrete gravity dam, two power houses
generating 1450 MW, and a 458 km long canal with 38 branches. The dam is
provided with a 30 span spillway of width 18.3 m each separated by 4.7 m thick
piers and equipped with radial gates 18.3 m X 14.7 m. The service spillway of 23
spans has a sloping – cum- horizontal stilling basin as energy dissipater and the 7
span auxiliary spillway has two chutes terminating in to ski- jump buckets. Figures 2,
Sarovar spillway. Aerator for the service spillway consists of an aeration groove of
2.45 m X 2.45 m with a ramp angle of 40 and ramp height of 0.4 m. The aerators in
cavitation index and the availability of the straight length along the glacis between
the tangent point of the crest curvature and the tangent point of the lower circular
The aerators were staggered to accommodate the air ducts in the divide
walls. Due to the staggered positions of the aerators in adjacent bays, the air intake
towers are placed just adjacent to each other, one opening in either bays. Air intake
towers are provided in the adjacent divide walls of the spillway. The intake of the
tower is provided with smooth bell mouth entries to minimize the head losses. The
one meter walk way in the aeration groove was provided for inspection. A slope of
1:1.358 was provided to connect the walk way with the original slope of 1:06 to the
spillway and to facilitate self draining of the groove. Figure 5 shows the details of
both the service and the auxiliary spillway to ensure the performance of the aerators
and to improve upon their designs. The model studies were required to ensure that
the aeration grooves are not filled up with water, the formation of jet trajectory is
satisfactory under all discharges and no undesirable flow conditions develop where
the jet impinges on the downstream side. Model studies for the aerator were
conducted for the entire range of discharges ranging from discharge intensities of 25,
45, 135 and 145 cumec/m .The effect of completely closing the mouth of the air
intake towers; thereby stopping the air supply was also studied.
The ramp angle of 2.50 of the original design of aerator for service spillway
was found to be inadequate. Three ramp angles of 4, 5, and 6 degrees were studied
and angle of 40 was found to be suitable. It was observed that the performance of the
aerator was satisfactory for all the discharges. The jet trajectory was formed and the
jet was impinging down stream of the aerator without filling the aerator for any of the
discharges. The length of the jet was found to be between 18 to 22 m for various
discharges. Piezometers were installed on the spillway surface to insure the jet
length. A sudden rise in the pressure on the spillway surface was observed due to
impact of the jet. It was suggested that the location of the aerators and the
connecting air intake towers for each of the 5 bays of the spillway should be
divide wall.
The aerators for the lower chute of the auxiliary spillway consisted of a ramp
of 0.7 m with a ramp angle of 60 at El. 63.5 m and another aerator at El. 51.9 m with
a ramp angle of 50 and height 0.6 m. Sample calculation for the aerator of lower
chute spillway is attached as annexure for reference. The aerators of higher chute of
auxiliary spillway consisted of a ramp of 60 and height 0.7 m located at two locations
at El. 75.24 m and El. 67.74 m respectively. It is important to note that since the
slope of the auxiliary spillway was flatter, higher ramp heights and thereby larger
ramp angles were required. Model studies for the auxiliary spillway were conducted
for both upper and lower chute. The lower chute spillway would be operated only
when the inflow discharge exceeds the capacity of the service spillway at FRL.
Therefore, it was observed on the model that with the partial gate operation of the
lower chute spillway, the flow cascades over the lip of the ski jump bucket and
hydraulic jump forms in the bucket region. Due to this the water level heads up and
gradually closes the lower aeration groove making it ineffective. It was feared that
instead of mitigating cavitation the groove itself will act as a cavitating machine.
Therefore, it was suggested that the lower aeration groove could be dispersed with.
cavitation index along the entire length of the spillway up to the ski jump bucket for
all the discharge intensities was higher than 0.2. Also, considering the frequency of
the operation of the upper chute spillway, it was found that there is no need of
providing any aerator for the upper chute. The performance of the upper aerator was
Fig. 6: Details of the aerators for the lower chute auxiliary spillway
The aerators needed special attention during construction stages. The top ends of
the divide walls were modified to form fan shape nappe over the partly constructed
blocks. No damage to the ramp or the air ducts have been observed when the water
was passed over the partly constructed spillway blocks. The dam has been
constructed up to the crest El. 121.92 m and the performance of the aerator for the
completed stage of spillway is awaited. Photos 1 shows the view of the aerator on
AERATORS
Tehri dam project consists of a 260.5 m high earth and rockfill dam with three
spillways and a power house complex with generation capacity of 1000 MW. The
three spillways are one chute spillway and two shaft spillways with the crest at El.
815 m, El. 815 m and El. 830.2 m and discharging capacity of 5500, 3650 and 3850
m3/s respectively. The FRL and MWL are at El. 830 m and 835 m respectively. The
chute spillway consists of 3 bays of 10.5 m width each with crest at El 815 m. The
spillway is 718 m long with a fall of 234 m. Due to the long length of the chute one
aerator would not have been sufficient, as the air supplied by one aerator would
detrain. Three aerators have been provided at El. 773.16 m, El. 731.05 m and El.
678.42 m respectively. The aerators are in the form of ramp of heights 0.2, 0.15 and
0.1 m respectively and an aeration groove connected with gallery which opens
downstream of the ramp with openings of size 1.5 m x 1.5 m. Figure 7 shows the
plan and cross section of the spillway with location and details of the aerators. Photo
2 shows the view of the chute spillway showing aerators at three locations.
