Work Method
Of
Page 1 of 46
Construction of Kadamrasul bridge over the river Shitalakhya near Mir Akhter Hossain Ltd.
5No. Gudaraghat of Narayanganj City Corporation (NCCKB)
Project.
Table of Contents
1. Purpose........................................................................................................................................6
2. Scope...........................................................................................................................................6
3. Normative References.................................................................................................................6
4. Organization................................................................................................................................6
4.1 Head Office Organization Chart.........................................................................................6
4.2 Site Management team with Organization Chart................................................................7
4.3 Responsibilities of the Authorities......................................................................................7
5 Programme of Works..................................................................................................................8
5.1 Items of Works....................................................................................................................8
5.2 Scheduling of Work Plan....................................................................................................9
5.3 Scheduling of Manpower Deployment...............................................................................9
5.4 Scheduling of Equipment Deployment.............................................................................10
5.5 Scheduling of Procurement of Major items of Materials..................................................10
5 Key Resources...........................................................................................................................10
5.1 Equipments........................................................................................................................10
5.2 Staff and Personnel...........................................................................................................10
6 Works under the Scope.............................................................................................................11
6.1 General Preparatory Works...............................................................................................11
6.2 Coordination and Management of Interfaces....................................................................12
6.3 Mobilization of Manpower and Equipments.....................................................................12
6.3.1 Introduction.................................................................................................................12
6.3.2 Mobilization Plan............................................................................................................13
6.4 Selection and Establishment of Base Camp......................................................................14
6.5 Survey Work.....................................................................................................................14
6.6 Planning and Scheduling...................................................................................................14
6.7 Time Control & Progress Meeting......................................................................................15
6.8 Progress Photographs, Reports and Meeting....................................................................15
6.9 Daily Record, Weekly/Montly Return..............................................................................15
6.10 Quality Control & Quality Assurance...............................................................................16
6.10.1 Quality Control...........................................................................................................16
6.10.2 Quality Assurance.........................................................................................................16
6.11 Safety Management Program..........................................................................................16
6.12 Health, Environment & Safety Commitment....................................................................18
6.13 Communication.................................................................................................................19
Page 2 of 46
Construction of Kadamrasul bridge over the river Shitalakhya near Mir Akhter Hossain Ltd.
5No. Gudaraghat of Narayanganj City Corporation (NCCKB)
Project.
Page 3 of 46
Construction of Kadamrasul bridge over the river Shitalakhya near Mir Akhter Hossain Ltd.
5No. Gudaraghat of Narayanganj City Corporation (NCCKB)
Project.
9 Construction of Rc Piers (Pier Head, Pier Shaft and Pile Cap), Rc Abutment and Wing Wall36
9.1 Pile Head Breaking and removal.........................................................................................36
9.2 Blinding Concrete.................................................................................................................36
9.3 Steel Reinforcement............................................................................................................36
9.4 Form work & Scaffolding.....................................................................................................37
9.5 Mixing of Concrete..............................................................................................................37
9.6 Pouring and placing of Concrete.........................................................................................37
9.7 Pocking and compaction....................................................................................................37
9.8 Curing..................................................................................................................................37
9.9 Removal of form work........................................................................................................37
10 Construction Procedure for The Construction of Precast Prestressed Girders...........................38
10.1 Bed preparation.................................................................................................................38
10.2 Form work.........................................................................................................................39
10.3 Placing of Pre-stressing Materials.....................................................................................39
10.4 Concreting.........................................................................................................................40
10.5 Post-Tensioning................................................................................................................41
10.6 Calibration........................................................................................................................41
10.7 Recording elongation........................................................................................................42
10.8 Grouting............................................................................................................................42
10.9 Lifting and Shifting of Girders.........................................................................................43
10.10 Construction Method RC deck Slab...........................................................................44
10.11 Concrete slope protection..............................................................................................45
10.12 Scouring Protection at Pier Base...................................................................................45
Page 4 of 46
Construction of Kadamrasul bridge over the river Shitalakhya near Mir Akhter Hossain Ltd.
5No. Gudaraghat of Narayanganj City Corporation (NCCKB)
Project.
List of Appendices
Page 5 of 46
Construction of Kadamrasul bridge over the river Shitalakhya near Mir Akhter Hossain Ltd.
5No. Gudaraghat of Narayanganj City Corporation (NCCKB)
Project.
1. Purpose
This method statement has been prepared to demonstrate sequential construction work procedure and
work method for Construction of Kadamrasul bridge over the river Shitalakhya near 5No. Gudaraghat
of Narayanganj City Corporation (NCCKB) Project.
2. Scope
The project is about the Construction of Kadamrasul bridge over the river Shitalakhya.The works
included providing Preliminary, General and Site Facilities, Sub-soil Investigation including
topographic survey, Viaduct Substructure, Viaduct Superstructure, Main Bridge Substructure, Main
Bridge Superstructure, Environmental Safety and Management and Electrical Works. Total Length of
Bridge 1154m.Main bridge length 380m and Viaduct length(Narayanganj end) 494m and
Viaduct(Nabiganj end) 280m.Ramp length (Narayanganj end) 160m and Ramp length(Nabiganj
end)75m.Width of Deck slab(Main Bridge)12.80m,Width of Deck slab(Narayanganj end)12.80m and
Width of Deck slab(Nabiganj end)10.40m.
3. Normative References
Head Office Organization Chart -See Appendix A
Site Management team with Organization Chat - See Apendix B
Staff and Personnel - See Appendix C
Schedule of Work Plan - See Appendix D
Manpower Deployment Schedule - See Apendix E
Equipment Deployment Schedule - See Apendix F
Procurement Schedule of Major items of Materials - See Apendix G
Layout Plan of Contractor site office - See Apendix H
HSE Policy - See Apendix I
4. Organization
The head office organization chart specifically refers to the central or main office of a company or
organization. The project director holds the highest position in this chart from the perspective of
construction and maintenance. The other officials play various roles in communicating with the site
office.
Page 6 of 46
Construction of Kadamrasul bridge over the river Shitalakhya near Mir Akhter Hossain Ltd.
5No. Gudaraghat of Narayanganj City Corporation (NCCKB)
Project.
Project Manager:
The Project Manager has the overall responsibility for this procedure and will be handled
by a competent person.
