Progress Reporting Plan
Progress Reporting Plan
TOCHUKWU.
0 25.10.17 PRESENTED FOR BID THEO. O C.NNADI
O.
enak
ENAK Document Number Rev
ENAK/NAOC/CCPR/TECH BID/PEP
0
Project Management
Document No.
0
CLOUGH CREEK PLATFORM
REFURBISHMENT
PROGRESS REPORTING PLAN
enak E n e r g y S e r v ic e s L td .
Document ENAK/NAOC/CRPR/TECH
Number BID/PRP
Document Type : TECHNICAL TENDER Date : 27 /10/ 2017
TABLE OF CONTENTS
1. GENERAL...................................................................................................................................................... 5
1.1 DEFINITION...................................................................................................................................... 5
1.2 REFERENCE DOCUMENTS............................................................................................................ 5
1.3 PURPOSE......................................................................................................................................... 5
1.4 RANGE OF APPLICATION.............................................................................................................. 5
1.5 RESPONSIBILITY............................................................................................................................. 5
2. INTERNAL REPORTING............................................................................................................................... 6
3. REPORTING TO COMPANY......................................................................................................................... 6
Document ENAK/NAOC/CRPR/TECH
Number BID/PRP
Document Type : TECHNICAL TENDER Date : 27 /10/ 2017
Document ENAK/NAOC/CRPR/TECH
Number BID/PRP
Document Type : TECHNICAL TENDER Date : 27 /10/ 2017
1. GENERAL
1.1 DEFINITION
CONTRACTOR: means EESL – ENAK ENERGY SERVICES LIMITED that has been
awarded the CONTRACT by COMPANY.
Project Calendar
1.2 PURPOSE
The purpose of this procedure is to define the rules and methods to be used for reporting during
the CONTRACT.
Engineering
Procurement
Prefabrication
Installation
Pre-commissioning
1.4 RESPONSIBILITY
The Planning and Reporting Manager is in charge to collect the reports of each discipline
managers and to compile data to issue reports to COMPANY.
CLOUGH CREEK PLATFORM
REFURBISHMENT
PROGRESS REPORTING PLAN
enakE n e r g y S e r v ic e s L td .
Document ENAK/NAOC/CRPR/TECH
Number BID/PRP
Document Type : TECHNICAL TENDER Date : 27 /10/ 2017
The managers who have to issue an internal weekly report during the relevant phases of the
project are:
2. INTERNAL REPORTING
Internal reports are issued on a weekly basis. Each manager issues his weekly report to the Planning
and Reporting Manager on Monday after the cut-off date before 12.00 AM.
During Offshore works, the Construction Manager and the Pre Commissioning Manager issue a daily
report.
3. REPORTING TO COMPANY
Monthly reports are issued to be received by COMPANY at the latest on Wednesday morning
after the monthly Cut-Off date detailed in the Project Calendar.
HSE
QA/QC
Organization
POB
Project Control – Document Control
Project Control – Progress
Project Control – Planning
Areas of Concern
3.1.2 ENGINEERING
CLOUGH CREEK PLATFORM
REFURBISHMENT
PROGRESS REPORTING PLAN
enakE n e r g y S e r v ic e s L td .
Document ENAK/NAOC/CRPR/TECH
Number BID/PRP
Document Type : TECHNICAL TENDER Date : 27 /10/ 2017
General
Activities this month
Activities next month
General
Activities this month
Activities next month
General
Activities this month
Activities next month
General
Activities this month
Activities next month
General
Activities this month
Activities next month
General
Activities this month
Activities next month
3.1.8 CONTRACT
3.1.11 ATTACHEMENTS
Document ENAK/NAOC/CRPR/TECH
Number BID/PRP
Document Type : TECHNICAL TENDER Date : 27 /10/ 2017
3.2.1 GENERAL
A narrative on achievements, activities planned for the coming period, critical activities,
and areas of concern.
A statement of actual versus planned progress achieved and major drawings and
documents issued per area and discipline (as a percentage and in a narrative form).
A Technical Queries follow up.
A statement on VENDOR drawings received and approved and outstanding items.
A narrative on achievements, activities planned for the coming period, critical activities,
and areas of concern.
A statement of purchasing status, expediting status, inspection status and shipping
status per category of equipment or materials for the week, actual versus planned.
Document ENAK/NAOC/CRPR/TECH
Number BID/PRP
Document Type : TECHNICAL TENDER Date : 27 /10/ 2017
A narrative on achievements, activities planned for the following period, and areas of
concern.
CONTRACTOR emits daily logs for COMPANY during activities at WORKSHOPS and during
SITE operations such as:
CONTRACTOR emits daily logs for COMPANY during activities at WORKSHOPS and during
SITE operations such as:
Document ENAK/NAOC/CRPR/TECH
Number BID/PRP
Document Type : TECHNICAL TENDER Date : 27 /10/ 2017
CONTRACTOR provides the following reporting attachments as part of the Project Status Reports:
In addition to the MDR, CONTRACTOR prepares, issues and weekly updates a Document
Status Report of all design and Engineering documents (e.g., drawings, specifications, data
sheets, material requisitions and the like) to be produced for the WORK.
The Document Status Report shows the following data:
CONTRACTOR prepares issues and weekly updates a Procurement Status Report in the
form of a control log for all planned and actual purchases necessary for the WORK
throughout the CONTRACT duration.
The Procurement Status Report shows as a minimum the following data:
Requisition
o Number and title
o Criticality level
o Actual date of issue
Call for Tenders
o Number
CLOUGH CREEK PLATFORM
REFURBISHMENT
PROGRESS REPORTING PLAN
enakE n e r g y S e r v ic e s L td .
Document ENAK/NAOC/CRPR/TECH
Number BID/PRP
Document Type : TECHNICAL TENDER Date : 27 /10/ 2017
CONTRACTOR prepares, issues and regularly updates Four (4) Week Look Ahead
Inspection Programs indicating the confirmed inspection dates for the first two (2) weeks,
and inspections planned for the further two (2) weeks. The following information is given:
WORKSHOP / WORKSITE location where inspection shall take place with address and
contact
Date of inspection and probable duration
Purpose of inspection
CONTRACTOR prepares, issues and regularly update a Shipping and Delivery Report to
include:
PO number
Equipment or material description
Item number
Quantity
Shipping departure date
Means of transport
Exchange Control Number
Intermediate dates (location of, and departure date from port or airport of embarkation,
location of, and arrival at port or airport of disembarkation, date customs cleared, etc.)
Planned delivery date on WORKSITE and/or SITE
Required delivery date on WORKSITE and/or SITE in line with the time schedule
Actual delivery date on WORKSITE and/or SITE
CLOUGH CREEK PLATFORM
REFURBISHMENT
PROGRESS REPORTING PLAN
enak
E n e r g y S e r v ic e s L td .
Document ENAK/NAOC/CRPR/TECH
Number BID/PRP
Document Type : TECHNICAL TENDER Date : 27 /10/ 2017
The weekly progress report gives the overall progress for the considered week.
The monthly progress report is given through the progress report excel file. This report
calculated at cut-off date includes: