Professional Documents
Culture Documents
Fig. 1.1 The state of stress in an elastic half space subjected to a point load at the surface
To develop the fundamental equations for the stresses induced, Boussinesq idealised
the medium as a half space (i.e an infinitely large area with infinite depth) with elastic,
homogenous and isotropic properties. The stresses at any point within the medium due
to a point load P at the surface are given by the following equations:
kP 3P
z (1.1)
z2 r 2
5/ 2
2z 2 1
z
P 3x 2 z x2 y2 y 2 z
x 1 2 2
3 2 (1.2)
2 R 5 Rr R z R r
P 3y2z y2 x2 x 2 z
y 5 1 2 2 3 2 (1.3)
2 R Rr R z R r
1
It is evident from the above equations that the induced vertical stress (z) in the elastic
half space is independent of the properties of the transmitting medium.
On any horizontal plane (i.e. at a given depth), the vertical stress distribution has a
bell-shaped surface with maximum stresses occurring on the vertical plane passing
through the point of load application (see Fig. 1.2 below).
z
Fig. 1.2 Stress distribution on a horizontal plane in a loaded elastic half space
The distribution of vertical stress on any vertical plane has the following characteristic
profile (Fig 1.3).
0
Fig. 1.3 Stress distribution in an elastic half space subjected to point loading at the surface
It is clear from the above figure that the vertical stress is maximum at the surface and
theoretically reduces in intensity to zero at infinite depth although for practical
purposes it can be assumed to approach zero at a finite depth.
2
Fig. 1.4 An elastic half space with a uniform surface load
Fig.1.4 above shows a uniformly loaded half space with the uniform load applied over
a circular area whose radius is a. If the contact stress (uniform pressure) applied on the
surface is o then the stresses and strains at depth z directly below the centre of the
loaded area where stresses () and strains ( ) are maximum are given by the following
equations:
1
1 (1.4)
z 0
1 (a / z ) 2 3 / .2
o 2 z 1 z3
x y r 1 2 2 (1.5)
2 a z2 1/ 2
a2 z2 3/ 2
0 (1 ) z/a z/a
. z (1 2 ) 1 ( 1.6)
E
1 ( z / a ) 2
3/ 2
1 ( z / a)
2 1/ 2
1 1
r ( z E z ) z (1.7)
E 2
Note that because of the circular nature of the loaded area, the radial stress (x) is the
same as the tangential stress (y).
The maximum total elastic surface deformation (Δ )or deflection which occurs at the
centre of the loaded area is given by the following equation.
2 o a
E
1 2 (1.8)
3
where E=elastic modulus of the medium
μ=Poisson’s ratio.
In the general case of an N-layer system, the stress-strain conditions may be examined
by making the following simplifying assumptions:
a. Two-layer structure
A two-layer system represents the simplest form of a multi-layer system. The state of
stress in a two-layer system was examined by Burmister and the results may be used to
provide an insight into the state of stress and strains in a general multi-layer pavement
structure. In practical terms, a two-layer structure is exemplified by a full-depth gravel
pavement (i.e. a layer of gravel material lying on a subgrade) or a full-depth asphalt
pavement.
4
o
0 1 2 o
h1 E1 E1
2
z=h1
E2 5 E2
sub-grade
z
(a) Uniformly loaded two-layer system (b) Stress distribution under the centre of loaded area
Fig. 1.6 Influence of strength ratio on distress distribution in a two-layer pavement structure
In the general case where Layer 2 is the subgrade and Layer 1 a uniform pavement
structure, it is seen that the stress on the sub-grade (interface stress) due to a given
surface load intensity can be reduced considerably by choosing the pavement material
to have high strength relative to that of the subgrade material (i.e. a high E1/E2 ratio).
This forms the rationale for building a flexible pavement as a multi-layered structure
with high quality materials in the upper layers. In addition, because the stress
distribution shows decreasing intensity with increasing depth, subgrade stresses are
also reduced considerably by building thicker layers.
Fig. 1.7 may be used to evaluate the vertical compressive stress on top of the sub-grade
for any two-layer pavement structure with known material properties. The figure may
also be used to establish the thickness of the full-depth pavement that will satisfy a
limiting vertical compressive stress criterion.
5
Fig. 1.7 Vertical interface stresses for two-layer systems (after Huang)
In this case, when it is assumed that =0.5, the total elastic deformation at the surface
is given as:
1.5 o a 2
(1.9)
E a2 z2 1/ 2
6
where E=modulus of the subgrade.
The development of the above equation assumes that the deflections registered on a
pavement surface are all due to the deformation within the subgrade from depth z to
infinity and none within the pavement structure itself, i.e.,
=p+s=s (1.10)
where,
=total surface deflection
p=deflection within pavement (=0)
s=deflection within the sub-grade from depth z to infinity
This is not strictly true because some component of the total deformation comes from
the pavement layer(s). However, because of the stress distribution properties of the
stronger pavement material, the actual deflections beneath a road pavement are usually
smaller than the theoretical deflections in the subgrade.
To take into account the reinforcing effect of the pavement on surface deflections the
following equation was provided by Burmister.
1.5 o a
F2 (1.11)
E2
where F2 is a dimensionless factor dependent on strength ratio as well as depth/radius
ratio of the pavement (see Fig. 1.9).
Fig. 1.9 Influence values for deflections in a two-layer system (after Burmister)
7
b. General multi-layer structure
In a more general case, an N-layer structure (typified by a three-layer structure) will
have the following states of stress at the various interfaces that may be of interest to
evaluate.
o
In the analysis of the state of stress in a multi-layer pavement structure, the magnitude
of the compressive stress on top of the subgrade is of paramount importance and
concern as this has the potential to cause shear failure in the subgrade. In addition, for
pavements with an asphalt concrete layer, it is also important to evaluate the tensile
strain at the bottom of the asphalt layer as this has the potential to cause fracture failure
in the form of cracking which will propagate to the surface.
3
h 3 E h 3 E
E 1 1 2 2 (1.12)
e h h
1 2
8
a material having a thickness equal to the combined thickness of the layers and having
an equivalent modulus given as
3
N 1 3
hi Ei
Ee , N 1 i 1N 1 (1.13)
i 1
hi
With the method of equivalent modulus, it is tacitly assumed that all the different layer
materials have the same Poisson’s ratio. It must be noted that this methods is incapable
of transforming a multi-layer structure into an elastic half space. However, if desired,
the resulting two-layer structure may be reduced to an elastic half space by applying
the method of equivalent thickness which follows in the next section.
The basic assumption underlying the method of equivalent thickness is that the stresses,
strains and deflections developed in a multi-layer structure below a particular layer
will be unaffected by changes in the layer provided its flexural stiffness remains
constant. The flexural stiffness of a layer is given by (E I)/(1 – µ 2) where E is the
elastic modulus, I is the second moment area or moment of inertia of the layer (its
value depends on h3, h is layer thickness) and µ is Poisson’s ratio.
E A h A3 E B h B3
(1 A2 ) (1 B2 )
By means of the above expression the thickness (hB) of new material required to
replace what was existing can be evaluated. This thickness is called the equivalent
thickness. Consider a two layer structure as shown in Fig. 1.11 (a) which is to be
transformed into a single layer or an elastic half space.
he2
h1
E1, µ 1 E2 , µ 2
E2 , µ 2 E2 , µ 2
(a) (b)
E1h13 E2 he32
(1.14)
(1 12 ) (1 22 )
E1 1 12
he 2 h
13
2
(1.15)
E 2 1 2
If the value of Poisson’s ratio is the same for Layer 1 and Layer 2, Equation (1.15)
reduces to
E
h e2 h1 3
1
E 2
Even though the transformation shown in Fig. 1.11 (b) appears to have resulted in two
layers, in principle the resulting structure is a one layer structure since the material in
the equivalent layer (new upper layer) has the same elastic properties as the material in
Layer 2. Hence in effect there is only one layer which extends to infinity in depth (an
elastic half space).
The values of the stresses and strains at the lower side of the interface are obtained by
applying the Boussinesq equations to a semi-infinite space at a depth z=he below the
surface.
E1 1 22 E 2 1 32
he3 h2 h1 3 3 (1.16)
1 1 E 3 1 2
2 2
E2
10
Structures having more layers may be treated by applying this procedure
progressively. In a general n-layer structure, the equivalent thickness of the (n-1)
layers above Layer n (sub-grade) may be calculated from the expression
i n 1 Ei 1 n2
he,n f hi
3
2
(1.17)
i 1 En 1 i
where f=correction factor generally taken as 0.8 employed to give better agreement
between the values derived by the approximate method and those by exact elastic
theory. Equation (1.17) may be simplified if the Poisson ratio is taken as the same in
all the layers.
The method of equivalent thickness and the Boussinesq equations must be used to
evaluate stresses and strains at the lower side of the interface only as the calculations
apply to the assumed semi-infinite space. From considerations of continuity the
vertical stress (and likewise the horizontal strain) on both sides of each interface are
equal in value. Radial stresses and vertical strains at the upper side of an interface can
be evaluated from those on the lower side and the conditions of continuity using the
equations for three-dimensional stress and strain based on the generalised Hook’s law
which may be written as
z
1
E
z ( x y ) (1.18)
11
2 Stresses in Rigid Pavements
2.1 Introduction
Stresses in rigid pavements may result from
1. Wheel loads
2. Changes in temperature
3. Volumetric changes in subgrade.
These changes tend to deform the concrete slab causing stresses of widely varying
intensity to develop. Since the modulus of elasticity of concrete is much greater than
that of the foundation soil, a major portion of these stresses are carried by the concrete
slab itself through what is known as “beam action”. This behaviour may be explained
in an approximate way by considering the stress distribution characteristic as if it were
the case of a two-layer flexible pavement structure for which the reinforcing pavement
material ( in this case the rigid slab) overlying the sub-grade has a very high elastic
modulus such that E1/E2 is extremely high.
Consider a finite slab of dimensions shown in Fig. 2.2 in which curling stresses have
developed.
y
Ly x
Lx
Fig. 2.2 A finite rigid slab
12
The curling stresses in the X and Y directions are given by the following equations:
Et
x
2(1 2 )
C x C y (2.1)
and
Et
y
2(1 2 )
C y C x (2.2)
where
E= modulus of elasticity of concrete
t= temperature difference between surface and bottom of slab
= coefficient of thermal expansion
= Poisson’s ratio
Cx, Cy are correction factors (see Fig. 2.3) dependent on Lx/l or Ly/l where l is the
radius of relative stiffness of the slab given by the expression
1/ 4
Eh3
l (2.3)
12(1 )k
2
Curling stresses at the slab edges are obtained by putting =0 in the corresponding
stress equation. For example, in the y-direction
13
Et
edge ( y ) Cy
2
The modulus is then evaluated as the slope of the pressure (P)-deflection () curve i.e.
P
k
The stress and deflection developed due to loading at the corner of a rigid slab are
respectively given by the following expressions;
14
3P a 2
0 .6
c 2 1 (2.4)
h l
P a 2
C 2 1.1 0.88 (2.5)
kl l
where
c =corner stress
C = corner deflection
a = contact radius of load P
3(1 ) P l
i (ln 0.6159) (2.6)
2h 2
b
where,
b = a when a 1.724h
b 1.6a 2 h 0.675h.......when.....a 1.724h
P 1 a a
2
i 1 ln 0.673 (2.7)
8kl 2 2 2l l
0.803P l a
e 4 log 0.666 0.034 (2.8)
2
h a l
0.431P a
e 1 0.82 (2.9)
l
2
kl
15
grade, friction stresses will develop which in long slabs may be sufficient to cause
cracks. Stresses due to friction are evaluated thus
C Lf
C a
(2.10)
2
where
C = unit weight of concrete
L= length of slab
fa= friction coefficient between underside of slab and subgrade (fa=1.5 )
L1
tie bars
L2
direction of travel
2.5.1 Reinforcement
It is assumed that all the tensile stresses from friction force are taken up by the steel
alone. The area of steel required per unit width of slab is given as
C hLf
AS a
(2.11)
2 fs
where
AS = area of steel per unit width of slab
fS = allowable steel stress
L = the length of slab for longitudinal reinforcement, or
= the width of slab for transverse reinforcement.
h = the thickness of slab
16
2.5.2 Tie bars
These are placed along the longitudinal joint to tie two adjacent slabs together so that
the joint will be tightly closed to ensure load transfer across it. For tie bars, the area of
steel required is given by
C hL 1 f a
AS (2.12)
fS
where,
L1 = the lane width.
For a given area of steel, it is advisable to choose the smallest size bars.
The length of tie bar is governed by the allowable bond stress and should be based on
the full strength of the bar i.e.
fS d
t 1
b
2
2.5.3 Dowels
Dowel bars are used across a transverse joint to allow load transfer to the adjoining
slab. One end of the dowel bar is fixed and the other end into the adjoining slab is
lubricated to allow for expansion across the joint. Lubrication may be achieved by
wrapping the end to be lubricated in a sheath of polythene material. The following
table sets the recommended dowel sizes and length depending on slab thickness.
Slab thickness ,h, inches (cm) Dowel diameter Dowel length -inches (cm)
5 (13) 12 (30)
6 (15) 14 (36)
7 (18) 14 (36)
h
8 (20) 14 (36)
8
9 (23) 16 (40)
10 (25) 18 (48)
11 (28) 18 (48)
12 (30) 20 (50)
Note that 1inch= 25 mm and dowels are to be spaced 30cm (12 inches) on centres.
17
3 Structural Design of Flexible Highway Pavements
3.2.1 Traffic
Traffic on highway facilities varies in the number of vehicles and vehicle types.
Vehicles may also vary in the number and configuration of axles and the magnitude of
the loads on the axles. Each of the different types of vehicles or categories of vehicles
such as private cars, buses, rigid trucks and articulated trucks, etc. within a given
traffic stream is weighted differently in terms of the structural damage they cause to a
pavement. For the purposes of the structural design of flexible pavements, only
commercial vehicles (vehicles whose un-laden weight is 1500kg or more) and the
magnitude of the loads on their axles are of interest. Vehicles with un-laden weights
below 1500kg cause no significant structural damage to pavements and are, therefore,
ignored in routine traffic analysis for pavement design.