Senior Structural Engineer:
A Senior Structural Engineer is a highly skilled professional with extensive experience and expertise
in the field of civil engineering, specializing in the design, analysis, and management of various
structures. This role involves leading the structural design process, ensuring compliance with codes
and standards, and overseeing projects from conception to completion. A Senior Structural Engineer
provides technical leadership, mentors junior engineers, and collaborates with multidisciplinary
teams. With a focus on quality assurance and client interaction, they play a pivotal role in ensuring
the safety, durability, and functionality of structures. Key qualifications include advanced education
in civil or structural engineering, professional licensure, significant industry experience, proficiency
in structural analysis software, and strong communication and leadership skills.
Material and Quality Control Engineer:
Responsible for different field and laboratory tests relating to construction material & works of the
project. Responsible for Quality control of all RCC works, Pile Works, fixing of shutter, admixture,
stressing and grouting, carry out field quality control tests. These entire tests were done with ASTM,
BS and AASHTO Test procedure. Monitoring of all types of laboratories testing as required as
follows: Mix design of different grade of concrete, Slump test, concrete strength, Cement setting
time, tensile strength of steel, FM of sand etc.
Site Supervision Engineer (Civil):
The Site Supervision Engineer (Civil) is in control of Plan, organize, train, evaluate, and supervise
subordinate staff's work; assist subordinate engineering staff with difficult engineering problems;
Page 7 of 46
Construction of Kadamrasul bridge over the river Shitalakhya near Mir Akhter Hossain Ltd.
5No. Gudaraghat of Narayanganj City Corporation (NCCKB)
Project.
plan, organize, and direct office and field engineering staff in conjunction with public works
construction and improvement.
5 Programme of Works
Page 8 of 46
Construction of Kadamrasul bridge over the river Shitalakhya near Mir Akhter Hossain Ltd.
5No. Gudaraghat of Narayanganj City Corporation (NCCKB)
Project.
Page 9 of 46
Construction of Kadamrasul bridge over the river Shitalakhya near Mir Akhter Hossain Ltd.
5No. Gudaraghat of Narayanganj City Corporation (NCCKB)
Project.
5 Key Resources
5.1 Equipments
Equipment List
No Equipment Name Model and Capacity Number Remarks
CAT 745C-RS, UK/Singapore
i. Articulated Haulers 4 Nos
(100 cum per day)
SANY-China & XCMG – China
ii. Excavator 2 Nos
(Capacity 10 cum/hr)
SIMEM JUMPER-1500, India
Concrete Batching KYB – CONMAT, India (Model: CRP600IL
iii 2 Nos
Plant
(Capacity - 60 cum/hour)
Transit concrete KYB – CONMAT, Graves-India
iv 2 Nos
mixture machinery (Capacity – 7 CBM)
Shantui-China
v Dozers 2 Nos
(Capacity 20 cubic meter per hour)
Caterpillar (Model-C5533E)
vi Soil compactors 2 Nos
(2-3 tons Capacity)
Dynapac – India (Model: CC425)
vii Road Rollers 2 Nos
(Capacity 8-10 Tons)
VOGELE (Super 1800-3), Germany (250
viii Pavers 2 Nos
sq.m per 8.00m width)
HLCM, China (Model: QLM II 100/10-
ix Gantry crane 2 Nos
16/12) (100 Tons Capacity)
SANY- China (Capacity 60 ton), Kobelco-
x Crawler Crane 2 Nos
India
Kobelco – Japan (Model F&G-622) (10,000
xi Floating crane 2 Nos
Tons Capacity)
Hydraulic rig for Soilmec (SR-40) - Italy and XCMG-China
xii 2 Nos
boring of piles
Page 10 of 46
Construction of Kadamrasul bridge over the river Shitalakhya near Mir Akhter Hossain Ltd.
5No. Gudaraghat of Narayanganj City Corporation (NCCKB)
Project.
Conducting detailed
topographical survey. Construction of Site Office.
Bridge lighting&Thunder
Protect.
Page 11 of 46
Construction of Kadamrasul bridge over the river Shitalakhya near Mir Akhter Hossain Ltd.
5No. Gudaraghat of Narayanganj City Corporation (NCCKB)
Project.
6.3.1 Introduction
The intent of this mobilization plan is to represent the general sequence on how the project will
commence. This involves the number of personnel, equipment’s and materials. However, this plan
summarizes the proposed methodology for executing various phases of the site. This has to do with
the integration of personnel, equipments, materials, and the use of the site for staging, stockpiling and
Page 12 of 46
Construction of Kadamrasul bridge over the river Shitalakhya near Mir Akhter Hossain Ltd.
5No. Gudaraghat of Narayanganj City Corporation (NCCKB)
Project.
other activities, and security. Upon Close of Contract, we will establish a Contract Mobilization Team
led by the Project Manager to develop and coordinate all contract mobilization tasks. The Contract
Mobilization Team will prepare a fully developed and detailed Mobilization Plan.
Page 13 of 46
Construction of Kadamrasul bridge over the river Shitalakhya near Mir Akhter Hossain Ltd.
5No. Gudaraghat of Narayanganj City Corporation (NCCKB)
Project.
xvi. Dumping area will be selected for surplus soil from excavation.
They will also establish coordinates of each structure existing on the roadway, field proposed road
alignment, cross sections, bench mark, reference points etc. on the basis of approved drawing &
direction as well as supervision of the Engineer’s representative. Necessary protective measures will
be taken to safe guard the above works against any possible damage. From the survey work they will
prepare shop drawing showing alignment of boundary fencing, location of different structures
including location of Engineer’s and contractor’s site facilities, cross sections at different locations,
estimate volume of earth work to be undertaken, identify the location of obstructions etc. which will
be submitted to Engineer for his approval. Limit of the embankment shall be set out by fixing wooden
pegs at intervals of 25m. The pegs shall be fixed 0.5m beyond the actual limit of embankment or
further away in case widening of embankment is required for diversion of traffic
Page 14 of 46
Construction of Kadamrasul bridge over the river Shitalakhya near Mir Akhter Hossain Ltd.
5No. Gudaraghat of Narayanganj City Corporation (NCCKB)
Project.
Page 15 of 46
Construction of Kadamrasul bridge over the river Shitalakhya near Mir Akhter Hossain Ltd.
5No. Gudaraghat of Narayanganj City Corporation (NCCKB)
Project.
We shall also submit a video record of the work progress during the month. The video record shall be
at least 30 minutes in duration and it shall be submitted at 6 months interval in three electronic (CD )
copies, in a format approved by the Engineer.