The dam has since been completed and power generation has started.
However, the reservoir has not been filled up to FRL and the spillways have not
AERATORS
Photo 2: Downstream view of the chute spillway with the three aerators
Fig. 7: Plan and cross section of the Chute spillway showing aerators
Indira Sagar Dam Project is located on river Narmada in East Nimar district.
The dam is a 92 m high concrete and 653 m long gravity dam. The spillway consists
of 20 spans of size 20 m x 17 m. with the crest at El. 245.13 m. The FRL/ MWL are
at El. 263.36 and El. 262.13 m respectively. The spillway has been provided with
roller bucket as energy dissipater. Since the length of the spillway to be protected is
short only one aerator has been provided at El. 225.97 m at the end of the pier in
the form of a 1.2 m high ramp. A wedge of 0.6 m has been provided on either side in
plan adjacent to piers to deflect the jet towards centre of span for allowing aeration
from the sides and in the wake of the piers. This is a very convenient location which
does not need any separate air duct system. Figures 8 and 9 show the plan and
section of the spillway with details of the aerator. Photo 3 shows the view of the
spillway passing discharge. The dam has been commissioned in 2006. The aerators
spillway with crest at El 101.23 m has been provided to discharge a design flood of
17,275 cumec. The FRL and MWL are at El 115.25 m and 116.10 m respectively.
There are 9 spans of size 15.55 m x 14.02 m for passing the design flood. A stilling
basin with horizontal apron has been provided for energy dissipation. An aerator in
the form of a 0.56 m high ramp, a groove of size 1.4 m x 1.4 m and an aeration
gallery of size 2.5 m x 3.75 m has been provided at El 63.5m .The ramp angle is
80.The ramp angle and the groove height seem to be little high for the steep slope of
the spillway and there is a possibility of jet trajectory crossing the spillway glacis and
falling in the stilling basin for some discharges. The aeration groove could have
been provided little higher on the spillway glacis, so that more length could have
been protected. Figures 10 and 11 show the section of the spillway and the details
of aeration groove respectively. Photos 4 and 5 show the view of the spillway under
The dam has been completed in 1991 and the spillway has been functioning since
then. No cavitation damage has been observed on the spillway glacis. Photos 4 and
AERATOR
The Chamera H.E. Project, Stage – I is the downstream most project in the cascades
on the river Ravi. It is a 125 m high concrete gravity dam with breast wall spillway. The
provided with openings at 32.5 m below FRL El. 762.5 m with breast walls and a ski-jump
bucket is provided for energy dissipation. The aeration groove is provided in the form of a
groove and connected with a duct in the pier. No ramp or air gallery has been provided.
Figures 12 and 13 show the plan and section of the spillway with the aeration groove.
The project was constructed during 1987 to 1993 and commissioned in the year
No cavitation damage has been observed on the spillway glacis. Hence the performance of
CONCLUSIONS
data for planning. Fine tuning of the design is done with the help of model studies.
This paper has highlighted the design features of the aerators on five existing
projects in India.
ACKNOLWDEGMENTS
The authors are thankful to Mrs. V.M. Bendre, Director, Central Water and
Power Research station for her encouragement and valuable suggestions given
during the preparation of this paper. The authors are thankful to various project
authorities for referring the model studies to CWPRS, participating in discussions for
finalizing the design of aerators and arranging site visits. The guidance given by the
Shri S.P. Sen, Director, NHPC and discussions with officers from NHPC, THDC,
References
Publication.
2. CWPRS Technical report 1993 ,” Hydraulic model studies for design of aeration
grooves on spillway”
Annexure
Data:
No. of spans : 4
Span width : 18.3 m
Thickness of pier : 4.7 m
Width at toe : 87.3 m
Design max. Discharge : 11,785 m3/s
Max. Water level : 140.2 m
H= 140.2-63.5= 76.7 m
⎡ ⎤
36 × 0.1019 ⎢ 2 × 0.188 × 0.9946 ⎥
= 1+ 1+
0.9946 ⎢ ⎥
⎢⎣ (0.1019 × 6)2 ⎥⎦
= 8.9
Calculate βmax. = 0.03(λmax-5)
= 0.117
Calculate Emin =
10 3
2.3
( )
(tan θ )1.15 exp 1.15(tan α )2
Emin =
10 3
2.3
(
(tan 0.1047 )1.15 exp 1.15(tan 5.95)2 )
=33
Qair =10 X W
= 10X87.3
= 873 m3/s
qw
Fq =
(
g H 11.5 )
135
=
(
9.81 76.71.5 ) =0.064
Qa
β= = 895/11785= 0.076
Qw
⎡ 1
⎤
3
π β
⎛ ⎞
tan ⎢ ⎜⎜ a ⎟⎟ ⎥ = 378
10 0 .7
Calculate ∆E =
3 ⎢ 2 ⎝ β max ⎠ ⎥
⎣⎢ ⎦⎥
E = Emin+∆E
= 33 + 378 = 411
Calculate average atmospheric pressure below the jet
− 2
V
∆ p = ρ w w = 0.088
E
Calculate air velocity in the duct
∆p × 2 gd × ρ w
Va =
0.43(1 + 2ξ tot ) × ρ a
= 76.6 m/s
Number of air ducts = 2
1 Q
Area of each duct = × a
2 Qw
1 895
= × = 5.84 m2
2 76.6
say 6 m2