Fig. 3.1 provides the different types of commercial vehicle axle configuration that are
likely to be encountered on any roadway. The volume and nature of commercial
vehicles using or expected to use a highway facility may be expressed in a number of
ways depending on the level of detail required or the details of traffic flow and vehicles
that are available. Traffic data on commercial vehicles may be expressed in one of the
following forms in order of increasing level of detail or accuracy:
number of commercial vehicles
number of commercial vehicles by type
number of commercial vehicle by axle configuration
number of commercial axles by type and load on the axle
18
AXLE CONFIGURATION
RIGID TRUCK
(2 AXLES)
2 2
RIGID TRUCK
(2 AXLES)
2 4
RIGID TRUCK
(3 AXLES)
2 4
ARTICULATED TRUCK
(3 AXLES)
2 4 4
ARTICULATED TRUCK
(NORMAL TANDEM)
[4 AXLES]
2 4 4 4
ARTICULATED TRUCK
(NORMAL TANDEM)
[5 AXLES]
2 4 4 4 4
ARTICULATED TRUCK
(TRIAXLE)
[6 AXLES]
2 4 4 4 4 4
Expressing design traffic in terms of number of commercial axles by type and load on
the axle allows the most reliable estimates of the damaging effect of traffic on
pavements to be made. Except in axle load studies, such form of data is of course
impractical to collect in routine traffic survey for design purposes. On the other hand,
design traffic data in terms of the number of commercial vehicle types is easy to collect
and presupposes that there is adequate information or data on the damaging potential
of the different types of commercial vehicles to permit the total effect of the
anticipated traffic on the pavement in terms of the number of standard axles to be
evaluated. Such data will exist in the form of average load equivalency factors for
commercial vehicles in general, for a given class of road within a given part of the road
network.
L
c
ESAL = (3.1)
8.2
where c is an exponent ranging between 3 and 6, with a value of 4.5 being typical. In Australia, c=4 is
commonly adopted and the standard axle load used as a denominator in Eqn (3.1) varies according to
whether the axle is single with single wheels, or single with dual-tyred wheels, or tandem with dual-
tyred wheels.
Li
n 4 .5
ESAL= (3.3)
i 1 8.2
In spite of the differences in commercial vehicles by way axle configuration type and load on the axles,
it is possible, for the purposes of analysis to place the vehicles into a finite number of commercial
vehicle categories by axle configuration type irrespective of the magnitude of the axle loads. Consider
the case in which a population of N commercial vehicles is placed into M categories. Let the kth
category be made up of Mk vehicles and characterized by Nk single axles per vehicle without due regard
to axle configuration. Assuming that the commercial axles could all be considered single, then the ESAL
per pass of all the commercial vehicles within this category is given as;
L i, j
Mk Nk 4 .5
ESALk= (3.4)
j1 i 1 8.2
The average ESAL per pass of a commercial vehicle (truck factor-TF) within this category, TFk,
therefore, becomes;
L i, j
Mk Nk 4 .5
1
TFk =
M k j1 i 1 8.2
(3.5)
In the case where legal load limits on axles are well respected by commercial vehicle operators within
the trucking industry, large variations in axle loads within a given category are unlikely and TFk as given
by Eqn (3.5) would characterize the structural damage potential of each vehicle within this category
fairly accurately. By extending the above concept to cover all categories of commercial vehicles within
the traffic stream, an equivalency factor may be obtained that applies to any commercial vehicle
irrespective of axle configurations and loads. Thus based on the commercial vehicle population and
categories above, TF applicable to any commercial vehicle within the population is evaluated thus;
L i , j, k
4 .5
M Mk Nk
1
TF= (3.6)
N k 1 j1 i 1 8.2
The accuracy of the above expression for the truck factor is further enhanced if the
evaluation is based on a large sample of data collected over a substantial part of the
road network and over a fairly long period of time. Such equivalency factors are useful
20
parameters for estimating the ESAL for design on the basis of just the estimates of
number of commercial vehicles without necessarily knowing the type or category of
commercial vehicle nor the magnitude of the loads on the axles.
ESALo n TF
k
k k (3.7)
It is important to know at the onset that for a multi-lane carriageway, traffic on the
most heavily-travelled lane is what is used for design. For a single carriageway with
opposing traffic, there must be simultaneous traffic data collection for the two
directions of travel in order to establish the lane that carries the higher traffic and hence
the design traffic. Once the number of equivalent standard axles corresponding to the
average daily commercial traffic for the design lane has been evaluated, the cumulative
number of standard axles for the first year is obtained by aggregating the daily value
over 365 days
The cumulative number of standard axles, ESALcum, expected during the design life of
the pavement is obtained by taking into account the traffic growth during the design
period. Given a traffic growth rate of r% per annum and a design life of n years, the
traffic growth during the design period is taken care of by a parameter called the traffic
growth factor, G, which is given by the following expression.
n n
r r
1 100 1 1 100 1
G (3.8)
r r
ln 1
100 100
The traffic growth factor is then applied to the first year number of standard axles to
obtain the cumulative number of standard axles for design ESALcum , i.e.,
Numerical example
Due to the natural variability of soils deposits, the strength of the sub-grade will vary
along the road alignment. This means that several and different CBR values will be
obtained from the strength investigation along the proposed route. Depending on the
value selected for analysis purpose, the design can represent under-design or over-
design. If the average value is selected, about one half of the road is over-designed and
one half under-designed. If the mini mum value is selected most of the road section is
over-designed. Some level of risk must be taken in the selection of the CBR for
design. Since the sensitivity of sub-grade strength increases as traffic increases, the
design sub-grade CBR value is selected on the basis of the anticipated traffic levels; a
higher percentile value must be selected for higher traffic to minimise the risk of
failure. When this approach is adopted, then at high traffic levels, the design sub-grade
CBR approaches the minimum CBR value. The table below (Table 3.1) provides a
guide to the selection of design sub-grade CBR based on traffic levels.
The following numerical example explains the procedure for determining the design CBR.
22
Numerical Example
The sub-grade CBR values along the alignment of a proposed road which is expected
to carry medium traffic are as follows: 4,6,3,8,12,10,5,7,9,12,14,7. Determine the CBR
for design.
Solution
Step 1
The CBR values must be ranked in ascending order as shown in the table below.
Step 2
Plot Percentile values (column 4) against CBR values (column 1) and obtain a curve
which has the characteristics of half a normal distribution curve or half a bell, similar
to the sketch below.
Percentile
100
50
Xp CBR (%)
Step 3
Select the design percentile value using the design traffic expressed in terms of ESAL
and Table 3.1 as a guide. If P is the percentile value of interest then the corresponding
CBR for design is Xp. Correct this value to the nearest whole number. Since traffic is
23
expected to be medium, P=75 and hence the design CBR value is read as X75 rounded
to the nearest whole number.
For the Poisson’s ratio, the values in Table 3.2 provide a useful guide.
Range of Representative
Type of material values value
Fine-grained sub-grade soils 0.40-0.50 0.45
Granular sub-grade soils 0.25-0.40 0.35
Unbound granular soils 0.25-0.40 0.35
Cement-stabilised granular soils 0.10-0.30 0.20
Bitumen-stabilised granular soils 0.30-0.50 0.40
Asphaltic concrete 0.35-0.50 0.40
24
(AASHTO) design method and the Transport and Road Laboratory (TRL) CBR design
method will be presented here.
SN 1
log ESAL cum 9.36 log 1 0.83 log 1.395 log CBR (3.12)
25.4 R
where,
SN= structural number in mm
CBR=design sub-grade CBR in %
. R=regional adjustment factor with a value =1 for areas with rainfall throughout the
year and value =0.1 for dry and arid conditions, and intermediate values for
intermediate rainfall conditions.
The following equation is then used to relate SN to the to the individual material types
and thickness of the pavement:
SN a1 D1 a2 D2 ...an Dn (3.13)
The data in the table below provides an indication of the magnitude of layer
coefficients for different pavement materials.
25
Table 3.3: Typical layer coefficients for layer materials
Layer/Material Layer
coefficient
Surface course
Hot mix asphalt concrete 0.44
Sand mix asphalt concrete 0.35
Base
Natural gravel (CBR>80%) 0.12
Crushed gravel (CBR>80%) 0.13
Dense graded crushed gravel 0.18
Soil cement 0.20
Hot mix asphalt concrete 0.40
Sub-base
Natural gravel (CBR>30%) 0.11
Crushed stone 0.11
Cement/lime-stabilised materials 0.12
For any given structural number, there is an infinite number of pavement material
combinations and thicknesses that will provide satisfactory service. In view of this,
there are guidelines that can be used to narrow down the number of solutions.
Experience has shown that the wearing layer can be 50 to 100 mm thick while the sub-
base can be 100 to 200mm thick. Because the cost of the construction must be
minimised, a knowledge of which of the materials available is the most costly per unit
thickness will also assist with the solution of an initial layer thickness.
Example
Find the structural geometry of a new pavement that is to be surface-dressed and will
carry an anticipated traffic of 2.5 x106 standard axles over the design life if the design
sub-grade CBR is 20%.
Solution
Traffic class=T4
Sub-grade class =S5
Design chart to use: Chart 1: Granular Road Base/Surface Dressing
4.1 Introduction
The structure of an airport flexible pavement may consist of untreated or treated
(stabilised) granular base overlain by an impervious or waterproofing riding course
much in the same way as with flexible highway pavements. However, it is
recommended that whenever possible, flexible airport pavements must be constructed
as full-depth asphalt pavements as such a construction apart from not entrapping water
which tend to reduce subgrade strength and impair performance is able to spread loads
over a broader area and requires less pavement structure thickness. Several methods for
design of flexible airport pavements exist but the most comprehensive and very recent
is the method by the Asphalt Institute which will be discussed here.
28
The following steps are then followed for the tensile strain and the compressive strain
criteria:
1. Using the mean annual air temperature, select the appropriate graph from the
family of curves relating TA to subgrade modulus and various levels of allowable
repetitions which corresponds to the temperature. This is to be done for each
strain criterion.
2. Using the design subgrade, determine from the selected graph the thickness of
pavement (TA) that will satisfy the strain criterion for the different lines of strain
repetitions shown on the selected graph. The results may be set out in a tabular
form as shown below.
Note that this procedure will produce two tables one for tensile strain criteria and
the other for compressive strain.
3. Develop the allowable traffic, Na , curve for each criterion by plotting the data in
each table on a semi-log graph paper with TA on the arithmetic scale.
1. Draw up a table (Worsheet No. 1) showing the forecast aircraft movements for 5-
year periods up to the design period. For each period, draw up two columns (A and
B) and record under A the forecast traffic movements within the period and under
B the cumulative number of movements up to the end of the period for all types of
aircraft that will use the facility. See example worksheet below.
2. Transfer the data for the cumulative aircraft passes for the design year onto
Worksheet No. 2 (see sample format below). On this worksheet record for each
aircraft type the number of equivalent DC-8-63F strain repetitions at various
distances from the centreline using the cumulative movements or passes for the
design period. These are determined for each aircraft from the appropriate aircraft
29
equivalency charts (Fig. D1-D65). For compressive strain criteria, the thicknesses
to consider are; 10, 20, 30, 40in and for tensile strain 10, 30, 50in.
3. For each assumed thickness, sum the entries under each ‘distance’ column and
circle the maximum value.
4. Develop the predicted traffic, Np , curve by plotting the circled maximum value
against the assumed thickness for each criterion. This curve must be developed on
the same graph on which the Na curve was developed for the corresponding and
each strain criterion.
6. The simultaneous solution will yield two thickness values; one for the tensile strain
criterion and the other for compressive strain. Select the greater of the two as the
design thickness of the pavement.
30
Fig. 4.2 Sample Na, and Np curves for a given strain criterion
31
5 Design of Rigid Airport Pavements
5.1 Introduction
There are several methods available for the structural design of rigid airport
pavements. Each of these designs considers the important factors that affect the ability
of the pavement to perform adequately in service. These factors are
Aircraft type, character and gear loads
traffic volume
concentration of traffic in certain areas of the pavement
construction material quality
The pavement is designed for capacity operations for the types of aircraft that are
expected to use the facility. Thereafter, the structure of the pavement can be modified
(reduced ) in areas where loading is not expected to be critical.
The method uses design charts produced by PCA which have been prepared for each
type of aircraft and its characteristics in terms of landing gear arrangements, load on
the gear, wheel spacing and tire contact area. Thus the chart used for an aircraft must
be the one with the details corresponding to the characteristics of the aircraft.
32
Table 5.1 Factor of safety for rigid airport pavement design
4. Select the design chart corresponding to the aircraft being considered. Fig. 5.1 is
an example of a design chart for Boeing 727 with a dual wheel landing gear,
contact area per tire of 237 psi and wheel spacing of 34 inches.
Fig. 5.2 PCA design chart for Boeing 727 with dual wheel landing gear
5. Determine the allowable working stress to be used in the design chart by dividing
the 90-day strength of the concrete (or its equivalent) by the selected factor of
safety.
6. Enter the appropriate design chart for the aircraft being considered with the
allowable working stress and determine the thickness of pavement required.
7. Repeat steps 3-6 for each critical aircraft anticipated to use the airport. Then select
the most critical thickness (largest) for the particular pavement area.
The outcome of the procedure outlined above may be set out in a tabular form as
follows for three example critical aircrafts say MD-11, B-727, DC-10.
33
Pavement area
Taxiway and runway ends Central portion of runway
Factor Working Slab Factor Working Slab
Aircraft Gear load Operations1 of stress Thickness of stress Thickness
safety safety
(1) (2) (3) (4) (5) 6) (7) (8) (9)
MD- 11
DC-10
B-737
1
Describe aircraft operations in column 3 as either frequent or non-frequent (occasional)
34
6. Rock Aggregates for Road Works
6.1 Introduction
Natural rocks constitute the primary source of aggregates used in highway construction.
These rocks exist in the form of rock outcrops at or near the earth’s surface or gravel
deposits usually along streams channels. In most cases, crushed rock aggregates from
stone quarries may constitute the sole structural layer materials for high performance
roads. Other types of aggregates (considered artificial) that may find limited use in
pavement construction are slug –a by-product from blast furnace and production of steel,
and light-weight aggregates produced by heating clay to a very high temperature.
The importance of aggregates in highway construction lies in the fact that the materials
constitute about 80% of the weight of paving mixtures. For engineering applications,
however, the most important consideration of rock materials, whether naturally-occurring
or artificial, is how well they serve in the various applications such as in the construction
of sub-base, bases, surfacing and other civil engineering works.
i. Igneous rocks
These are formed from the cooling of hot magma that flowed from depth to or towards
the earth’s surface. Those that cooled on the earth surface (extrusive rocks) did so rapidly
and tend to have fined-grained crystals as against those that cooled slowly beneath the
earth’s surface (intrusive rocks) which tend to have large surface crystal grains. Well-
known igneous rocks include basalt, granite, porphyry and gabbro. Depending on the
silica content, igneous rocks may be described as acidic, intermediate, basic and ultra-
basic.
1
Silica content (%) Nature of rock
>66 Acidic
55-66 Intermediate
45-55 Basic
<45 Ultra-basic
2
Table 6.1 Engineering classification of rocks
i. CLEANLINESS
The presence of foreign or deleterious materials in aggregates makes them unsuitable for
use in highway construction especially in the formulation bituminous paving mixtures.
3
Deleterious materials may be in the form of cay lumps, vegetation, soft particles, etc. the
standard method of determining the presence of deleterious materials is the Sand
Equivalent test carried out on the portion of the aggregates passing the 4.75 mm (No. 4)
sieve.
The Flakiness Index measures the percentage by mass of aggregate particles whose least
dimension is less than 0.6 times their mean dimension. The Elongation Index measures
the percentage by mass of the aggregate particles whose largest dimension is greater than
4
1.8 times their mean dimension. The mean dimension is the average of two adjacent sieve
sizes between which the aggregate particles being measured are retained.
The surface texture of aggregates is an expression of the nature of the inter-growth of the
minerals forming the rock including the size of the crystals of the minerals and the
probable bond strength resulting thereof. The surface texture of a crushed rock may be
described as follows (see Table 6.3).
These categories are based on the impression gained by a simple examination of hand
specimens and are therefore not a precise petrographical index because of the subjective
nature of the description. However. Aggregates for road construction should be rough to
provide inter-particle friction and a good bond with bituminous binders
iii. TOUGHNESS
Aggregates used for road construction may come under compressive load or may
experience polishing by the traction and shearing action of traffic. The toughness of an
aggregate measures the resistance of the material to quality–degrading forces. Several
parameters are available for measuring the toughness of an aggregate. These include the
aggregate
Aggregate Abrasion Value,
Polished Stone Value
Aggregate Impact Value,
Aggregate Crushing Value
10% Fines Value
Unconfined compressive strength
5
The resistance of aggregates to surface wear is assessed by the Aggregate Abrasion Value
and the Polished Stone Value. These parameters are extremely valuable in evaluating the
suitability of aggregates that will form part of the wearing course of a highway pavement
where degradation by attrition is highest. A very popular test is the Los Angeles Abrasion
test which is most often used to obtain an indication of both the toughness and abrasion
resistance of an aggregate. Typical test values range from 10% for extremely hard
igneous rocks to about 60% for soft limestone and sandstones.
The Aggregate Impact Value gives a relative measure of the resistance of the aggregates
to sudden impact whereas the Aggregate Crushing Value measures the resistance to a
compressive load. Materials with crushing values greater than 25-30% are not
considered suitable for use in pavement construction. Aggregate quality may also be
assessed by its Unconfined Compressive Strength (qu) which is carried out on the solid
rock material. For good quality road stones qu values should be greater than 100MN/m2.
The 10% Fines Value gives a measure of the resistance of the aggregate to crushing and it
is the compressive load required to cause 10% fines (material passing 2.36mm BS sieve)
to be formed during the relevant test. A high value is indicative of a material with high
resistance and hence high quality. The minimum value acceptable of road aggregates is
about 8kN.
A test for asphalt affinity (or lack of it) of an aggregate is the stripping test in which the
un-compacted bituminous mixture is soaked in water and the coated particles evaluated
6
visually. Immersion-compression test may also be used to evaluate the potential of the
aggregate to cause stripping problems. In the test, the strength of a compacted paving
mixture after soaking in water is compared to the strength of an identical un-soaked
sample. The reduction in strength is an indication of the quality of the aggregate in terms
of its resistance to stripping in the presence of water. Samples composed of hydrophilic
aggregates will exhibit a higher reduction in strength in the immersion-compression test
than those composed of hydrophobic aggregates.
Vap
Vpp-Vap
Vs
By definition,
Ws
Gsa (6.1)
Vs w
Ws
Gsb (6.2)
(Vs V pp ) w
7
Ws
Gse (6.3)
(Vs V pp Vap ) w
where
Vs=volume of solids
Vpp=volume of water permeable pores
Vap=volume of water permeable pores absorbing asphalt
Vpp-Vap=volume of water permeable pores not absorbing asphalt
Ws=weight of aggregate
100
G (6.4)
P1 P2 P
...... n
G1 G2 Gn
where
G=Specific gravity of the blend
G1, G2, ….Gn=specific gravity values of component or fraction 1, 2, …n respectively
P1, P2, ….Pn=% by weight of each component or fraction in the total blend.
Note that the equation is general and may be used to evaluate all the three types of
specific gravity values defined above.
8
Fig. 6.2 Types of aggregate gradation
LL=25%
PI<12% (in dry areas) or <6% (in wet areas)
Shrinkage Limit <4%
Suitable materials have a minimum 4-day soaked CBR of 80%. Table 6.4 provides a
guide to the required gradation of natural gravels intended for use in base course
construction.
9
Table 6.4 Typical gradation limits for natural in base course construction
%Passing
Sieve size Nominal maximum size
37.5mm (1 ½ in) 20mm (3/4 in) 100mm (3/8 in) 5mm (3/16 in)
37.5mm 100 - - -
20mm 80-100 100 - -
10mm 55-80 80-100 100 -
5mm 40-60 50-75 80-100 100
2.36mm (No.7) 30-50 35-60 50-80 80-100
1.18mm (No. 14) - - 40-65 50-80
600μm (No. 25) 15-30 15-35 - 30-60
300 μm (No. 50) - - 20-40 20-45
75 μm (No. 200) 5-15 5-15 10-25 10-25
10
Table 6.5 Grading Limits for all-in crushed-rock aggregate bases
Because of the tendency for all-in aggregates to segregate whilst being transported and
spread, they are usually kept wet during the transportation and spreading processes.
p= aA+bB+cC+… (6.5)
where,
p=% of blend passing a particular sieve size
A, B, C,….=the respective % of component materials A, B, C, etc. passing the particular
sieve size
a, b,c,..=the decimal proportions of aggregates A, B, C, etc. respectively in the blend
(a+b+c+..=1.0)
11
It is necessary as part of the blending technique to first plot the gradation of the
aggregates to be blended and the specification limits on a gradation chart before actual
blending is attempted. The plots make it easier to
decide whether a blend can be formed using the available aggregates to meet the
required specifications
identify the critical sieve sizes and
select appropriate trial proportions
An important fact to note from such curves is that the gradation for all possible
combinations of any two materials always lies between the gradation curves for the
individual materials and that if the curves for the two materials cross at a point the curves
for all possible combinations of the two materials will also cross that point.
a+b+c+…=1 (6.6)
As many equations as represent the number of unknowns (a, b, c..) may be written and
the resulting set of equations solved simultaneously. Where the specification for a
particular sieve size is a range, the recommended p value to use in Eq. 6.5 in formulating
the equation corresponding to that sieve size must be the mid-range value. Of course any
value within the range may also be used. If in the solution of the simultaneous equations
one of the unknowns turns out to be negative as can happen and which obviously has no
practical significance, the indication is simply that the target specification values (the p
values in Eq. 6.5) used in developing the equations are simply unattainable in whatever
proportions the materials are combined. The values of p should in that case be revised but
still kept within the specifications limits in the next trial. Even when a reasonable
solution (no negative values) appears to have been found, the satisfactory one will be the
solution for which a check of the resulting gradation with the specification limits meets
the requirements for all sieve sizes.
Step 1
Plot the % passing values for aggregate A on the right hand vertical scale representing
(100% of aggregate A on lower horizontal scale). Do the same for the values for
aggregate B on the left hand vertical scale (100% of aggregate B on the upper horizontal
scale; refer to Fig. 6.3).
12
Step 2
Connect points corresponding to the same sieve size on the two vertical scales with a
straight line and label the line with the sieve size for identification purposes. Note that
any vertical line intersecting each sieve size line will define the blend gradation on the
vertical scale and the blend proportions on the bottom and top horizontal scales.
Step 3
For a given sieve size line, mark on the line the points where the line crosses the upper
and lower specifications limits measured on the vertical scale. The portion of the straight
line between the two marks represents the proportions of the aggregates A and B
measured on the horizontal scale that will meet the specification limits for that particular
size.
Step 4
Draw two vertical lines one for the upper and the other for the lower spec. limits such that
the limits for all sizes in the specs, will not be violated. The region on the horizontal scale
bounded by the two vertical lines represents all proportions of possible satisfactory
blends. In practice the mid-point of the horizontal region is selected for the desired blend.
The point of intersection of the vertical through this point with the various size lines will
define the gradation of the blend on the vertical scale.
Step 5
If there are three materials to be blended, the resulting blend after Steps 1-4 is treated as
if it were a single material and then blended with the third material by repeating the
process from the beginning (Steps 1-4).
If at the end of Step 5 the proportion of the various components in the three-component
blend is x% of (A+B) and (100-x)% of C and the A+B blend is itself composed of y% of
A and (100-y)% of B, then the three-component blend (let us call it material D) is made
up in composition as follows:
The table below sets out the proportion of the individual materials in the blend.
13
Thus, the size fractions of the final blend will consist of the above proportions of the
corresponding size fractions of the individual components.
For a multi-component blend, Steps 1-4 are applied repeatedly each time taking the
resulting blend as a single material before combining with the next material. At each
blending stage, it is important to note the proportions in which the components forming
the blend exist in order that at the end of the process, the exact proportion of the
individual materials composing the final blend may be evaluated.
% of Aggregate B in blend
100 0
100 100
3/4
3/8
#4
#8
# 25
0 0 100 0
% of Aggregate A in blend
any vertical line in this region
will give a blend which will
satisfy specs. for all the sizes
14
7. Asphalt (bituminous) Paving Materials
When straight-run asphalts or vacuum tower bottoms are too soft they are given further
treatment in order to increase their hardness to a level acceptable for road building purposes.
This is achieved by subjecting the material to a process known as air-blowing. Air-blowing
converts the asphalt stock to one of modified properties (particularly increased hardness)
through polymerisation by contacting with air (oxygen).
In some cases, vacuum tower bottoms from the distillation process may be treated with
propane solvent to extract heavy oils such as lubricants in a process referred to as propane
de-asphalting. The residual asphalt from this process is a hard glassy product known as
propane-precipitated asphalt. This type of asphalt cannot be used directly for paving
applications but can be blended with any of the types of asphalts already mentioned to obtain
a product of intermediate consistency and the resulting product is referred to as a blended
asphalt. Thus depending on the crude type and available process capabilities, several
manufacturing options are available for the production of asphalts.
7.2.1 Penetration
This is the depth in units of 0.1mm that a standard needle loaded to 100g will penetrate an
asphalt sample for a standard duration of 5 seconds when the temperature of the sample is
maintained at 25oC (see illustration in Fig. 7.1). The harder an asphalt cement the lower its
penetration and vice-versa.
1
Fig. 7.1 Penetration of asphalt cement
7.2.2 Viscosity
Viscosity which is a measure of the resistance of a fluid to flow is a
fundamental property of fluids. This parameter is considered the most
appropriate parameter in describing the consistency of asphalts.
Asphalt viscosity may be evaluated when the sample is in a fluid state
at two standardised temperatures; 60oC and 135oC. The viscosity at
60oC commonly called the absolute viscosity and measured in units of
poise corresponds to the viscosity of asphalt in asphaltic pavements
during hot summer weather and represents the consistency of the
asphalt in its most critical state in service. In SI Units, 1 poise=0.1Pa.s.
The viscosity at 135oC is referred to as the kinematic viscosity
(measured in centistokes) since at this temperature the asphalt is
sufficiently fluid to flow under gravitational forces alone. This
viscosity corresponds approximately to the viscosity of asphalts at
mixing and lay-down conditions. The kinematic viscosity is the ratio
between the viscosity and density of the asphalt and has units of m2/s
in SI Units and cSt (centistokes) The SI unit of kinematic viscosity is
the square meter per second [m2/s].
The Gaussian unit of kinematic viscosity is the stokes [St = cm2/s].
Ten thousand stokes equal one square meter per second
[10,000 stoke = 1 m2/s].
20 50 A
PI ( 7.1)
1 50 A
where,
log Pen at T1 log Pen at T2
A
T1 T2
In practice, PI can be evaluated from a knowledge of the standard penetration value of the
asphalt cement and the softening point temperature. The parameter A in Eqn, 7.1 then
becomes
log(Standard pen.) log(800)
A
25 TR &B
Asphalts that are considered suitable for road building purposes have PI values ranging
between –2 and +2.
3
7.5 Grading
Asphalt cements are placed under different standard grades by way of their hardness or
degree of fluidity in order to make it possible for users to differentiate between them and/or
to select the type appropriate for an intended application. Asphalt cements may be graded on
the basis of either penetration at 25oC or viscosity at 60oC.
The numerical values for each grade represent the range within which the penetration for that
particular grade must lie. For example, any asphalt sample whose penetration lies between 40
and 50 (including the lower and upper limits) is classified as a 45-50 pen. grade. Because
asphalt manufacturers would be required to produce a specific grade for application, there is
no question of having an asphalt binder not belonging to any of the above grades, i.e.,
manufacturers control their production methods in order to obtain the required grade.
It is must be noted that there is no direct correspondence between viscosity grades and
penetration grades. Whereas, for example, most 60-70 pen grades will qualify as AC-20
grades and vice versa, AC-20 grades are not equivalent to 60-70 pen. grades. As a result,
specification for asphalts for road construction are based either on penetration or viscosity
but not both. However in some cases, an additional requirement in terms of viscosity for
penetration grades or in terms of penetration for viscosity grades may be imposed on a
particular grade just to restrict the range of possible materials.
4
ability to deform easily without rupture in order to resist stresses whilst existing as a
component of an asphaltic pavement (visco-elastic behaviour)
The durability of an asphalt cement in relation to its performance as a binder is its resistance
to changes (for the worse) in these original properties during in-service use. An asphalt
pavement with a durable binder should be able to support traffic-induced stresses and strains
and detrimental weather conditions for a long time. Characteristic features of a pavement
experiencing durability problems are pavement disintegration, ravelling and all kinds of
cracking. The asphalt binder in such a pavement is considered to have age-hardened or
become brittle.
Age-hardening continues in service although at a much lower rate for the first 2-3 years until
the pavement approaches its maximum density under traffic. In that condition, the rate of
hardening is significantly reduced due to the low pavement permeability and the reduced
potential for oxygen to diffuse into the pavement and react with the asphalt.
5
When it comes into contact with the surface of an aggregate an emulsified asphalt breaks or
sets (i.e. the asphalt globules react with the surface of the aggregates, lose their charge and
coalesce to form a continuous film on the aggregate as the water evaporates). Depending on
the rate of set or break, an emulsion may be described as rapid setting (RS), medium setting
(MS) or slow setting (SS). In general the rate at which an emulsion-aggregate mixture will set
depends on the following:
composition of the emulsion
the porosity of the surface to which the emulsion is applied
the rate of evaporation of the water which is dictated by wind conditions, relative
humidity and environmental temperature and
the surface chemistry of the aggregates with which the emulsion comes into contact.
The “h” designation means a harder base asphalt cement is used in the emulsion. The “HF”
designation refers to a high float residue which is an indication of chemical gelling of the
emulsion residue.
Selection and uses of emulsified asphalts are generally as follows (see ASTM D3628)
Rapid-setting grades: Surface treatments and penetration macadam
Medium-setting grades: Open-graded cold asphalt-aggregate mixtures
Slow-setting grades: Tack coat, dense-graded cold asphalt–aggregate mixtures,
slurry seals.