Page 16 of 46
Construction of Kadamrasul bridge over the river Shitalakhya near Mir Akhter Hossain Ltd.
5No. Gudaraghat of Narayanganj City Corporation (NCCKB)
Project.
As full pledged laboratory shall be established to facilitate time to time testing of materials & works
at site etc. during execution of work. Routine test of aggregate, sand, soil, cement, bitumen etc. shall
be carried out at site regularly maintaining minimum frequency of testing for process control. On
completion of every part of work results of relevant test, measurements & levels indicating
compliance with the specifications shall be submitted to the Engineers. A sample estimation shall be
maintained to ensure tractability to all samples taken from the works. Special testing for reinforcing
bar, water, bitumen shall be carried out in approved laboratory preferably BUET/ KUET/RUET.
6.10.2 Quality Assurance
A quality control team headed by Quality Control Manager assisted by Material Engineer, Laboratory
Technician and number of quality control inspectors shall maintain Quality Assurance. Sources of
procurement of construction materials will be inspected and samples will be collected and tested in
the field laboratory or any other suitable laboratories prior to purchase of the same with a view to
assuring that the quality of the materials conforms with the specification, so that no inferior or
defective materials are brought to job site, Close vigilance will be taken so that suppliers and
manufacturers refrain from supplying unspecified or under specified materials
In order to ensure safety of professionals and workers at site, due care and attention shall be paid
during for site preparation works, sand filling works and operation of electrical equipment and other
aspects that may cause construction hazards. The implementation of Safety Management Program at
site will start from the time, the possession of site is taken by us & shall end after the completion of
work and handing over of the project to the company.
In order to ensure accident free work at site the following safety measures will be completed &
responsibility for the securely and safe working environment of the site shall be maintained:
1. Training: The safety inspector will train the workers regularly and will disseminate all
information pertaining to Government safety laws and general safety codes for maintaining
minimum risk exposure within the working environment.
Page 17 of 46
Construction of Kadamrasul bridge over the river Shitalakhya near Mir Akhter Hossain Ltd.
5No. Gudaraghat of Narayanganj City Corporation (NCCKB)
Project.
2. Equipment: All equipment engaged at site shall be maintained in trouble free good working
condition.
3. Inspection: The safety Inspector will conduct continuous inspection of equipment & related
items to ensure proper functioning & prime safety in operation of works related to excavation
& embankment works dredging works etc. The site inspectors will identify all hazardous
zones taking into account all sources of hazards under normal and abnormal conditions. He
will also ascertain special requirements concerning nature and handling as well as storage of
all inflammable materials like fuel, gases, chemical etc. and provide plant, equipment & other
services accordingly, including all functions to ensure safety of the operating and maintaining
persons together with all other workers at site. Hazardous materials, inflammable materials,
gas cylinders etc. will be stored at a separate protected place at a safe distance from the
working place. Product level & material safety data sheet provided by the
manufactures/suppliers of each imported material will be strictly followed before use of the
concerned materials in respect of accidental release measures, handling and storages, exposure
control/ personal protection etc.
4. Disciplinary action: A site Safety manual for the project will be prepared and enforced at
working site. Any worker/personnel violating any provision of the safety codes will be
brought to book and punished according to the gravity of the offence in conformity with the
prevailing rules and regulations of the country.
i) Easy access and exit of Fire Fighting Vehicles to and from project site
ii) Easy access and exit to and from First Aid Equipment
b) Sufficient numbers of security guards will be engaged and posted round the clock at
gates and other positions with uniforms, batons and torchlight etc. for protection.
Security Inspectors will be on round to supervise them particularly during night.
Entrance of outsiders inside the project will be prohibited and workers shall be
provided with Identity Cards.
c) Proper lighting of the storage area, working area and camp area will be made with
temporary posts providing with search lights for area lighting for safety and security.
Sufficient number of rechargeable lights will be kept for emergency purposes in case
of power failure.
Page 18 of 46
Construction of Kadamrasul bridge over the river Shitalakhya near Mir Akhter Hossain Ltd.
5No. Gudaraghat of Narayanganj City Corporation (NCCKB)
Project.
a) Personnel protective equipment (PPE) like clothing for handling hazardous materials,
goggles, shoes, helmets, safety belt, safety nets, handling of electrical appliance will
be provided to them.
c) Construction plants and equipment will be operated only by skilled and trained
personnel to avoid accident from mishandling and lack of knowledge.
d) Prior to commencement of each stage of the work a job safety analysis shall take place
to identify hazards and develop procedures to minimize hazards and prevent
occurrence of accident.
e) All incidents, injuries and near misses shall be investigated and documented with
corrective actions on incident reports.
f) Safe access shall be provided to all areas required to perform the works.
g) Different insurance policies like personnel accident policy and workmen compensation
policy etc will be made, so that the personnel and workers, in the project can be
compensated against any loss/damage caused due to accident at site.
h) It will be ensure that no open electric cable is left scattered at any place in the project
to avoid accident.
ii. Warning sign with no smoking / no fire at important locations will be installed.
iii. First aid box with necessary medicine and trained personnel will be provided in the camp for
giving first aid, if necessary and first aid service shall be made available full time when work is in
progress.
iv. Contractor must act following or in accordance with Environmental Management plan which has
been provided with the tender as Volume 2 of 3 of the Employer’s Requirements.
v. A detail of environmental management system shall be prepared and submitted to the Engineer
for approval.
vi. An Environmental Management Officer shall be deployed and be available at site whose duties
throughout the construction period shall be entirely connected with environmental management at
site.
Page 19 of 46
Construction of Kadamrasul bridge over the river Shitalakhya near Mir Akhter Hossain Ltd.
5No. Gudaraghat of Narayanganj City Corporation (NCCKB)
Project.
vii. Daily environmental reports shall be submitted to the Engineer as required by the Environment
Management Plan. A summary report shall be submitted as part of the Monthly Progress Report.
viii. Alternate weekly Joint Inspection shall be arranged relating to Environmental, Health and Safety
at Site/ Base Camp/ Site Accommodation/ Field Offices and weekly report shall be submitted to
the Engineer as required by the Environment Management Plan. A summary report shall be
submitted as part of the Monthly Progress Report.
ix. Dust suppression arrangement shall be available with providing a water bowser and water pump
at site.
x. Garbages and other wastage material shall be collected and disposed to a safe designated place
thus do not produce contamination or pollution of flowing water channel/ river or stagnant water
bodies etc.
xi. Fuel and chemicals shall be stored and precaution shall be taken to avoid spillage of such
materials during delivery for work or refueling vehicle and equipment.
