WELTEK LIMITED
nedoge)
CLASSIFICATION: RESTRICTED
PROJECT TITLE:
NEDO GAS PLANT EXPANSION PROJECT
DOCUMENT TITLE :
After Action Review
REVISION RECORD
Revision |Date Issued | Date Revised Review by:
Rot, | 17/40/2023 18/10/2023 Mercy Matthew | Chuma Maduka
REVISION STATUS APPROVAL
Page Total
{incl. cover) oFNEDO GAS PLANT EXPANSION PROJECT
Document Tittle: After Action Review
Project Scope
‘The Project scope covered the following.
Review of Engineering Drawings, Equipment drawings and other documentation issued.
Carry out site to identify tie-in points on equipment and on the pif
Planning schedules and Programs covering all aspects of work.
ing networks.
Fabrication of all spools as required.
Installation of all pipes, valves and fitings as required.
Carry out NDT for welded joint (RT).
Constructs and installs pipes support.
Internal cleaning and hydrotest of welded spools
Painting installed pipe supports.
Nitrogen purging and preservation
What We Expected to Happen
A stakeholders’ meeting should be held to review the contract and the agreement before.
mobilization to site.
Petra Services Limited (PSL) is expected to send all documents regarding the project to
Weltek and they should be informed of any direct communication between the client and
PSL.
Weltek expects all supervisors especially the QC Inspectors to be present when major
activities like welding are being executed on-site.
Weltek expects that all standard procedures will be followed as ini
documents.
\Weltek expects proper implementation of HSSE p.
What Happened
Stakeholders’ meetings were not held.
Petra Services Limited sent all documents to the client and excluded Weltek from every
direct communication.
Weltek representatives at site were initially not carried along with some decisions at site,
until it was escalated to the Top Management before this was corrected,
There was a work shutdown on-site because of a delay in financial transactions.
2|PagePLANT EXPANSION PROJECT
le: Afier Action Review
Conclusion
‘The team was able to execute the project successfully regardless of the limitations experienced
during the project and no workplace accident was recorded on site.
Action Points
Project should start with a kickoff meeting.
‘Trust should be established between the Petra Service Limited and Weltek Limited,
Use of proper Documents, Drawings (DED, P&ID etc..), and Weightage to know the
percentage of work done on site,
wat ropmnrtaivel Pn N\cfter Petra Representati
Signature:
Signature:
vas 2 3f ofS Date:
3|Page