6
7.7.2 Cutback Asphalts (or Cutbacks)
A cutback is a liquefied asphalt obtained when an asphalt cement is liquefied by dissolution
in an organic solvent (cutter). The type of organic solvent or cutter used will determine the
rate at which the cutback will lose its liquid component and become solid, and hence the type
of cutback. If the cutter used is of high volatility (such as naphtha or gasoline) the resulting
cutback is described as "rapid curing" (RC); if a kerosene-type solvent which is of medium
volatility is used, the cutback is described as "medium curing" (MC). A cutback containing
low-volatile oils (such as diesel or gasoil) is described as "slow curing" (SC). Curing of
cutback-aggregate mixtures occurs simply by the evaporation of the cutter from the cutback
and does not involve any chemical reaction between the aggregates and the asphalt material.
Cutbacks are commercially available in different grades: the thinnest and most fluid grade is
designated by the suffix number 30 which is available in “medium curing” type only (MC-
30). Table 7.3 provides the grades of cutbacks commercially available in the paving industry.
The numbers shown against the various grades represent the minimum kinematic viscosity (in
centistokes) at 60oC for the particular grade. Each grade has an upper viscosity limit which is
double the minimum viscosity (or grade number)). Thus MC-70, SC-70, and RC-70 for
example, all have viscosities at 60oC ranging between 70 and 140 cSt.
7
7.8.1 Aggregate for Asphalt Concrete Design
Aggregates for asphalt concrete mix must be sound and pass the strength and shape
characteristics determined by the following tests:
i) Los Angeles Abrasion test,
ii) Soundness test,
iii) Flakiness Index test
iv) Elongation Index test
v) Aggregate Impact test
vi) Aggregate Crushing test
vii) 10% Fines test.
In addition, the aggregates must also be rough-textured with angular cleavage and perhaps
cubical in shape. The gradation must also represent the most economical blend that satisfies
all specification requirements for the intended use of the asphaltic concrete.
a. Mixture preparation
About 1150-1200g of the graded aggregates meeting specifications are placed in a mixing
pan. The actual quantity of material required is that which will result in a compacted
specimen height of 631.27mm. Usually, it is recommended to prepare a trial specimen prior
to the complete test schedule so that if this height is no met the quantity of aggregates taken
could be adjusted per the following formula:
63.5
Q Qo (7.2)
h
To provide adequate data, three test specimens must be prepared for each asphalt content and
aggregate combination. The asphalt content is by definition given as
Weight of asphalt
Asphalt content x 100 (7.3)
Weight of asphalt Weight of aggregates
A separate pan is required for each specimen. Specimens must be prepared to asphalt
contents that vary in 0.5 % increments with at least two of the test specimens having asphalt
content above the optimum and two below. Usually six different asphalt contents are selected
requiring a total of 18 Marshall specimens to be scheduled.
The weighed aggregates are dried in an oven and maintained at a temperature about 30 oC
above the mixing temperature. The mixing temperature is the temperature which corresponds
8
to asphalt viscosity of 17020cSt. This temperature is obtained from the viscosity-
temperature data on the asphalt cement being used. A quantity of the required asphalt cement
corresponding to the desired asphalt content of the mix is added to the heated aggregates and
then quickly and thoroughly mixed to obtain a uniform coating of asphalt on the aggregates.
b. Compaction of mixture
The whole of the mixture is transferred into the compaction mould for compaction to
proceed. Compaction takes place when the mixture has attained the compaction temperature
which is the temperature corresponding to a viscosity of 28030cSt. This temperature which
is slightly lower than the mixing temperature is obtained from the viscosity–temperature
curve for the asphalt cement sample being used and is usually in the region of 130-140oC.
Samples that cool below the compaction temperature are not recommended for use and must
be discarded. The hammer and mould to be used for the compaction must be heated to
temperatures around 100oC or a bit more. It is recommended that the inside of the mould be
given a light application of oil to aid later extrusion of compacted samples. In compacting,
one face of the specimen receives the required number of blows of the hammer: the faces are
reversed and the same number of blows is administered to the reversed face. The number of
blows per face is dictated by the level of traffic as follows:
After the compaction, samples are identified and allowed to cool preferably overnight before
being extruded from the compaction moulds.
Vmb=WSSD-Wsub
9
Hence the bulk density of the compacted sample becomes
Wa
Bulk density, mb 7.4
WSSD Wsub
Approach 2: Wax-coated sample method
In this approach the sample is first weighed in air (Wa), then coated with paraffin wax
(candle) and weighed in air again (Wc). It is then fully submerged in water and weighed
submerged (Wcsub). At the end of the weighings the following volumes obtain if the
weighings are recorded in grams:
Wc W a
Volume of wax (7.6)
G wax
W W a
Bulk volume of sample,Vmb [Wc Wcsub ] c (7.7)
G wax
Wa
Hence, bulk denisty of compacted sample (7.8)
Vmb
d. Voids analysis
The important properties of the compacted specimens of the paving mixture are the bulk
density, and voids in the mixture. Three different kinds of voids are identified. These are;
10
b. volume in mineral aggregates (VMA)
This is the volume of inter-granular voids space between the aggregate particles of a
compacted paving mixture that includes air voids and volume of the asphalt not absorbed
into the aggregate and expressed as a percent of the total volume
Fig. 7. 2 represents the equivalent weights and volumes of a compacted Marshall specimen.
where,
Vmb= bulk volume of compacted specimen
Va=volume of air voids
Vb=volume of asphalt or bitumen
Vba=volume of asphalt absorbed into aggregates
Vma=volume of voids in mineral aggregates
Vmm=voidless volume of compacted mix
Vsb=bulk volume of aggregates
Vse=effective volume of mineral aggregates
Wb=weight of asphalt
Ws=weight of aggregates
By definition,
11
V mb V sb
VMA 100 (7.9)
V mb
(100 Pb )
VMA 1001 G mb (7.10)
100G sb
where,
Gmb=bulk specific gravity of the compacted specimen
Gsb=bulk specific gravity of the aggregates
Pb=asphalt (bitumen) content in %
By definition
Va V (Vsb Vba Vb )
VTM 100 100 mb (7.11)
Vmb Vmb
G
VTM 1001 mb (7.12)
Gmm
where,
Gmm=theoretical maximum specific gravity of the compacted specimen.
VMA VTM
VFA 100 (7.13)
VMA
In the above equations, Gsb is a constant of the aggregates used but Gmm and Gmb are
dependent on the asphalt content of the compacted specimen and must be evaluated before
the voids calculation for each asphalt content can be made. Gmb is derived directly from the
bulk density values of the specimen. Gmm may be evaluated for each asphalt content by the
standard test ASTM D2041. A more practical way of determining Gmm for each asphalt
content is to use the standard test (ASTM D2041) to determine the value at an asphalt content
close to the optimum. The value so determined is used in the following equation to determine
the parameter Gse which is a theoretical constant of the aggregates.
100
Gmm
100 Pb P (7.14)
b
Gse Gb
where,
Gse = the effective specific gravity of the aggregates
Gb=specific gravity of asphalt (values range between 1.01-1.03)
12
Once Gse has been evaluated, subsequent values of Gmm for any other asphalt contents can
then be calculated using Eqn 7.14.
Once the density-voids analysis has been completed, the relevant data obtained must be
interpreted. This is accomplished by using the data to prepare the following plots:
As a precaution, it is necessary to check that the plots exhibit characteristics similar to the
corresponding plots in Fig.7.4 shown below.
13
Fig.7.4 Graphical presentation of asphalt concrete design data by the Marshall method
a. Stability increases with asphalt content, reaches a peak and then decreases. With many
recycled mixtures, however, stability may decrease with increasing asphalt content and
not show a peak.
b. Flow increases with increasing asphalt content
c. Density increases with increasing asphalt content up to a peak and then decreases. Note
that peak density and peak stability do not necessarily occur at the same asphalt content.
d. VTM decreases with increasing asphalt content
e. VMA decreases with increasing asphalt content reaches a minimum and then increases.
f. VFA increases with increasing asphalt content.
It is to be noted that peak density and peak stability do not necessarily occur at the same
asphalt content. Maximum stability tends to occur at an asphalt content slightly lower than
for maximum density.
14
Determination of the optimum asphalt content
The optimum asphalt content may be determined by any of the following two methods:
b. Enter the appropriate curves in the previous plots and determine the
stability
flow
air voids (VTM)
VMA and
VFA
corresponding to the average asphalt content determined previously.
c. Compare the values of the above parameters obtained from the plot with the specification
values or limits. If any of the values fails to meet the specifications, the mixture should be
redesigned, otherwise the mix formulation is accepted.
ii. Determine the values of the following parameters at the tentative optimum asphalt content:
Marshall stability
Flow
VMA and
VFA.
iii. Compare the values of each of the above parameters against the specification values or
limits. If all are within specification requirements, then the tentative optimum asphalt
content is indeed the optimum asphalt content otherwise the mixture should be
redesigned.
The Job Mix Formula is the gradation and the asphalt content which satisfy all specification
requirements and upon which plant mixtures are to be produced for the construction. This is
selected at the final stage of the laboratory design as the mix that was most economical and
gave the most satisfactory results.
15
7.9 Stiffness of Compacted Asphalt Concrete
For engineering calculations relating to asphaltic concrete mixture behaviour under loads, the
stiffness of the mix is used as a term analogous to Young’s Modulus. It is sometimes referred
to as the Resilient Modulus (MR). The stiffness of mixtures just like the stiffness of asphalt
cement is dependent on temperature and duration of loading. The relationship between
stiffness (Smix or MR), time (t) and temperature (T) is expressed as
S mix M R
(t , T ) (7.15)
where , = stress and strain respectively. The dependence of asphalt concrete stiffness on
temperature is illustrated below.
Stiffness
Temp
The following times are considered representative of the duration of the given traffic load
application conditions.
Traffic load Approx. load
Application type duration (s)
Fast traffic 0.01-0.1
Braking and accelerating 0.1-1.0
Parked >>1.0
Mixture stiffness may be determined by conducting indirect tensile tests on the compacted
specimen or estimated from the stiffness nomograph attached using the following data input:
For the evaluated mix stiffness to be representative of service conditions, the input stiffness
(Sb) of the asphalt binder should be that of the asphalt within the mix and not that of the
original asphalt selected for the mix. Hence the stiffness must be that of the asphalt recovered
from the mixture or that of the Thin Film Oven Test residue.
The heated aggregates from the dryer are conveyed via an enclosed elevator to a tower plant
where they are discharged onto vibrating screens that separate the materials into a number of
sizes. The screened aggregates are then stored in hot bins from where a control system
proportions them into a weigh box. The weighed mixture is then discharged into a pugmill
where the required amount of asphalt cement already weighed and stored in a weigh bucket is
introduced after a few seconds of dry mixing. The pugmill is equipped with a counter rotating
twin shaft that helps coat the aggregates with asphalt quickly. The HMA produced is
transferred into a storage silo or discharged directly into trucks for transfer to the lay-down
site.
17
8. Bituminous Surfacing and Construction
8.1 Introduction
Bituminous surfacing is any surfacing that involves the use of bituminous materials to
waterproof the pavement surface and/or provide structural strength. Such a
construction may consist of an application of a thin film of bituminous binder onto a
base course or pavement surface followed by the spread of a single layer of chippings
as in a chip seal (surface dressing), or it may involve the use of high-strength asphalt
concrete to waterproof and provide structural strength to a pavement. Other types of
bituminous surfacing include slurry seal, fog seals, etc. In all such constructions, the
principal materials are bituminous binders (penetration or viscosity grade, cutbacks,
emulsified asphalts) and aggregates of specified gradation.
8.2 Priming
Priming by itself is not a bituminous surfacing but it is the first step in the
construction of bituminous surfacing. It involves the application of bitumen or
asphalt, which has been made more fluid, to a road base so that the bituminous
material (called primer), will soak and penetrate the surface. The primer should be
fluid enough to penetrate the pavement surface to a depth of between 3 to 10 mm.
Priming of a road base is for any or all of the following reasons;
coating and bonding of fine dust particles to the surface of the pavement
plugging capillary pores in the pavement to waterproof the surface
penetrating and strengthening the surface of the base layer by increasing
cohesion
coating the surface of the base to provide better adhesion between the surface
and subsequent bituminous surfacing
providing a strengthened short-term running surface prior to subsequent
paving.
The main types of primers are cutbacks of the MC-30, MC-70, SC-70, SC-250 grades.
Asphalt emulsions are not recommended for priming because of their tendency to
form a skin on the surface of the pavement. The choice of the grade of primer and its
rate of application is usually dictated by the nature of the pavement surface to be
primed, and the period of time that will elapse before the main bituminous surfacing
is applied. The following table provides a guide to the type of primer and rate of
application appropriate for the nature of the surface to be primed.
Priming should take place when the weather is hot and dry and never when rain is
impending or the weather looks threatening. In addition, surfaces to be primed should
be damp but not too wet. A primed surface should be left for 2 to 3 days to allow the
volatile cutter in the cutback to evaporate otherwise the residual volatiles can affect
subsequent bituminous treatments. A primed surface is blinded with sand or quarry
dust if the road is to be opened to traffic for some short period before the application
of the main bituminous layer. This will serve to prevent vehicle tyres from picking
the sticky residual bitumen remaining on the pavement surface and destroying the
primed surface. Blinding is not necessary if the main bituminous layer will follow
within one or two days during which period traffic will not be allowed on the primed
section.
8.3 Primer-seal
A primer seal results if a primed road base is covered with aggregates. In this case,
the binder used for priming must be more viscous than would be used for normal
priming (see surface dressing binder) since it is intended to serve both as a primer
and as a binding material to hold the chippings onto the road surface. A primer seal
provides a riding surface for traffic for a period longer than would be provided by a
normal primed base that is blinded with sand or quarry dust. In general a primer-seal
construction provides several advantages including the following:
1. Traffic is able to use the primed surface the same day and for a much longer
period without significant surface deterioration even if the main seal coat is
considerably delayed.
2. The construction results in less disruption to traffic.
3. The seal can last up to 24 months and is suitable for situations where
placement of the main seal is expected to be considerably delayed.
4. When the final seal coat is placed, a surfacing intermediate between a single
seal and a double seal is obtained. This leads to an enhanced surface integrity
which improves durability of the chip seal as a whole.
5. It results in minimal loss of chippings as about 95% chip embedment is
achieved. This in turn almost eliminates aggregate whip-off and associated
windshield breakage and results in an environmentally friendly surfacing.
The construction is generally adequate for lightly trafficked roads with traffic levels
not exceeding 500 veh/lane/day. Where roads carry up to 1,000 veh/lane/day or even
more, a double surface dressing may be appropriate. A double surface dressing is
simply a surface dressing applied on a surface dressing. It is recommended that the
application of the second dressing takes place at least 2-3 weeks after the construction
of the first surfacing to allow traffic help the chippings of the first dressing assume a
stable interlocking structure and become a firm foundation for the second dressing.
But successful performances have been observed for constructions that ignored this
recommendation. The nominal size of chippings to use in the second dressing
must be half that of the first.
Where there are two sizes to choose from, it is recommended to use the smaller
aggregates for roads in urban areas where traffic loads are low and the larger ones on
rural highways where commercial vehicle traffic and axle loads are high.