6.13 Communication
Communication will be made through written formal, written informal, oral formal and oral informal
basis depending on with whom the communication is made. Communication will be made by
establishing multiple communication channels and using simple language within and outside the
company, between functional segments of the company like top management, middle management
and field management as well as various outside parties like client, consultants and various other
authorities related with the project. Information regarding implementation of quality control measures
will be communicated to the Project Manager by the Quality Control Lab Manager/ Material
Engineer. The Information will be monitored and appraised periodically during progress of work and
corrective measures shall be taken in time. Communication for obtaining approval for different
materials will be made by filling up and submitting prescribed formats to the approving authorities
where particulars regarding manufacturers/ suppliers will be provided.
Communication with people outside the project will be made by installing telephone, internet and fax
at the site office. In addition, cellular mobile phone shall be used within / outside the project area for
easy and prompt communication to all concerned.
Page 20 of 46
Construction of Kadamrasul bridge over the river Shitalakhya near Mir Akhter Hossain Ltd.
5No. Gudaraghat of Narayanganj City Corporation (NCCKB)
Project.
Necessary police & other Govt. officials shall be contacted in case of necessity for control of traffic
and other matters related to provide of traffic.
7 Construction method
7.1 Temporary Diversion Road
Page 21 of 46
Construction of Kadamrasul bridge over the river Shitalakhya near Mir Akhter Hossain Ltd.
5No. Gudaraghat of Narayanganj City Corporation (NCCKB)
Project.
From the date of Commencement of the Works to the date of issue of Taking over Certificate for the
whole of the works as stated in the Contract, we shall be responsible for maintaining uninterrupted
passage of vehicles and pedestrians along the temporary traffic diversion road that may need to
construct.
The specific location of any detour or diversion should be depends on site condition i.e where the
alignment of proposed new bridge falls on new alignment beyond existing bridge, existing bridge
shall be used as detour. So, separate diversion does not need in this case. But where the alignment is
on the existing bridge, prior to dismantling of existing bridge a detour should be provided by
construction of steel baily bridge of 3.5 m clear carriageway over the canal/ river.
Both end approach of baily bridge should be constructed by filling embankment as per specification
of roadway embankment with proper treatment of embankment bed if needed.
The diversion/ detour road should be paved with 6.00 m and 1.5 m earthen shoulders on either side.
Pavement of temporary diversion road should be preferably of HBB over one layer brick flat soling.
Clearing and grubbing shall be carried out by removing trees, stumps, roots, water hyacinth etc. &
disposing off the debris & vegetation within available limits. All surface objectives, stumps, roots and
other obstructions shall be removed. After removal of the debris’s vegetation and obstructions, the
top soil shall be cleaned up and removed to required depth as per specification and stock pile at a
designated area for future reuse in the project.
Demolition of structure: This work shall include demolition of bridges, culvert & other structures and
building within the ROW required to complete the works, which will be carried out as per
specification & with the prior approval of the Engineer. The salvaged materials receivable from the
demolition of different structures except baily bridge & steel bridge shall be the property of the
contractor which will be recycled and reused for sub base/ pavement construction with prior approval
from the Engineer in charge.
7.2.2 Removal of Existing Pavement
The removal of existing pavement shall consist of removal of base, sub base course aggregate etc.
Prior to removal of existing pavement, trial pits and trenches shall be made to ascertain the depth and
composition of the pavements by the Engineer.
All bituminous, seal coat, wearing course, leveling course and bricks shall be removed by
mechanically or manually. All recovered materials shall belong to the contractor as per specification
and all suitable materials shall be recycled/ reused with the approval of the Engineer.
Page 22 of 46
Construction of Kadamrasul bridge over the river Shitalakhya near Mir Akhter Hossain Ltd.
5No. Gudaraghat of Narayanganj City Corporation (NCCKB)
Project.
This will include excavation for water channel & for the foundation of bridges, retaining walls,
culverts & any other structures not otherwise prescribed. Cofferdams & false inland shall be
constructed for construction of bridges/ culvert along with dewatering as per requirement.
There are areas along the alignment where the road foundation under the embankment fill may
require soft ground treatment and strengthening prior to placement of embankment material, to
stabilize the foundation using specialized techniques as directed by the Engineer.
One layer of separation geotextile filter fabric shall be placed, as directed by the Engineer, over the
prepared ground surface in areas that remain soft, unstable and muddy due to proximity to the ground
water table, before installing the granular drainage blanket. Joints shall be overlapped by a minimum
of 0.5 m or if sewed together with a minimum overlapped of 0.25 m.
Vehicles or construction equipment shall not be allowed on the filter fabric until a sufficiently thick
layer of drainage blanket has been placed carefully so as not to damage the fabric.
Any clay from the sand drain placement operations that contaminates the working surface shall be
removed.
Page 23 of 46
Construction of Kadamrasul bridge over the river Shitalakhya near Mir Akhter Hossain Ltd.
5No. Gudaraghat of Narayanganj City Corporation (NCCKB)
Project.
This will consist of construction of the embankment including preloaded embankment & berm as
well as back fill not specified elsewhere as per specification by furnishing, placing, compacting and
shaping suitable materials as per specification to the line levels and grades, dimension and cross
sections according to drawing and direction by the Engineer. Prior to placing of any fill materials all
clearing, grubbing shall be completed.
Necessary precaution and safety shall be maintained for the dredge fill work to avoid hindrance of
route for ship, water vessel and cargo etc. Series of beacon light shall be hoisted over the delivery
pipe as well as on the dredger for warning at night time.