The rate of primer binder application is a function of the size of aggregate to be used
for the primerseal; the volume of traffic anticipated on the road; the spray
temperature, and the porosity of the pavement surface. The spray temperatures
considered are for either cold or hot applications and are respectively 15oC and 135oC.
The porosity of the pavement surface is placed into four types, namely,
tightly bonded,
fine bonded,
coarse and
crushed rock.
For both cold and hot binder applications the aggregate spread rate is dependent only
on the size of chippings selected. Table 1 from GHA Spraying Seal Manual provides
an example guide to materials application for a tightly bonded pavement surface with
the primer seal applied cold.
Similar tables are available for other surface types and for cold and hot binder
applications.
v. Rolling (Compaction)
Only pneumatic-tyre rollers of mass between 12 and 15 tonnes and a wheel load
greater than 1 tonne with a tyre pressure of 550kNm2 are specified for use. Steel-
wheeled rollers are not recommended for use as they tend to compact only the high
spots and crush aggregates. Pneumatic-tyre rollers result in kneading compaction and
are able to re-orient the aggregates to lie on their flat side with their least dimension
vertical so that there is also embedment rather than just mere compaction. This results
in a more interlocking aggregate layer for the seal. Where necessary two rollers may
be employed to keep pace with the tack coat application and aggregate spread.
5
8.4.2 Problems associated with surface dressing
Surface dressings that are not properly constructed may experience one or more of the
following problems:
i. Streaking
This is an alternating series of light and dark longitudinal parallel lines on the
road surface due to uneven application of binder on the finished surface. Such
unevenness may result from clogged spray bar nozzles or incorrect height of
spray bar above pavement surface.
ii. Bleeding
This is the flushing to the surface of bituminous binder in the surfacing so that
the passage of a vehicle leaves an imprint of the tyres on the surface. Bleeding
causes pavement surfaces to be shiny and extremely smooth. The problem is
caused by the application of too much binder or by the loss of cover
aggregates.
In general the benefits to be derived from a fog seal application on a surface dressing
include:
complete retention of surface dressing chippings
longer pavement life from improved retention of cover aggregates
improvement in the surface riding quality
windshield breakage and paint chip from whip-off aggregates are completely
eliminated
noise from vehicle tyres is substantially reduced
enhanced roadway aesthetics from a well-defined carriageway
6
8.6 Slurry seal
A slurry seal is a bituminous surfacing placed in the form of thick workable slurry of
a mixture of asphalt emulsion, water, aggregate and filler. The slurry, which is
premixed in a specially equipped truck, is spread on the road surface by means of a
spreader box to a thickness of about 5-10mm. When placed, slurry of optimum design
should set in about 30-60mins. Depending on the aggregate gradation used, three
slurry types, namely, type I, type II, and type III may be produced. The following are
the gradation requirements for the three types of slurry. ( Table 8.3).
Type I slurry is suitable for sealing cracks, filling voids and correcting surface defects
on airfields where surface sealing is the primary needs. The slurry is applied at the
rate of 3.3-5.4kg/m2.
Type II slurry is suitable for filling surface voids, correcting severe surface erosion
conditions, providing a wearing surface on bituminous base course or soil-cement
bases, or as a sealer on stabilised base courses. The rate of application is 5.4-
8.2kg/m2.
Type III slurry is suitable for providing a new wearing surface to improve aesthetics
or the skid resistance of a polished surface or building a crown. The rate of
application is 8.2kg/m2 or more.
8.7.3 Compaction
The compaction process is affected by confining conditions, which in the field are
provided by the surrounding HMA material, the underlying layer and the compactor
contact area in its zone of influence. Because temperature has a profound effect on the
workability of asphalt paving mixtures, compaction should be carried out at the
proper compaction temperature determined on the basis of the viscosity-temperature
characteristics of the asphalt binder used. Whatever the case, compaction should be
carried out before the asphalt mat cools below 80oC; below this temperature, the mix
will become stiff and no amount of compaction can compress it to occupy a smaller
volume. At no time during the compaction operations should rollers be parked on the
8
hot mat since parking will cause depressions that may be difficult to remove even
with additional rolling.
When compacting unsupported mats with constant cross slope, the first pass of the
roller should be on the low edge of the mat with each successive forward pass moving
toward the high edge of the laid mat. Special care must be taken in compacting
longitudinal joints as an improperly compacted joint may be a future location for
water damage, ravelling or even a potential driving hazard. Where possible, especially
when paving two-lane carriageways, the longitudinal joint can be deleted by paving in
echelon. This of course will require the use of two pavers. In other cases, about 50-
75mm of the cold mat adjacent to the new mat to be placed is first cut back to expose
a clean dense vertical face. The face is then tack- coated and the adjoining run placed
to overlap the cut by about 25-50mm. Using lutes, the overlap is pushed back
immediately after placing to form a small ridge along the joint.
Longitudinal joints are the areas to be rolled first and a steel-wheeled roller must be
used. Rolling should take place close behind the paver with the roller compressing the
joint and overlapping onto the fresh asphalt by about 150mm. This is continued until a
smooth joint is obtained. Rolling is then continued on the opposite side and then
worked back toward the joint. During all rolling operations, the next forward pass
should overlap the previous by at least 150mm. Also each roller pass should end
beyond the preceding pass by at least one meter to prevent the development of a
bump. When the general rolling operations have been completed, a visual inspection
has to be conducted to ascertain the condition of the freshly compacted surface. If
rolling was properly carried out, there should be no roller marks, scuffmarks and
undulations.
i. Compaction equipment
Compaction equipment for asphalt works includes steel wheeled rollers, vibratory
steel-wheeled rollers, pneumatic-tyred rollers and plate compactors. To be suitable for
asphalt works, the compacting surfaces of the equipment must be smooth and free
from marks. To prevent the sticking of the asphalt concrete mix to the compactor
tyres, the equipment must be provided with a watering system and a spray bar for the
controlled application of water on the compacting wheel or steel drum and scrappers
and a series of mats mounted on a transverse bar which are kept wet and in contact
with the drum to remove any asphalt mixture that sticks to the wheel. The water
system is used during the breakdown rolling but not for finish rolling.
9
The breakdown roller should be operated as close to the paver as practicable in order
to take maximum advantage of the temperature of the mix and thus obtain the
maximum increase in density. Where the speed and productivity of the paver is high
more than one compactor may be deployed in the breakdown rolling. Initial rolling
should normally begin at the lower side of the run with the roller moving
longitudinally and reversing along the same track. The roller should then move
progressively across the run to the opposite side, completing a forward and backwards
passes on each track and with each track overlapping the previous by about 150mm.
Normally two passes of the breakdown roller may be adequate but up to four passes
may be necessary if a thick layer is placed.
Intermediate or secondary rolling is carried out right after the initial compaction and
should only be delayed if the asphalt temperature is higher than the optimum required
for proper compaction so that excessive deformation or shoving by the compacting
drum does not occur. Rolling commences along the longitudinal side of the run and
returns on the same track before moving across the run in full roller width to the
opposite side. Rolling then continues until the required density is achieved. This may
require between 6 to 12 passes depending on the thickness of mat and temperature
conditions. Traditionally pneumatic-tyred rollers are used for intermediate rolling as
they are very effective in removing roller checking (fine hairline transverse cracks)
produced by steel-wheeled rollers during breakdown rolling.
Finish or final rolling is carried out while the mat is still warm enough to allow
removal of all roller marks so as to obtain a smooth uniform finish without causing
shoving and fine or hairline transverse cracks in the surface of the mat. Rolling may
be accomplished by using steel-wheeled rollers or pneumatic tyred-rollers with
relatively high tyre pressure.
Thus, for example, the field density to be achieved may be specified as minimum 95%
of laboratory density. There are no special criteria for selecting which of the above to
specify as target density. In fact, all the above types of densities have been specified
for density control on many projects with varying degrees of success and failure. It
appears however that minimum density values are commonly specified with respect to
the laboratory bulk density.
Relative compaction levels that are consistently above 100% may indicate over-
compaction that can have serious consequences on rutting. Over-compacting the
asphalt mat may result in air voids content below 3% which will cause rutting to
10
develop early in the life of the pavement. But generally, relative compaction levels
consistently approaching or exceeding 100% may likely be more the problem of a low
reference density rather than of over-compaction. Therefore the interpretation of the
degree of compaction must be approached with caution.
Quality control refers to those tests necessary to control a product to determine the
quality of the product being produced. The contractor usually carries this out. During
asphalt overlay operations, QC may be necessary to ensure that material being
supplied to the lay-down crew is consistent and within specifications and/or to detect
at the onset any deficiencies in mix productions if and when they occur so that any
problems attributed to the mix can be fed back to the design laboratory or production
plant for corrections or adjustments to be made.
On the other hand quality assurance are those tests necessary for the owner to make a
decision on acceptance of a project and to ensure that the product being delivered is
indeed what the owner specified. The Engineer’s representative carries out the tests.
A successful QC/QA requires that the Materials Engineer, the paving team and the
personnel at the hot-mix asphalt plant work together.
Tests to undertake
In line with quality control and assurance, the following are considered important
tests to perform during manufacture and placement of asphalt concrete mixtures:
Aggregate gradation
Asphalt content
Temperature
Compaction and voids analysis
Density tests (theoretical maximum density and in-situ density)
Visual inspection
a. Aggregate gradation
Even though several aggregate properties are important, routine testing during
construction is usually limited to gradation only. Aggregates for grading tests must be
sampled from the stockpile, cold feeder belt, hot bins and extracted asphalt mixture.
Gradation of the asphalt mixture is the most important since it is the final product.
Evaluation at other points will however allow the engineer to troubleshoot the
gradation problem and quickly identify the location where it is occurring.
b. Temperature
This parameter is very important during mixture production and during field
compaction. The asphalt concrete must be produced at just the right temperature to
ensure good coating on the aggregate and a satisfactory compaction. Excess
temperature causes oxidation and loss of volatiles to occur to the asphalt cement
reducing mixture durability. An indication of asphalt concrete being produced at an
unacceptably high temperature is the blue smoke syndrome which literally means a
11
bluish smoke coming out of the mixture as it is discharged into a delivery truck.
Monitoring the temperature of the laid mixture is very necessary to ensure that
compaction is carried out at the proper compaction temperature as determined per the
viscosity-temperature characteristics of the asphalt cement. Where the temperature of
the laid mix is high, compaction has to be delayed to allow the mix to come to the
compaction temperature. It is also necessary to ensure that the temperature of the mix
does not fall below a value that makes compaction ineffective. The recommended
minimum temperature for compaction is 80oC.
c. Asphalt content
This is very important in ensuring that the asphalt concrete is being produced per the
Job Mix Formula and also in guaranteeing a satisfactory performance. Asphalt content
has direct effect on mixture properties such as film thickness, voids, stability and
flow. A mixture with low asphalt content may have durability problems whereas one
with high asphalt content is likely to have stability and bleeding problems. Asphalt
concrete from the spreader must be sampled and the solvent extraction test carried out
in order to determine the asphalt content. Improper asphalt content can be caused by
inaccurate aggregate proportioning in the batch or drum mixing facility, improperly
calibrated asphalt cement meter, segregation, and even sampling and testing errors.
d. Laboratory compaction
Samples of the asphalt concrete must be taken regularly and for every batch
production during construction for laboratory compaction and other tests in order to
verify that mixture characteristics or properties meet specification requirements. If the
required density levels are not achieved, the mix may deform under load, harden
prematurely, lose fatigue resistance and be more susceptible to moisture-induced
damage (stripping). The laboratory density values are the standard against which the
level of compaction being achieved in the field is evaluated. The compacted samples
also enable voids analysis to be carried out.
e. Filed density
To check the level of in-place density achieved, nuclear gauges may be used or cores
may be taken for laboratory analysis. The results of the density tests are used to
establish the relative compaction achieved by comparing the field density to the
laboratory density.
f. Visual inspection
As test results can never identify all the problems that may occur, visual inspections
must be carried out during QC/QA evaluations. This way, potential trouble areas can
be identified and corrected or areas that appear deficient can be sampled to determine
if deficiencies really exist.
Primarily the scale and importance of the project and material variability determine
the frequency of testing. The following is only a guide to the minimum number of
tests to be conducted on an asphalt overlay project.
12
Test Frequency
13
9. Pavement Failures and Maintenance
PSI
maintenance
Years in service
The present serviceability index (PSI) is a qualitative rating of the current surface condition of a pavement.
Newly constructed roads can be expected to have PSI values in the range 4.5-5.0 whereas roads in poor
condition have values below 2.0. As indicated in the figure, the deterioration of a road is generally gradual in
the first few years but begin to proceed at a much higher rate with time. With timely intervention in the form of
pavement maintenance, it is possible to return the service condition of the road almost to the as-constructed
state. Pavement failure will manifest visibly in the pavement, at one time or the other, as a defect in
the structure or the surface or both. The defects affect the serviceability, appearance and structural
capacity of a road.
Each of these failure modes has its own peculiar characteristics and manner of impacting upon the
performance of pavements. It must be emphasized, however, that it is not always the case that a given
pavement distress can be ascribed to one particular mode of failure since in general one mode of
failure may induce or lead to other modes. The type of pavement may affect the preponderance of one
mode of failure over the others. For example, whereas in rigid pavements cracking of concrete slabs is
a predominant mode of failure, in unpaved roads the major failure modes are structural deformation
and surface defects with cracking being virtually absent.
When related to the function of the road, the mode of failure will determine whether the failure can be
described as a structural failure or a functional failure. Structural failure refers to all failures that
include a collapse of the pavement structure or a breakdown of one or more of the pavement
components of such magnitude as to make the pavement incapable of sustaining loads imposed upon
its surface. Functional failure on the other hand refers to all types of failures which will not allow the
pavement to carry out its intended function without causing discomfort to passengers or without
causing high stresses in the vehicle that passes over it due to roughness.
1
a. Structural Deformation
To a very large extent, a structural deformation mode of failure has the highest potential to
incapacitate a pavement structurally since it may cause complete collapse of one or more of the
components of the pavement.
b. Cracking
This mode of pavement failure is associated more with paved than unpaved or gravel roads. In paved
roads (mostly asphaltic and rigid), cracking provides evidence of fatigue failure and/or failure under
tensile stresses of the surfacing material. Cracking rarely appears in unpaved roads and only so mostly
in cases where fills in embankments undergo lateral movement and subject the soil material to tensile
stresses and/or where layer materials undergo shrinkage and develop shrinkage or desiccation cracks.
c. Surface defects
Pavement distresses that manifest as surface defects generally affect the ride-ability of the pavement
and in some cases also the structural performance of the pavement. Remedial measures for such
defects are mostly confined to the surfacing and may not require any structural changes to be made to
the pavement.
Location
The location of a distress is given in terms of two points along the length of the pavement. These
points delineate a pavement section to which the subsequent description of distress pertains.
Generally for long sections the description of distress is not precise. The pavement may then be
divided into various short sections to allow for more accurate description.