Before commencement of dredge fill work, earthen ring dyke to be constructed outer periphery of
filling area either cutting earth by excavator from inner side of the same if available or carried earth
by dump truck and spreading by bull dozer. Ring dyke so constructed to be maintained & repair until
filling work completed up to desired sub-grade level. Thick polythine paper may be placed over inner
side slope of dyke for protection the dyke from leakage or damage etc. An outlet will be provided for
facilitation to dispose of excess water accumulated from dredge fill material that will be connected by
pipe / earthen drain to a disposal point preferably nearby culvert or channel. The disposal pipe /
earthen drain will be maintained following standard of HES procedure without creating any hazard or
affecting surrounding agricultural land, fishery, poultry, dairy, domestic firm etc. Bull dozer will be
used for spreading materials and soil compactor will be used for compaction.
b) In case of locally arranged borrow materials outside the project area excavator will be used for
cutting earth and dump truck/ tipper for carrying filling materials. The materials shall be laid in layers
not exceeding 200 mm thickness. The above layer shall be watered and properly compacted with 8-
10 Ton Vibro Roller and tested before the next layer is placed. Provision for drainage of rain water
shall be kept during the process of earth filling and compaction
This item shall consist of clayey silt with a plasticity index in between 10 to 20% for use on dredged
sand embankment having thickness 600 mm. Carried earth will be used in accordance with
specification and in conformity with lines, levels, grades or typical cross section or as established by
the Engineer, following construction method same as road way embankment. Spreading &
compaction of cladding layer will be performed by excavator and mini roller.
Page 24 of 46
Construction of Kadamrasul bridge over the river Shitalakhya near Mir Akhter Hossain Ltd.
5No. Gudaraghat of Narayanganj City Corporation (NCCKB)
Project.
Embankments shall be constructed in layers of uniform thickness ( not more than 200 mm lose )
approximately parallel to the finished grade of the road with compaction by heavy mechanical
vibrating rollers proceeding in the direction of the alignment and gradually covering the width of the
embankment or by overlapping passes. Successive layers of the embankment shall be graded with
motor graders or by other means in conjunction with the compaction operation.
A smooth surface grade having an adequate crown slope or cross fall shall be maintained to provide
for rainfall runoff at all times.
Placing and compaction of embankment material may proceed in light rain provided that compaction
achieved in accordance with the density requirements. In case of moisture content greater than
optimum, mechanical harrow will be used to dry saturated materials naturally.
Compaction shall be undertaken at moisture content close to the optimum moisture content
determined for the specific degree of compaction. Where sand is used, the material shall be saturated
with water before compaction. Sufficient number of mobile water tanker to be used for watering the
filling materials.
This will consist of the preparation of top surface of the road bed to accommodate the placement of
the pavement structure and shoulder or gutter in accordance with the specification and in conformity
to the lines, grades and width as shown on the drawing and cross section or as directed by the
Engineer. The existing road bed shall be scarified, blended and shaped to conform to the line, level
and grade. Any high place in the road bed shall be cut to grade, all depression shall be filled with
approved materials so as to bring the surface to approved elevation. All objectionable materials like
large stone, rock, roots stumps etc, shall be removed from below sub grade elevation. The sub grade
shall be compacted in layers not exceeding 150mm compacted thickness of minimum 95% maximum
dry density. The sub grade for pavement widening shall be compacted by rolling with approved
heavy vibratory compactor. Ditches and drains shall be provided and maintained for satisfactory
drainage of the sub grade. If ruts are found in the sub grade the sub grade shall be scarified and
thoroughly compacted.
The sub grade shall be shaped as required according to camber or cross falls. Where the sub grade is
found to be of inferior strength, the same will be strengthened by providing an additional sand layer
which will be mixed with formation & completed as per requirement of specification.
This work shall consist of construction of shoulder as per specification by furnishing, placing,
compacting and shaping with approved materials as per specification & drawing.
Page 25 of 46
Construction of Kadamrasul bridge over the river Shitalakhya near Mir Akhter Hossain Ltd.
5No. Gudaraghat of Narayanganj City Corporation (NCCKB)
Project.
This item shall consist of furnishing & hauling from outside of ROW material like natural soil, or
sand or any brand of soils, sand etc. of specified quality & placing, shaping compacting & testing the
material above the compacted sub grade to form the lowest layer of the pavement according to
specification & to the lines, graders, thickness & location shown in the drawing. This will be placed
in layers as per drawing on the top of embankment, as required to camber or cross falls and shall be
compacted as per specifications.
Sub base work of specified thickness shall be done with properly blended materials of crushed burn
brick chips/rock/useable salvaged materials etc. in specified proportion and leveling & spreading the
same in specified layer of 75mm to 200mm thickness with spreading by mechanical means along
with watering & compacting the same to the full width to the specified density with 10 Ton capacity
Vibratory Roller as per specification, immediately after spreading.
In case of profile course as per drawing, the existing bituminous pavement shall be removed and the
existing base course top layer shall be scarified and re-compacted with necessary aggregate sub base
materials.
The lower portion of the above base course shall be constructed with mixture of sound durable
crushed gravel or crushed rock with some sand in accordance with the requirement & in conformity
with the lines, grades & cross sections as per drawing & approved by the Engineer. The upper 75mm
of the above base course shall consist of crushed rock materials. Before placing the base course any
defect on the sub base shall be removed. Base course shall then be applied in layers of required
thickness with required compaction as per drawing. The work will be executed in the same manner as
per sub base work.
Any irregularities that developed in the surface of aggregate sub base/ base course during compaction
shall be corrected by loosening the surface, adding or removing materials and re-compacting until the
surface presents a smooth regular appearance.
Prior to commence aggregate base in permanent works, a trial section of 400 to 800 sqm with a
minimum length of 100 m at a location approved by the Engineer shall be constructed. All field test
will be carried out in the trial section. If the initial trial section is not successful subsequent trial
section will be undertaken at contractor’s expense. The Engineer will approve commencement of
Aggregate base layer while the trial section is successful.
Page 26 of 46
Construction of Kadamrasul bridge over the river Shitalakhya near Mir Akhter Hossain Ltd.
5No. Gudaraghat of Narayanganj City Corporation (NCCKB)
Project.
The item shall consist of application of medium curing cutback MC-30/ MC-70 as specified in Article
28.4.1 on the new non bituminous finished surface of the crushed stone base layer after cleaning the
same with steel brush/ air compressor etc. The placement of bitumen shall be made mechanically by
bitumen distributor. Rate of application between 0.8 and 1.2 ltrs/ sqm and depth of penetration should
be 3 mm and 10 mm.
This item shall consist of application of tack coat with cut back bitumen emulsion meeting the
requirement of specification on the bituminous surface prior to the laying of the asphaltic wearing
course, base course or regulating course after swept cleaning of all dust, lose material and wind
blown silt/ sand. Placement of cut back bitumen shall be made mechanically. To ensure uniform
coverage a pneumatic tyred roller may be used on the spared tack coat.