2
9.1.3 Causes of pavement failures
Pavements begin to deteriorate when opened to traffic after construction as a result of one or more of
the following:
a. Traffic loading
Flexing of pavement under repeated loading leads to fatigue, cracking and structural failure over weak
subgrades and where the depth of carriageway construction is inadequate to provide sufficient spread
of loads from vehicles.
c. Temperature
Extreme temperatures between day and night may cause thermal movement that tends to cause cracks
to develop in a pavement surface. High temperatures can cause stability problems in asphaltic
pavements leading to rutting, ripple formation, corrugation, flow of surface material and in rigid
pavements cracking, spalling, and blow ups.
d. Moisture movements
Water is the greatest enemy of a pavement. When moisture has access into a pavement layer it
weakens the shear strength of the layer materials and reduces the load carrying capacity. Moisture
movement into underlying pavement structure may also cause volumetric changes such as swelling
and shrinkage that can lead to shrinkage or swelling stresses with the potential to cause cracks or
heaving in both rigid pavements and structural asphalt layers.
f. Weathering
This leads to chemical changes in asphaltic concrete and Portland cement concrete and subsequent
embrittlement especially in asphalt binder leading to cracking and progressive loss of matrix.
g. Rainfall
For unpaved roads, rainfall apart from causing weakening of pavement layer materials causes the
development of erosion gullies through the progressive washing away of materials from the surface
by erosion. Erosion gullies may be particularly pronounced on sections with steep slopes where
because of the slope angle being greater than the surface camber surface runoff moves longitudinally
along the road or diagonally across the road instead of transversely to the side ditches and drains.
3
Alligator crack (crocodile crack, alligator crazing, fatigue crack, map crack, chicken wire
crack)
Alligator crack is a crack pattern which forms as a series of interconnected, closely spaced sharp-
angled, many-sided cracks which resembles chicken wire or the skin of an alligator. Alligator cracks
in asphalt pavements begin at the bottom of the asphalt surfacing where tensile stresses and strains are
the highest under a wheel load and spread to the surface. Initially, the cracks appear as a series of
longitudinal cracks which after repeated traffic loading then join up to form many-sided crack
patterns.
Causes
Alligator cracks may be caused by
fatigue failure of the asphalt concrete layer under repetitive axle load applications.
overstressing of pavement structure due to excessive axle loads
inadequate structural capacity of pavement
shear failure in the underlying pavement layers due to insufficient layer strength, poor compaction
or inadequate drainage.
loss of visco-elastic property of the asphalt concrete due to embrittlement or age-hardening
Causes
This pavement distress is caused mainly by
shrinkage of the pavement sub-grade reflecting through a thin road construction
thermal contraction and expansion of the asphalt concrete layer
fatigue cracking in aged or embrittled asphalt concrete.
use of hard asphalt binder in asphalt concrete mix
use of poor quality materials
poor construction
Causes
Longitudinal cracks may be caused by
lack of lateral support in embankment fill
volume changes in clayey or expansive sub-grade soils
differential settlement between cut and fill that reflects through the asphalt layer
poorly constructed lane joint in asphalt pavement
displacement of joint at point of pavement widening
reflection of joint crack in a rigid or an old asphalt pavement that has been overlaid.
Causes
These cracks are caused by
thermal expansion and contraction of the asphalt concrete
asphalt age-hardening which causes binder embrittlement and loss of visco-elasticity of the
asphalt concrete layer
use of hard asphalt binder in asphalt concrete mix
overheating of asphalt concrete mix during hot-plant manufacture
use of poor quality materials
poor construction
Causes
The defect occurs when
soft binder-rich surface mixes are subjected to high stresses from braking and acceleration.
a poor bond exists between the surface course and the underlying base course
thin wearing courses are laid
the base course material has low strength (modulus)
Edge crack
This is a longitudinal crack which develops close to the edge of a pavement and which sometimes is
accompanied by transverse cracks towards the shoulder. In some cases, settlement may occur within
the narrow strip of pavement between the edge crack and the edge of the pavement.
Causes
Edge cracks may be caused by
lateral movement of the pavement material due to insufficient shoulder support especially in areas
of high embankment fill.
settlement or yielding of sub-grade or base material close to the edge of the pavement.
Reflection crack
This is a crack that develops when discontinuities or cracks in an overlaid asphalt concrete pavement
propagate through the new overlay to the surface. Such cracks may therefore show as longitudinal,
transverse or any other type of crack pattern.
Causes
Reflection cracks may be caused by
Cracks or joints in an underlying rigid pavement
5
Low temperature cracks in an overlaid old asphalt concrete layer
Longitudinal cracks in an overlaid old asphalt surface
Fatigue cracks in the old asphalt surface
Causes
Potholes are caused by
abrasion and dislodgment of surface material by the action of traffic
asphalt binder embrittlement and subsequent stripping or raveling of asphalt pavements.
localized shear failure of the pavement base due to improper compaction, improper aggregate
gradation, use of unsuitable material
Infiltration of water into pavement
Causes
Bleeding is caused by
unstable mix or excessive amounts of binder in the asphalt concrete
low air void content in the asphalt concrete layer
stripping of aggregates
use of soft asphalt binder in asphalt concrete formulation
spillage of petroleum products onto the pavement surface
excessive application of tack coat
Causes
The defect may be caused when
the asphalt concrete pavement lacks adequate stability
the applied forces on the pavement surface due to braking or acceleration exceeds the shear
strength of the asphalt concrete or the underlying layers
a thin asphalt concrete overlay is placed over granular bases and sub-bases.
6
the bond between an asphalt wearing surface and the binder course is poor or has been broken.
Causes
Corrugations may be caused by
tender mix or lack of stability of asphalt concrete due to excess asphalt content or use of soft
binder
use of mix with excessive amounts of rounded aggregates or excessive fines
braking and acceleration actions of vehicles particularly at intersections
wavy compaction at the time of placement of asphalt mat
uneven spread of gravel layer and subsequent wavy compaction in gravel roads
Causes
Ravelling may be caused by
abrading of asphalt films from aggregate particles that were insufficiently or poorly coated with
asphalt during mix production.
segregation of the asphalt concrete matrix at the time of placement of the asphalt mat so that
there is concentration of coarse aggregate without sufficient fines to aid continuous inter-particle
contact and bonding.
poor mat compaction resulting in low asphalt concrete density
asphalt age-hardening and embrittlement leading to brittle fracture of asphalt films and
subsequent dislodgement of coated aggregate from asphalt concrete matrix under traction forces.
use of high dust to asphalt ratio in asphalt concrete mix formulation.
use of hard grade asphalt for asphalt concrete manufacture.
low asphalt content in asphalt concrete.
Rutting
A rut is a longitudinal depression in the wheel tracks often accompanied by pavement uplift along its
sides when pavement materials are displaced.
Causes
Rutting may be caused by
permanent deformation in any of the pavement layers or sub-grade as a result of continuous
wheel tracking over a narrow width of the pavement.
continued densification of pavement layer materials under traffic after initial compaction or as a
7
result of plastic deformation of surfacing materials subjected to repeated trafficking or
channelization.
insufficient compaction of pavement layers during construction.
improper asphalt concrete mix design for asphalt pavements
use of excessive amounts of rounded aggregate in asphalt concrete mixes in asphalt pavements
use of soft bituminous binder in asphalt concrete formulation
inadequate structural capacity of pavement.
Shear failure
This defect is the collapse of a component of the pavement structure in shear due to stresses
exceeding the shear strength of the layer. The distress is recognizable by a depressed area and an up-
heaved area.
Causes
Shear failure may be caused by any or a combination of the following
excessive wheel loads
inadequate base/sub-base compaction during construction
weak sub-grade layer
use of poor quality materials in pavement layers
inadequate pavement drainage
Edge failure
This is the progressive disintegration or breakage of the pavement structure from the edge inwards,
for paved roads usually where there are no kerbs and where vehicle over-run is common, such that
pieces of the pavement are broken, become loose, are dislodged and then displaced resulting in the
reduction of the pavement across its width.
Causes
Edge failure may be caused by
lack of lateral support at the edge of the pavement in embankment zones
insufficient base thickness
base failure
excessive loads applied at the edge of the pavement
inadequate compaction at the edge of the road
inadequate or poor drainage
narrow carriageway encouraging vehicle overrun at the edges
Causes
A depression may be caused by
failure of a soft spot in the underlying pavement layers
consolidation of a soft spot in the sub-grade
8
poor compaction after re-instating utility opening
Causes
Loss of skid resistance may be caused by any or a combination of the following:
bleeding of the asphalt concrete surface.
polishing of surface aggregates by traffic action when aggregates with low polish or wear
resistance are used in asphalt concrete.
use of small size aggregate and excessive fines in asphalt concrete mix.
loss of surface texture due to the embedment of coarse aggregates in asphalt matrix as a result of
traffic action especially where soft or binder-rich mixes are involved.
use of rounded or naturally worn aggregates in asphalt concrete.
Causes
Cover aggregates on surface dressings may be lost by any of the following
use of dusty aggregates for the dressing
lack of strong bond between aggregates and bituminous binder
use of insufficient binder for dressing
erratic distribution of binder
binder embrittlement due to age-hardening
poor quality surfacing
De-lamination
This is the separation of the wearing course of the pavement from the underlying layer with
subsequent loss of a discrete and large area of the wearing course at the affected area. This is a
surface defect that affects the structure of the asphalt pavement. This usually occurs where a very
thin (veneer) layer of asphalt wearing course has been placed over a base course or a rigid pavement.
Causes
De-lamination may be caused by
loss of bond between the asphalt wearing course and the underlying asphalt base course.
the existence of a thin layer of dust on the binder course at the time of placement of the wearing
course.
seepage of water through cracks to undermine bond between wearing course and underlying layer
the presence of weak and loose layer immediately underlying wearing course
9
Stripping
This is an asphalt pavement distress characterized by the loss of bond between the aggregates in an
asphalt concrete matrix due to the displacement of the asphalt coating on the aggregate surface by
water. The defect typically begins at the bottom of the asphalt concrete layer and progresses upwards.
The distress may sometimes be very difficult to identify because it can manifest as rutting, shoving,
corrugations, ravelling or cracking but is typically and visibly evidenced by partially coated or
uncoated aggregates.
Causes
Stripping may be caused by any or a combination of the following factors:
presence of water in aggregates during asphalt concrete manufacture.
use of hydrophilic aggregate in asphalt concrete.
infiltration of water into the asphalt concrete layer.
poor drainage of the pavement base course.
poor compaction of asphalt concrete resulting in an open-textured surface.
Adverse camber
This is an irregular transverse profile of the carriageway where the camber or the crossfall is steeper
than current design parameters.
Causes
Adverse camber may be caused by
overlaying or resurfacing of the middle portions of a pavement excluding the edges in order to
maintain kerb upstand
subsidence
widening or re-aligning a road without subsequent re-profiling
Longitudinal crack
Longitudinal cracks are planes or lines of discontinuities that manifest in the rigid pavement surface
as thin lines that run approximately parallel to the longitudinal axis of the pavement.
Causes
The cracks are generally caused by the same factors that cause the formation of cracks in general and
include
contraction and expansion of the concrete slab
warping stresses in concrete developed from temperature changes
inadequate sub-grade support
inadequate steel reinforcement
excessive slab length
inadequate slab thickness
low concrete strength
lateral movement of base support or layer
expansion and shrinkage of base material
Causes
contraction and expansion of the concrete
warping stresses in concrete developed from temperature changes
inadequate sub-grade support
inadequate steel reinforcement
excessive length of slab
inadequate slab thickness
inadequate concrete strength
Causes
differential settlement of adjoining slabs
loss of sub-base material through pumping
poor sub-base or sub-grade support
curling or warping of slab due to temperature gradient across the depth of the slab
Spalling
This is the breaking into angular pieces of concrete material from the edges of cracks, joints, and
corners of the concrete slab or the flaky breakage of material from the surface of the slab.
Causes
Spalling may be caused by
use of poor quality concrete
corrosion of reinforcement bar
loading at the edges of joints and cracks
Blow-up (Buckling)
This is a localized upward movement of rigid pavement slabs which occurs at a transverse joint or
crack. The occurrence of the defect is mostly accompanied by transverse edge shattering.
Causes
Blow-ups may be caused by
expansion of adjacent slabs under hot weather conditions
inadequate provision for expansion joints between slabs
Pumping (Blowing)
This is a process accentuated by passing traffic by which a mixture of water, clay and fine-grained
soil is pumped out or exudes from underneath a rigid pavement slab through cracks, joints and the
edges as the slab is repeatedly caused to deflect downwards by passing vehicles.
11
Causes
Pumping may be caused by
infiltration of water into sub base through cracks and joints in the concrete slab without the
possibility of drainage
high fines content in sub-base material
Causes
This surface defect may be caused by any or a combination of the following;
use of poor quality aggregate
inadequate curing of concrete
poor concrete quality
overworking of surface during construction
Rutting
A rut is a surface defect and is characterized by a longitudinal depression in the wheel tracks often
accompanied by pavement uplift along its sides when pavement materials are displaced.
Causes
Rutting may be caused by
permanent deformation in any of the pavement layers or sub-grade as a result of continuous
wheel tracking over a narrow width of the pavement.
continued densification of the gravel layer under traffic
insufficient initial compaction of pavement layers during construction.
loss of gravel material from within wheel tracks
inadequate structural capacity of pavement
loss of strength due inadequate drainage
Erosion gullies
These are channels which run almost longitudinally or sometimes diagonally on the surface of gravel
roads created by the erosion of surface material by rain water running on the surface of the gravel or
earth road. Erosion gullies most often follow wheel tracks and characteristically turn diagonally to
join side drains.
Causes
Erosion gullies are caused by
the erosion of surface material by rain water running on the surface of the gravel pavement.
Slippery Surface
This is a surface defect characterized by slipperiness during wet weather causing danger to vehicles
on steep slopes and sharp curves.
12
Causes
use of clayey soil in forming base course
complete loss of gravel cover on clayey sub-grades
Loose gravel
This is a surface defect characterized by the presence of loosely compacted gravel or gravel in
windrows along the center of unpaved roads, wheel tracks and/or along the shoulders in parallel
orientation to the direction of traffic.
Causes
The defect is caused by
inadequate compaction of the gravel layer
use of gravel materials with insufficient fines to bind the coarse particles during placement and
compaction
segregation of coarse aggregates from fine particles by traffic action and subsequent whipping of
coarse aggregates to the centre and road sides.
Shoulder drop-off
This develops when there is elevation difference between pavement edge and shoulder such that the
riding surface of the pavement stands high above the shoulder level.
Causes
This defect may be caused by
erosion of the shoulder if it is unpaved
settlement of the shoulder relative to the pavement
building up the pavement without due adjustment to the level of the shoulder
Causes
This pavement defect may be caused by any of the following
formation of gravel wind-row on the shoulders of pavements that were formed with materials
containing excessive amounts of gravel
deposition of detritus and eroded material on the shoulder by rainwater
poor construction and improper maintenance
Causes
13
Vegetation encroachment results when
there is lack of routine maintenance
there are long intervals between periods of grass cutting particularly in areas with high rainfall
and rapid vegetation growth.