The tack coat shall be applied not more than 2 hrs in advance of the laying of the asphaltic wearing
course or regulating course.
Approval of all the ingredients, job-mix formula and procedures for mixing, transporting, laying &
compacting bituminous mixtures shall be taken from the Engineer before execution of work. The
bitumen content in the job mix shall be determined through series of Marshall Stability test satisfying
the criteria mentioned in the specification.
A degender/ bitumen storage tank having accurate permanent temperature gauge of minimum
capacity 10000 ltr will be installed at plant area where mixing temperature of bitumen will not be
exceeded 1650 C. Heating of bitumen will be ensured by a diesel operated blower.
Materials shall be mixed in the Asphalt Plant satisfying the requirements of the specifications and
volume of the work to be undertaken.
Mixed materials shall be transported to the job site by Dump truck. Dump Truck for hauling asphaltic
concrete shall have leak proof metal bodies inner surface of which shall be lightly sprayed with soapy
water, thinned fuel oil or paraffin oil to prevent adhesion of the asphalt. The truck shall have well
tied, tight fitting tarpaulin coverings to protect the asphaltic concrete from the weather and to
maintain temperature..
The equipment Asphalt Paver used for spreading of asphaltic concrete shall be of self power
mechanical types and capable of spreading the mixture in accordance with Specification and
drawings. The finisher shall be equipped with a device to confine the edges of the asphaltic concrete
to true line & grade.
The finisher shall operate in such a manner that the finished surface shall be smooth and even and
without tracks or tearing or corrugations and adjustable to a regular surface. Normally 120- 125 %
loose asphalt concrete thickness is desirable during laying which will be confirmed by trial section.
During laying operation thickness of loose asphalt will be checked frequently by a device/ hand tools
Page 27 of 46
Construction of Kadamrasul bridge over the river Shitalakhya near Mir Akhter Hossain Ltd.
5No. Gudaraghat of Narayanganj City Corporation (NCCKB)
Project.
marked & made of MS rod and plate. Laying temperature also will be checked by a digital/ metal
thermometer.
In exceptional cases where finishers cannot operate due to structural obstruction, asphalt concrete
may be manually laid in small areas with great care should be ensured to avoid segregation and
uneven surface.
Where asphaltic concrete is to be laid against concrete kerbing, the face of the kerb to be in contact
with the material, shall be painted prior to the laying of the material, with hot bitumen or an approved
rapid curing cut- back bitumen.
All joints in asphaltic concrete shall be made to ensure a continuity of level and bond across the joint.
A power driven asphalt cutter shall be used to cut the face of previously laid bituminous material to
make joint vertical & all crumbs removed. All the cut back faces of the existing work shall be painted
with hot bitumen or with an approved rapid curing cut-back bitumen.
Immediately after any asphalt has been laid and screed and before roller compaction is commenced,
the surface shall be checked for line and profile, all irregularities corrected, any fat accumulation
from the screed should be removed and all localized fatty areas removed by hot rake/ hoe and
replaced with fresh material from the hopper. Irregularities in alignment and grade along the edge
shall also be corrected before the edge is rolled.
The compaction equipment and procedures adopted for compaction shall be demonstrated by rolling
trials to the satisfaction of the Engineer. The materials shall be compacted in large section as per
specifications at an initial temperature 1250C. Rolling shall be continued until all roller marks have
been eliminated from the surface and a field density of not less than 98% of the laboratory compacted
density. No rolling shall be continued when the temperature attained 900C or less.
The materials shall be compacted in a longitudinal direction and the roller shall first compact material
adjacent to any joints and then work from the lower to the upper side of the layer overlapping on
successive passes by at least half the width of the rear roll or in the case of a pneumatic tyred roller, at
least the nominal width of one tyre.
No roller shall be allowed stand on the hot material and the newly finished surface shall be protected
from traffic until the mixture has cooled down to an ambient temperature or at least 24 hrs after final
rolling.
If during cooling, fine cracks found developed in the asphaltic concrete, rolling shall recommence
until such cracks are eliminated to the satisfaction of the Engineer.
After completion of all arrangement including installation & erection of Asphalt Plant and before
permanent work is put in hand, a site ( 50 m x 7.5 m ) selected by the Engineer shall be laid asphalt
concrete work under close supervision in accordance with the specification.
Such trials shall be used for the purpose of demonstration to the Engineer’s satisfaction the stability
of a mix or the adequacy of a rate of spread and also to eradicate any apparent defects in the plant and
equipments.
Page 28 of 46
Construction of Kadamrasul bridge over the river Shitalakhya near Mir Akhter Hossain Ltd.
5No. Gudaraghat of Narayanganj City Corporation (NCCKB)
Project.
All required field test shall be carried out in the trial asphalt bed. At least two representative samples
shall be made, boxed, fully described, labeled etc. for keeping as a record.
If approved by the Engineer the trial area shall constitute a standard for comparison and shall be
preserved free from use and the permanent work shall be carried out according to the same manner &
procedure as approved. If not approved for any reason, the trial area shall be hacked out, removed and
the trial repeated.
SURFACE REGULARITY:
The longitudinal regularity of the surface of any wearing courses and base course with in the
tolerance range ± 10 mm and a 3 m long straight edge aluminum bar to be used transversely to check
irregularities of laid pavement surface with in specified range.
8 BRIDGE
Page 29 of 46
Construction of Kadamrasul bridge over the river Shitalakhya near Mir Akhter Hossain Ltd.
5No. Gudaraghat of Narayanganj City Corporation (NCCKB)
Project.
Page 30 of 46
Construction of Kadamrasul bridge over the river Shitalakhya near Mir Akhter Hossain Ltd.
5No. Gudaraghat of Narayanganj City Corporation (NCCKB)
Project.
Page 31 of 46
Construction of Kadamrasul bridge over the river Shitalakhya near Mir Akhter Hossain Ltd.
5No. Gudaraghat of Narayanganj City Corporation (NCCKB)
Project.
If any unexpected ground conditions different from the test boring log is encountered, it shall be
immediately reported to the Engineer. Depth of boring shall be measured from the length of drilling
rod.
8.1.7 Placing of Reinforcement
Reinforcement shall be fabricated and installed in position as per the approved drawing.
Reinforcement will be fabricated in the form of a rigid cage with vertical main reinforcement at
periphery inside widely spaced helical ties. In addition to binding the vertical re-bars with ties by GI
wire, spot welding will be used. The cages will be fabricated in ± 12 meter length to facilitate
handling of the same. While lowering a piece of a reinforcement cage in the bore hole it will be held
against casing pipe with a portion the reinforcing cage protruding above casing for splicing with the
upper cage. Spacing of the cage shall be done by continuous welding of vertical reinforcement.
Immediately after cleaning of bore hole reinforcement shall be lowered carefully up to level shown in
the approved drawing in the form of rigid cage. Splicing of reinforcement shall be done by welding.
Sufficient support & arrangement shall be made to keep reinforcement in vertical position.
Page 32 of 46
Construction of Kadamrasul bridge over the river Shitalakhya near Mir Akhter Hossain Ltd.
5No. Gudaraghat of Narayanganj City Corporation (NCCKB)
Project.
concrete to sufficient depth. To ensure this before removing a section of tremie pipe height of
concrete inside bore hole shall be measured by lowering suitable measuring device in the bore hole.
Pouring of concreting shall continue for some time after concrete reaches approximately 1 meter
above the pile cutoff level to allow displacement of sediments or contaminated concrete completely
and good concrete appears. During progress of concreting work temporary caging & tremie pipe shall
be gradually withdrawn carefully without damaging green concrete.
The outside surface of the permanent casing of piles to river piers, for the depth indicated on the
Drawings from the underside of the pile cap shall receive two coats of anticorrosion tar type paint.
Before use of bentonite a certificate from the manufacturer shall be obtained showing the properties
of the consignment delivered to the site and approval of the same shall be taken from the Engineer.
Position of piles shall be checked with the reference points installed near the working area prior to
execution.
Verticality of bore holes shall be checked & controlled.
During boring with drilling fluid viscosity of the suspension shall be checked time to time using
Marsh Cone.
Density of the fluid inside borehole shall be checked and kept within limits to ensure displacement of
fluid and to avoid contamination of concrete during pouring of concrete.
Hydrostatic stability of the bore hole shall always be maintained.
Page 33 of 46
Construction of Kadamrasul bridge over the river Shitalakhya near Mir Akhter Hossain Ltd.
5No. Gudaraghat of Narayanganj City Corporation (NCCKB)
Project.
Several types of defects are associated with the extraction of temporary casing. The problems are
mainly related to the workability and head of concrete placed within the steel casing prior to their
extraction. If low slump concrete is used or where the period of time between mixing the concrete
and extracting the casing is in excess of one to two hours when hardening of concrete may occur.
Frictional drag force between the casing and low slump concrete during extraction may of such
magnitude that concrete and reinforcement cage may be lifted and shaft separation may occur near
the bottom of the casing. If the reinforcement cage is securely embedded in the lower portion of the
concrete shaft, only concrete outside the cage is lifted. We shall take care of this problem by cleaning
the tubes before they are lowered down the hole and use of high workability concrete.
Piles shall not be bored close to recently concreted pile to avoid damage of the pile.
We shall keep record of all activities for each pile in an approved record form. Recording of the soil
strata in the pile boreholes is an essential check on the site investigation data. Separate sheet shall be
used for individual piles. In the record sheet pile number, drilling time, obstruction encountered
during boring, pile reinforcement detail, concrete pouring time, depth of borehole, depth of casing,
depth of water table etc. shall be recorded and submitted for review of the Engineer.
Page 34 of 46
Construction of Kadamrasul bridge over the river Shitalakhya near Mir Akhter Hossain Ltd.
5No. Gudaraghat of Narayanganj City Corporation (NCCKB)
Project.
The load at each stage is held until the rate of settlement has decreased to less than 0.25mm/hour and
is still decreasing.
We shall conduct the ML test as per the pile load increments for loading as furnished in the
specification.
A square cap is cast on to the head of the concrete test pile with its underside clear of the ground
surface. We shall apply load to the pile by a hydraulic jack using Kentledge as reaction.
An arrangement for compressive test on pile using Kentledge has been shown in fig below.
The clearances between the pile and the reaction support systems shall be kept minimum 1.3 meter to
avoid the induced horizontal pressures from the supports.
The combined weight of the kentledge and reaction girder shall be at least 20% greater than the
Jacking force.
The hydraulic jack shall have a nominal capacity which exceeds by 20% or more the maximum test
load to be applied to the pile. This in necessary in order to avoid heavy manual pumping effort when
nearing maximum load and to minimize the risk of any leakage of oil through the seals. The ram of
the jack shall have a long travel to avoid the necessity of releasing oil pressure and repacking with
steel plates above the ramp as the pile is pushed into the ground. The kentledge stack shall be
arranged in such a way that it will topple over due to buckling of the reaction girders.
The jacking force on the pile shall be measured by a load cell or pressure capsule since the pressure
gauge fitted to most jacks is not sufficiently accurate, particularly when working towards the
maximum capacity of jack. The pumping unit shall have a calibrated pressure gauge mounted on it to
read in terms of the force of the ram.
The settlement of the pile head shall be measured by dial gauge set on each of four reference points
on the pile head. The dial gauges will be clamped to a datum frame securely mounted well clear of
the ground around the pile or the reaction support system. The gauges will be calibrated to read to
0.1mm. Level of the datum frames shall be taken before and after loading test to check that the
frame has not been displaced during the test.
Page 35 of 46
Construction of Kadamrasul bridge over the river Shitalakhya near Mir Akhter Hossain Ltd.
5No. Gudaraghat of Narayanganj City Corporation (NCCKB)
Project.
All field load test data shall be recorded in an approved form. From the field data a load-time-
settlement curve shall be drawn on a graph paper and the report shall be prepared and submitted for
review of the Engineer.
The Loading test shall be conducted with ASTM D4945-00 ( 1994). Detail method statement shall be
submitted to the Engineer for approval at least 45 days before testing. The method statement shall
include pile head preparation, cushion layer, type and capacity ( weight ) of hammer, method of
hammering ( drop from certain height ), equipment for installation ( rising and drop ) of hammer ( 45
ton capacity crawler crane ), digital apparatus for dynamic monitoring with calibration records etc.
A full comprehensive written report shall be submitted to the Engineer within 10 working days for
his approval. After the completion of loading test, all equipment and hammer used shall be removed
from the site.
Each completed piles shall be subjected to non destructive testing to determine the extent of any
defects that may be present in the pile. PIT shall not be performed until the concrete has cured for a
minimum of seven days unless otherwise approved by the Engineer
Page 36 of 46
Construction of Kadamrasul bridge over the river Shitalakhya near Mir Akhter Hossain Ltd.