9.2 Maintenance
Maintenance is an intervention measure designed to arrest the deterioration of a road and to restore
the service condition to the as-built state or, at least, very nearly so. The type and scale of the
maintenance activity will depend on the type of pavement failure being considered.
a. Routine Maintenance
This is the work that is performed as needed throughout the year and includes the day-to-day
maintenance of the road. Routine maintenance activities are carried out independent of the level of
traffic on the road. If routine maintenance is neglected or not done properly, or money diverted to
other maintenance categories, the condition of the road will quickly deteriorate. The following
activities listed in Table 9.1 are routine maintenance activities
b. Periodic Maintenance
This is the work required only over a long period of time or once every few years to preserve the structural
integrity of the road. If routine maintenance are undertaken at the right time and effectively, periodic
maintenance may become warranted after a very long time. Table 9.2 contains the list of activities
classified as periodic maintenance.
o Resealing o Re-gravelling
o Resurfacing o Rehabilitation
o Rehabilitation o Upgrading
14
9.2.2 Condition survey
In order to assess the maintenance needs of a road it is necessary to undertake condition survey. The
survey involves visual inspection of the condition of the pavement and rating of the condition. The
rating of the pavement condition is based on the pavement’s distress features such as cracks, potholes,
fretting, spalling, raveling, pavement surface distortions, edge failure, patched up areas etc. The
survey will include a description of the characteristics and attributes of the defects in terms of
location, type, extent or severity level, position on the road and spacing. The recognition of defect
types and their severity is helpful in determining the degree to which the current condition of a road
departs from the acceptable standard and in determining where and when an intervention activity may
be needed and the maintenance activity for remedying the distress. For pavements that need
structural strengthening, it is based on the condition survey that a structural evaluation or survey
programme may be drawn up for execution.
The road system must be divided into categories with an inventory made of each road’s width, length, drainage,
signs, markings, etc. The information about the condition of the road is then compared with set standards in
order to assess the road. This makes it possible to summarize the scale and cost of remedial works needed to
return the road to an acceptable standard for its particular category.
The frequency of inspection may range from about 24 hours for urban principal roads, main shopping
areas, residential streets to about 2 times per year for rural non-principal roads.
Procedures:
a) Mark out area to be patched at least 150mm from the edge of the pot-hole and within sound
and undamaged pavement with paint. Include all failed areas within square or rectangular
area with at least two sides parallel to the direction of traffic flow.
b) Cut along the lines marked on the pavement surface so that the cut sides are vertical and the
bottom of the pot-hole is level and to a depth equal to:
the depth of the existing asphalt pavement that has been overlaid but of which the overlay
has failed
or
a minimum of 100-200 mm or at least equivalent to one and a half (1½) times the depth of
existing pot-hole, ensuring the excavation is in sound insitu material.
c) Remove loose and failed material, and ensure dust is swept or blown out of the excavated
hole.
d) Compact the bottom of the pot-hole prior to placing base material to ensure soundness and
flatness of the base
e) Back-fill hole in layers with approved base material not exceeding 150mm depth of loose fill
and compact ensuring uniformity of compaction over the whole area
f) Compact base material using suitable tampers or compaction equipment, starting around the
edges and working into the centre of the pothole and ensuring that all edges and corners are
compacted uniformly and in acceptable layer thickness up to the bottom of the nominated
depth of pre-mix or hot-mixed asphaltic concrete to be laid
g) Apply Emulsion at a Nominated Application Rate to all vertical faces and to the base of the
pot-hole and allow to break.
h) Wait until the emulsion breaks by turning from brown to black before adding asphaltic
concrete mix.
Note: Place the asphaltic concrete mix in holes in layers of 30mm for Pre-mix asphaltic concrete and
two and a half (2½) times the nominal size of the chippings used to manufacture the Hot-mixed
asphaltic concrete
i) Compact with suitable compaction equipment, with an emphasis on all corners and edges.
Always compact from the outside of the patch to the centre.
j) Repeat for each subsequent layer of asphaltic concrete mix placed until the final layer is laid
loose 25mm higher than the existing pavement
k) Rake and tamp any excess mix back from the existing pavement to the edge joint of the patch
making a vertical face of 45° and rake the top of the patch to a uniform level surface.
l) Firstly, compact only the outer 100mm of the patch around the whole perimeter to ensure that
the joint matches the existing pavement and that correct sealing of the joints occur.
m) Continue compacting towards the centre of the patch until the whole patch is uniformly
compacted without any depressions and allowing for the finished patch to be approximately
12mm above the existing pavement to accommodate for base subsidence.
16
n) Seal the edges of the patch with emulsion, spraying 50mm onto the old pavement and 50mm
onto the new patch and seal with 5mm chippings (aggregates) to waterproof the joint
o) Clean up and remove all spoil and waste materials from the site..
Quality of Work:
All cutting, backfilling and Asphaltic Concreting of pot-hole patches to be completed
on the same day that the areas were worked on.
Ensure successive base layers are compacted around all edges and corners and that
the base finishes at the nominated depth that the patch is to be filled with asphaltic
concrete
Ensure that the finished level of the asphaltic Concrete patched pot-hole matches the
line and grade of existing pavement, allowing the finished patch to be approximately
12mm above the existing pavement to accommodate for base subsidence
Ensure that the finished Patch has a uniform texture with good skid resistance and
that the finished patch drains satisfactorily to the road shoulders.
Procedures:
a) Determine and mark out with paint the area to be repaired, by using a string-line or a 4-meter
straight edge, laid on the pavement surface at the original grade on either side of the
depression, rut, shoving or corrugation and at least 150mm from the outer limits of the failure
within sound and undamaged pavement.
b) Cut along the lines marked on the pavement surface to form a rectangle, so that the cut sides
are vertical and to a depth of 300mm and finishing in sound material with the bottom of the
failure flat and level.
c) Remove loose and failed material, and ensure dust is swept or blown out of the excavated hole.
d) Compact the bottom of the excavated failure prior to placing base material to ensure soundness
and flatness of the base
e) Back-fill hole in layers with approved base material not exceeding 150mm depth of loose fill
and compact ensuring uniformity of compaction over the whole area
f) Compact base material using suitable tampers or compaction equipment, starting around the
edges and working into the centre of the failure and ensuring that all edges and corners are
compacted uniformly and in acceptable layer thickness up to:
1. Line and grade of the existing pavement if the patch is to be Bituminous Surface
Dressed, allowing the finished patch to be approximately 12mm above the existing
pavement to accommodate for base subsidence
Or
2. the bottom of the nominated depth of Asphaltic Concrete to be laid.
Bituminous Surface Dressing of Repaired Depression, Rut, Shoving or Corrugation
g) Apply Cut-back AC-10 Bitumen or Emulsion at a Nominated Application Rate
h) Spread Chippings (aggregates) of 14mm or 10mm as nominated in a single and uniform layer.
i) Roll or tamp chippings with suitable compaction equipment, ensuring chippings are not
crushed.
j) Note: For Multiple Surface Treatment, apply a second coat of Cut-back AC-10 or Emulsion at
a the Nominated Application Rate & apply a second layer of 10mm or 7mm chipping as
nominated in a single uniform layer and roll or tamp.
Pre-mixed or Hot-mixed Asphaltic Concrete Repaired Depression, Rut, Shoving or
Corrugation
17
k) Apply Emulsion at a Nominated Application Rate, to all vertical faces and to the base of the
pot-hole and allow to break.
l) Wait until the emulsion breaks by turning from brown to black before adding Asphaltic mix.
Note: Place the asphaltic concrete mix in holes in layers of 30mm for Pre-mix and two and a half
(2½) times the nominal size of the chippings used to manufacture the Hot-mixed asphaltic concrete
m) Compact with suitable compaction equipment, with an emphasis on all corners and edges.
Always compact from the outside of the patch to the centre.
n) Repeat for each subsequent layer of asphaltic mixture placed until the final layer is laid loose
25mm higher than the existing pavement
o) Rake and tamp all the mix back from the existing pavement to the edge joint of the patch
making a vertical face of 45° and rake the top of the patch to a uniform flat surface.
p) Firstly, compact only the outer 100mm of the patch around the whole perimeter to ensure that
the joint matches the existing pavement and that correct sealing of the joints occur.
q) Continue compacting in towards the centre of the patch until the whole failure is uniformly
compacted without any depressions.
r) Seal the edges of the patch with emulsion, spraying 50mm onto the old pavement and
50mm onto the new patch and seal with 5mm chippings to waterproof the joint.
s) Compact with suitable compaction equipment, with an emphasis on all corners and edges.
Always compact from the outside of the patch to the centre.
t) Repeat for each subsequent layer of asphaltic mixture placed until the final layer is laid loose
25mm higher than the existing pavement
u) Rake and tamp all the mix back from the existing pavement to the edge joint of the patch
making a vertical face of 45° and rake the top of the patch to a uniform flat surface.
v) Firstly, compact only the outer 100mm of the patch around the whole perimeter to ensure that
the joint matches the existing pavement and that correct sealing of the joints occur.
w) Continue compacting in towards the centre of the patch until the whole failure is uniformly
compacted without any depressions.
x) Seal the edges of the patch with emulsion, spraying 50mm onto the old pavement and
50mm onto the new patch and seal with 5mm chippings to waterproof the joint. Clean up and
remove all spoil and waste materials from the site.
Quality of Work:
All cutting, backfilling and Bitumen Surface Dressing or Asphaltic Concreting of
failures to be completed on the same day that the areas were worked on.
Bituminous Surface Dressing of Repaired Depression, Rut or Corrugation
Ensure finished base work of the patched pot-hole matches the line and grade of
existing pavement and allow the finished patch to be approximately 12mm above the
existing pavement to accommodate for base subsidence
Ensure that the finished Patch has a matt texture with good skid resistance
Ensure work site is left in a clean and safe condition with no loose aggregate on
pavement surface and adhering to environmental requirements
Ensure the finished patch drains satisfactorily to the road shoulders
Pre-mixed or Hot-mixed Asphaltic Concrete Repaired Depression, Rut Shoving or Corrugation
Ensure successive base layers are compacted around all edges and corners and that
the base finishes at the nominated depth that the patch is to be filled with asphaltic
concrete
Ensure the finished level of the Asphaltic Concrete patched pot-hole matches the line
and grade of existing pavement and allow the finished patch to be approximately
12mm above the existing pavement to accommodate for base subsidence
Ensure that the finished Patch has a uniform texture with good skid resistance and
that the finished patch drains satisfactorily to the road shoulders
18
Ensure work site is left in a clean and safe condition with no waste asphaltic concrete
mix on pavement surface, and adhering to environmental requirements
Monitor road for reoccurring depressions, ruts, shoving and corrugation and report on
their performance on a regular basis
Procedures:
a) Determine and mark out with paint the area to be repaired, by using a string-line or a 4-meter
straight edge, laid on the pavement surface parallel to the defined road edge and 300mm from
the outer limits of the failure within sound and undamaged pavement.
b) Cut along the lines marked on the pavement surface to form a rectangle, so that the cut sides
are vertical and to a depth of 300mm and finishing in sound material with the bottom of the
failure flat and level.
c) Remove loose and failed material, and ensure dust is swept or blown out of the excavated hole.
d) Compact the bottom of the excavated failure prior to placing base material to ensure soundness
and flatness of the base
e) Back-fill hole in layers with approved base material not exceeding 150mm depth of loose fill
and compact ensuring uniformity of compaction over the whole area
f) Compact base material using suitable tampers or compaction equipment, starting around the
edges and working into the centre of the failure and ensuring that all edges and corners are
compacted uniformly and in acceptable layer thickness up to:
1. Line and level of the existing pavement if the patch is to be Bituminous Surface
Dressed, allow the finished patch to be approximately 12mm above the existing
pavement to accommodate for base subsidence
Or
2. To the bottom of the nominated depth of Asphaltic Concrete to be laid
Bituminous Surface Dressing of Edge Failure
g) Apply Cut-back AC-10 Bitumen or Emulsion at a Nominated Application Rate
h) Spread Chippings (aggregates) of 14mm or 10mm as nominated in a single and uniform layer.
i) Roll or tamp chippings with suitable compaction equipment, ensuring chippings are not
crushed.
j) Note: For Multiple Surface Treatment, apply a second coat of Cut-back AC-10 or Emulsion at
a the Nominated Application Rate & apply a second layer of 10mm or 7mm chipping as
nominated in a single uniform layer and roll or tamp.
19
Ensure work site is left in a clean and safe condition with no loose aggregate on
pavement surface and adhering to environmental requirements
Ensure the finished patch drains satisfactorily to the road shoulders
Pre-mixed or Hot-mixed Asphaltic Concrete Repaired Edge Failure
Ensure successive base layers are compacted around all edges and corners and that
the base finishes at the nominated depth that the patch is to be filled with asphaltic
concrete
Ensure the finished level of the Asphaltic Concrete patched edge failure matches the
line, level and grade of existing pavement with a safe rounded shoulder drop-off
edge.
Ensure that the finished Patch has a uniform texture with good skid resistance and
that the finished patch drains satisfactorily to the road shoulders
Ensure work site is left in a clean and safe condition with no loose aggregate on
pavement surface and adhering to environmental requirements
Monitor edge failure repairs and report on their performance on a regular basis
Procedures:
a) Mark out the extent of road to be Resealed or Sealed by clearly painting a line across the full
width of the road pavement at the start and finish of the area to be sealed.
b) First: Repair Pot-holes and Edge Failures by the appropriate procedures
c) Sweep the full extent of the area to be sealed by Tractor Broom or Hand Broom to ensure all
dust and deposited dirt is removed from the road surface. Ensure that the operator or sweepers
take account of the wind direction to ensure that dust is not blown back onto the swept
surface
d) Mark with paint the start and finish of the initial bitumen sprayer run (i.e. Length) which will
be dependent on the amount of chippings in spreading trucks on site at the time of spraying.
e) Mark with paint, string-line or small stones the edge line for the sprayer driver to follow.
f) Paper the transverse joints at the start and finish of each run.
g) Set up the Bitumen Sprayer 20 meters back from the start of the run and ensure that the spray
bar is set to it’s correct width and that the driver’s guide bar is properly set and a Dip of the
Volume of Bitumen is measured and recorded along with the sprayer temperature.
h) Immediately behind the Bitumen Sprayer set-up the Chip Spreading Vehicles, followed
immediately by the Pneumatic-Tyred Rollers.
i) The Supervisor instructs the Sprayer Driver what the Hot Bitumen application rate is and
reads the correct road speed off the chart so as to set the vehicle speed.
j) The Bitumen Distributor sprays the required rate of Bitumen uniformly over the whole extent
of the work, without stopping until it has reached the designated finishing point and then the
driver/operator dips the distributor on flat ground so as to record the actual bitumen usage.
k) The Mechanical Chip Spreading equipment follows closely behind the Bitumen Distributor
spreading a uniform single layer of chippings and leaving a 150mm wet edge if needed for
the adjoining bitumen run, ensuring that complete coverage is achieved and that all chippings
required are distributed in the work zone.
l) Embed the chippings with the Pneumatic-Tyred Roller by following close behind and at a
speed of between 10-15km/hr to ensure that the whole mat is uniformly rolled in straight
runs. Rollers will continue rolling until instructed to stop and must ensure minimum rolling
time is observed.
m) Sweep any excess pile of chippings off the road and add chippings by hand as necessary.
20
Note: If a second coat seal is required immediately after laying the first coat repeat the same process,
ensuring that any excess loose chippings from the first coat is removed prior to the second coat.
Note: Offset Transverse joints on the second coat so as not to overlay the same position of first coat.
n) Open road to slow moving traffic and control vehicle speed to minimise whip-off of
chippings.
o) Clean up and remove waste materials and excess from shoulders, drains and site
Quality of Work:
The finished seal surface shall have a uniform Matt Texture with a single layer of
nominated chippings and a minimal amount of loose chippings (aggregate) on the
surface.
Ensure no transverse or longitudinal joints are raised or bleeding.
Ensure the Daily Spray Record Sheet is correctly filled out immediately after
completing each sprayer run, and that the bitumen and chipping spread rates meet the
Targeted Design Rate criteria.
Ensure that all loose chippings are removed from the site and road.
Ensure that adequate signage is in place to warn the public of the need to take care on
the new work in its early set-up stages.
Monitor sealed areas and report on their performance on a regular basis
Crack Sealing
Classification: Routine Maintenance (Paved Roads)
Procedures:
a) Initiate proper traffic control safety procedures at job site
b) Mark all areas prior to cleaning site to define the extent of work
c) Sweep clean or blow out cracks with compressed air over the area showing cracking ensuring
that the area is completely dry
Quality of Work:
Ensure all crack sealing is flush with the existing pavement and sealed onto the
existing pavement.
21
Ensure that the cracks are sealed with 5mm chippings to prevent pick up by vehicle
wheels.
Monitor crack repairs and report on their performance on a regular basis
Procedures:
a) Mark out the extent of road to be overlaid with asphaltic concrete by clearly painting a line
across the full width of the road pavement at the start and finish of the area to be overlaid.
b) First: Repair Pot-holes and Edge Failures, Depressions, Ruts, Shoving and Corrugation and
Cracks
c) Sweep the full extent of the area to be overlaid by Tractor Broom or Hand Broom to ensure
all dust and deposited dirt is removed from the road surface. Ensure that the operator or
sweepers take account of the wind direction to ensure that dust is not blown onto the swept
surface
d) Mark with paint and a string-line the edge line for the paver driver to follow and the
beginning and end of the paver run.
e) Set up the Bitumen sprayer or small hand spraying unit loaded with Emulsion at the start of
the run and commence lightly Tack Coating the area to be overlayed with emulsion at the
specified application rate
f) Align the Asphalt Paver at the commencement of the overlay run and set the screed to the
correct width and to the loose laying depth ( ie 12% higher than the compacted finished level)
g) Heat the screed board by use of the paver burners and back the first truck load of Asphalt into
the paver hopper
h) Test the temperature of the mix deposited into the hopper to ensure it is at the correct
temperature to lay
i) Drive paver forward, laying a uniform mat with minor corrections of the paving levels being
adjusted by the screed operator as necessary
j) The paver operator drives at an optimum speed to ensure that the paver and trucks supplying
mix are continuously moving
Note: The paver should never stop or start on the job, to pick up mix as this will result in depressions
and humps in the new pavement – (ensure that minimal forward progress by the paver is maintained
while filling paver hopper or waiting for the next load of mix)
k) The Raker tries to minimize damage to the new mat and only add mix or remove mix on low
or high points as necessary
l) With a steel drum vibratory roller, commence initial break rolling to the nominated rolling
pattern designated by the supervisor, ensuring that the vibratory unit is operating correctly
and that the watering units on the drums are preventing pick up
m) Follow the initial break rolling by the steel vibratory drum roller, with a pneumatic tyre roller
to knead the mat, until uniform texture is achieved throughout.
n) Finally, re-roll with the steel drum roller to eliminate any marks left by the pneumatic tyre
roller, as the final pass
Note: The rolling of the mat should take place as close to the paver as possible and while the
pavement still retains its heat
Note: Care must be taken in the rolling pattern to ensure the mat is not shoved, torn or over
compacted thereby requiring a skilled operator to undertake the initial rolling passes
Note: If Longitudinal joints or Transverse joints are within the work scope these must be rolled first
by crimping a 100mm overlap of the joint with the existing pavement to ensure proper joint closure
and line and level.
22
n) Open road to slow moving traffic and control vehicle speed in the initial stages of usage,
ensuring that vehicles do not get stopped for extended periods on the new mat when freshly
laid.
o) Clean up and remove waste materials and excess from shoulders, drains and site
Quality of Work:
The finished asphaltic concrete mat shall have a smooth homogenous texture
Areas of poor texture, rideability or any obvious flaw shall be removed for the full
width of the run and to a length nominated by the Supervisor and repaved
Cores shall be taken as per the Testing specification and tested to ensure conformance
of properties
Ensure that adequate signage is in place to warn the public of the need to take care on
the new work in its early set-up stages.
Monitor asphaltic concrete overlay and report on their performance on a regular basis
Procedures:
a) Mark out the extent of road to be graded.
b) Scarify the existing surface by ripping to a minimum depth of 50mm below the average
maximum depth of the overall pavement deformations, thereby loosening the material for
reshaping of the pavement
Grading Option 1: The Grader starts from the Centre-line and works to the edge
c) Commencing on one side of the road at the center-line and in passes no longer than 200
metres, the grader operator will commence to turn all the scarified material into a wind-row
of material, towards the outer edge of the road formation.
d) The grader turns around and returns on the opposite side of the center-line again turning
materials to the outer edge or the road.
e) Continue the looping pattern of grading until all material is wind-rowed on the outer edge of
the road formation. (this may take 2 or 3 passes to trim material to a solid sub-base)
Grading Option 2: The Grader starts from the Outer edge of the road formation and works to
the center-line and then onwards to the opposite outer edge of the Road formation
f) Commencing on one side of the road at the outer edge and in passes no longer than 200
metres, the grader operator will commence to turn all the scarified material into a wind-row
of material, towards the opposite outer edge of the road formation.
g) The grader either backs up or turns around after each pass and continues turning materials to
the opposite outer edge of the road.
h) Continue the pattern of grading until all material is wind-rowed on the outer edge of the road
formation. (this may take 2 or 3 passes to trim material to a solid sub-base)
Compaction requirements and new sub-base placement:
i) Compaction equipment is then used to proof roll the undisturbed sub-base from outside of the
road to the centerline, so as to ensure maximum density and uniformity of line and level by
the rollers looping around the work site from outside to the center-line
j) Ensure that a clearly defined Crown in the formation is aligned up the center of the road
k) Turn windrowed material back into excavated areas in layers not deeper than 150mm and add
water to the loosely packed gravel.
l) Remove all materials greater than 100mm by hand from the surface prior to compaction
m) Start compacting the layer of loose material from the outside of the road into the centerline
n) The grader operator will repeat the process of spreading the old gravel and having the layers
compacted, up to the new gravel replacement level.
23
o) New sub-base material will be dumped at measured intervals along the job site as calculated
by the Supervisor/Contractor dependent on the nominated compacted fill depth.
p) The grader operator will spread the new gravel up to the finished surface level ensuring that
the correct camber, cross-fall and alignment are at the required depth and that all excess
material is graded beyond the pavement and not impeding water shed
q) Completing one half of the road at a time up to the crown level and alignment.
r) Compact the finished layer to a hard dense uniform surface.
s) Cross-falls shall be checked by use of a camber board at intervals no greater than 25meters.
t) Repeat the process on the opposite side of the gravel road ensuring shape and profile of cross
section of the road is maintained.
u) Clean up and remove waste materials and excess from shoulders, drains and site
Caution:
The grader should not make a final pass down the center line of the road with a
horizontal blade as this destroys the crown and will cause flattening and ponding in
the center of the road
Turnouts have to be cut to ensure that water is led away from the edge of the road by
following the natural contour.
No stockpiles of material should be left on the road overnight without adequate
barriers and signage designating the area
Quality of Work:
All planned work shall be completed and closed in one day to ensure the road is open
to traffic overnight without creating a hazard to the traffic.
The finished pavement shall be dense and hard of uniform texture with correct
alignment, cross-fall and camber
All excess material has to be removed from the pavement and edges ensuring a clean
work site with good drainage
Ensure that adequate signage is in place to warn the public of the need to take care on
the new work in its early set-up stages.
Monitor re-gravelled road and report on its performance on a regular basis
Procedures:
a) Mark out area to be cleaned by designating with flags or marker poles the extent of the length
of ditches to be cleaned by manual means.
Unlined Drain:
b) Cut and remove all large trees and shrub that has commenced growing within drain.
c) Trim all grass within drain to a height of less than 50mm leaving a short grass cover
throughout the extent of the ditch
d) Remove any silt build up or rubble and rubbish that have been deposited in the invert of the
ditch to eliminate all possibility of ponding.
e) Check the invert of the ditch to ensure sufficient fall to remove water and dig out depth of
ditch as needed to facilitate water flow
f) Clear and widen outfall or add turn-outs as needed to ensure that water flows away without
creating a scour at the end.
g) Where digging is needed ensure the side walls of the ditch have a slope between 1:1 and 2:1
thereby minimizing the possibility of scouring and erosion of invert and side walls
24
Lined Drain:
h) Dig out and remove all silt and rubbish build up throughout the length of the ditch
i) Pull out, chip or poison any weeds and plants growing through the lining of the drain
j) Clear and widen outfall to ensure the water flows away without creating a scour at the end.
k) Clean up and remove waste materials and rubbish from site.
Quality of Work:
Ensure ditches are clear of all deleterious material and that water flows freely with a
minimum of scouring or erosion action at end of the day.
Ensure slopes of ditches are stable and not susceptible to erosion and slumping.
Ensure that cut-off and turnout drains are adequately spaced and properly cleared to
minimize silt build up and to ensure that water escapes on a broad flow
Ensure work site is left in a clean and safe condition with all rubble and rubbish removed
Premix is a mixture of graded aggregate and cutback asphalt used for patching paved roads. The cold
mixture is prepared in the following manner:
1. Cutback formulation
The cutback asphalt is prepared by mixing kerosene with 80/100 pen grade asphalt. The asphalt is
heated to a temperature of 80-90oC before the required quantity of cutter (kerosene) is added. A
quantity of 36 litres (8 gallons)of kerosene is required for mixing with one drum or 153 litres of the
asphalt in order to obtain approximately an 80 percent cutback. The kerosene is added in increments
of 5 litres at a time and thoroughly stirred to ensure good mixing before the next increment.
2. Gradation of aggregates
The gradation of the aggregates to be used in the premix is as follows
3. Quantity of cutback
About 5.5% cutback by weight of aggregates is required to obtain a workable and durable pre-mix. In
the case where the proportion of fine material in the mix is on the high side, the quantity of cutback to
use for the premix may be adjusted upwards to 6%.
25
10. Quality Control of Road Works
10.1 Introduction
In Ghana, road works whether new development or maintenance, are generally executed
by contracting. A contract is a legal agreement between two parties where one party
agrees to carry out certain works in return for a reward (or in legal terms a consideration
usually of money) to be given by the other party in the contract. The party which agrees
to do the work is called the Contractor whilst the other that pays for the work or the
owner is referred to as the Employer or Client.
Prior to any construction of works, the Employer or Client employs an engineer to design
the solution scheme and to prepare contract documents comprising drawings,
specifications, bills of quantities and others. These documents are then sent to contractors
to tender for the work,. The Contractor who wins the contract for the road works and the
Employer then sign and go into a contract for the execution of work.
During work execution, the works must be monitored and controlled to ensure that a
high quality product is achieved and within budgetary allocations and that the finished
product is indeed what was specified. Monitoring or quality control is the joint
responsibility of the Contractor and the Client and it must be a continuous effort
throughout the construction process. Three important questions to pose and answer in
order to ensure the quality of the construction works are:
What are the items and areas to control?
What guides the control process?
What is to be done in the case of substandard works?
These and many more are questions that border on real situations that characterise
contracts in road works. A contract and the accompanying conditions must endeavour to
address all these problems to the extent humanely possible so that the road works do not
suffer any major setbacks in quality and budget.
1
can be achieved. Quality control and assurance are achieved in three separate but related
areas:
a. Materials control
b. Work control
c. Quantity control
For each of the above control areas, the activities and procedures required may comprise
one or more of the following:
Checking that appropriate instructions are given and any information required by
the Contractor is supplied in good time.
Checking that materials and workmanship are satisfactory and as specified, and
where necessary, issuing instructions for remedying faulty works or replacing sub
standard materials.
Checking lines, levels, layout etc. of the works to ensure conformity with the
drawings.
Issuing further instructions, drawing and clarifications of details as are necessary
to ensure satisfactory construction of the works.
Measuring the volume of work done
Undertaking all tests required and keeping records thereof
Reporting on all the foregoing to the Engineer/Consultant in the form he requires.
2
b. The quality of workmanship and material required.
For example, soils for use in building the pavement structure must be checked to see if
they meet the requirements in terms of
Gradation
Atterberg Limits
Strength characteristics (measured by California Bearing Ratio- CBR)
Aggregates for Portland cement concrete works (such as bridge and drains and culvert
construction, retaining walls), asphalt concrete formulation, surface dressings, etc, must
be checked to see that they conform to the specification requirements for such works. The
properties to check will include;
Shape
Strength
Abrasion resistance
Affinity for bitumen
Durability
In the case of bitumen, it must be ascertained that the material is of the right grade or
consistency (hardness if solid or viscosity if liquefied).
In asphalt overlay construction, material control will involve
Gradation of the aggregates for the mix
Asphalt content of the mix
Stability of the mix
Density and voids of the compacted overlay
3
For any of the above and other road building materials, samples that fail to meet
specification requirements must not be allowed for use. Where substandard materials
have been used, the contractor must be ordered to remove them and replace with
approved material meeting the quality requirements contained in the specifications
4
10.6 Quantity control
Quality control also requires that quantity is controlled in accordance with design and
drawings. Quantity items to control include
Length
Width
Depth or thickness
Volumes
Height
Angles
Elevations
Densities
No. of culverts, etc.
10.8 Recording
Good record keeping and documentation are essential to the Resident Engineer’s ability
to monitor and control the project and to deal with substandard work. Records should be
kept of
weather,
mistakes made by the Contractor,
defective construction and their location
quality test results
field inspections
5
field tests and results
items supplied for construction
sections of the roads for which certain items were used
instructions given to the Contractor and verbal agreements reached with the
Contractor.
Where possible photographic documentation may be employed to supplement the
record keeping. Each photograph is dated and location, subject and photographer
noted. These photographs are kept in a central album to be used in case of any
litigation.