5No. Gudaraghat of Narayanganj City Corporation (NCCKB)
Project.
9 Construction of Rc Piers (Pier Head, Pier Shaft and Pile Cap), Rc Abutment
and Wing Wall
9.1 Pile Head Breaking and removal
After successful completion in place boring, rebar casing installation and casting of In-situ pile,
foundation excavation should be commenced and open the pile head. Then concrete of pile head
should be broken into pieces preferably manually and removal the debris to a save distance.
Fabricated rebar shall be placed on the blinding concrete as per dia and spacing shown in the
approved drawing. Spacer block and necessary chair shall be provided to support upper layer rebar.
Sand cement block shall be used for ensure clear cover of rebar in the concrete.
Page 37 of 46
Construction of Kadamrasul bridge over the river Shitalakhya near Mir Akhter Hossain Ltd.
5No. Gudaraghat of Narayanganj City Corporation (NCCKB)
Project.
9.8 Curing
One or more pump with 1” dia flexible pipe shall be arranged at site for proper curing of concrete.
After removal of formwork for pier shaft and vertical wall shall be covered and wrap by hessian
cloth, wet burlap, cotton mats or other suitable fabric for a period of at least 7 days. These material
shall be kept thoroughly wet to the entire curing period. All concrete slabs shall be covered as soon as
possible with hessian cloth, sand, earth or other suitable material and kept thoroughly wet for at least
seven days.
If wood forms are allowed to remain in place during the curing period , they shall be kept moist at all
times to prevent them from shrinking.
Curing of concrete should be started after final setting time of concrete i.e within 24 hr after
concreting.
Page 38 of 46
Construction of Kadamrasul bridge over the river Shitalakhya near Mir Akhter Hossain Ltd.
5No. Gudaraghat of Narayanganj City Corporation (NCCKB)
Project.
Concrete Strength
Centering under beams, 14 days 7 days 80%
girders, frames or arches
Floor Slabs 14 days 7 days 70%
Vertical Walls 1 day 12 hours -
Columns 2 days 1 day -
Side of beam and all other 1 day 12 hours -
vertical surface
a) Construction of PC girder ( normally < 20.00 m length ) on ground level shall be done on a
casting bed made of bricks and cement concrete prepared on a level ground. During
construction of casting bed provision shall be kept to fix the bottom shutter with the bed by
spot welding with the anchors. The space between the beds shall be kept equal to minimum
height of girder plus 600mm for movement of workers. A typical plan and sketch of casting
bed arrangement has been shown in fig attached at the end of this method statement.
b) In case of construction of girders ( normally length > 20.00 m ) final height within span, a
rigid working platform on pipe scaffolding using joists, steel platform timbers etc. shall be
constructed at a level close to. At least two numbers of bed shall be constructed on each
platform. Width of platform for 30 meter girders shall be approximately 7.8 meter for two
beds. Alignment of the casting beds will be selected at center of final positions of two girders
to facilitate stressing of girders. The pipe supports will be properly braced and made safe
against anticipated loads. Re-bar placing & binding, cleaning & fixing of form work,
installation of pre-stressing materials, casting of girder, pre-stressing and operation for
shifting of girder shall be carried out on the platform.
Page 39 of 46
Construction of Kadamrasul bridge over the river Shitalakhya near Mir Akhter Hossain Ltd.
5No. Gudaraghat of Narayanganj City Corporation (NCCKB)
Project.
After placing & binding of girder reinforcements, end shutters and one side shutter shall be erected
and ducts shall be placed in position according to alignment and cable profile shown in the approved
drawing. The ducts shall be secured in position by binding the same with girder reinforcement and
suspenders at close intervals. Joint of ducts shall be made using couplers of minimum 150mm length
made of 3mm higher diameter sheathing pipe . Anchorage will be positioned and secured in such a
way, so that the centre line of the ducts passes axially through the anchorage assembly duct.
Anchorage will be fitted with the end shutter by J hooks. Care shall be taken to ensure water tight
joints between anchorage and duct and joints of ducts. Required end block reinforcement shall be
placed on each side of the tendon at the anchorage to take care of the tensioning bursting force as per
detail shown on shop drawing. Cables shall be threaded into the sheathing pipe before pouring of
concrete. During threading of cable through the sheathing a blunted cap shall be fitted on the head of
thread as a precaution against damage of sheathing pipe wall by the sharp end of strands. Cables shall
be extended beyond both ends of the girder up to required distance for gripping of the same by
tensioning Jack. To facilitate lifting and sheathing of girders after stressing, provision shall be kept
for fixing lifting attachment near the supporting point of the girder during form work. After
inspection and approval of girder reinforcement, placement of sheathing pipes, anchorage, etc., the
side shutter of the other side will be placed and completed. Form release agent shall be applied on the
Page 40 of 46
Construction of Kadamrasul bridge over the river Shitalakhya near Mir Akhter Hossain Ltd.
5No. Gudaraghat of Narayanganj City Corporation (NCCKB)
Project.
inside of the steel forms to prevent bond between the form and the concrete cast in it. Sufficient side
supports will be provided to keep the formwork aligned during concrete pouring.
10.4 Concreting
Mix proportion of different concrete ingredients shall be determined through mix design and trail
mixes to achieve required strength and workability. Slump of concrete shall be maintained at
approximately 100mm. Mix design shall be done considering use of plasticizers to minimize water
cement ratio and achieving desired workability.
During pouring of concrete both form Vibrator and immersion type Vibrator will be used. Special
care shall be taken to ensure proper compaction and elimination of void/accumulation of air bubble
near end block and just behind anchorages. Care shall be taken to avoid damage and displacement of
duct during pouring of concrete. Tendons inside the duct shall be pulled to and fro during pouring of
concrete and for several hours after concrete casting and also in the next day of pouring of concrete to
keep the tendons free and unbonded in the duct from accidental ingress of mortar inside the sheathing
and to prevent setting of ingressed mortar, if any. 6-9 nos. of concrete cylinder shall be prepared as
representative sample of each girder concrete.
When pre-stressing operations will be planned to be carried out within the spans with abutment at one
end or both ends, concreting of the abutment wall above girder support level shall be completed after
completion of prestressing operations.
10.5 Post-Tensioning
All post tensioning steel shall be tensioned by means of hydraulic jacks so that the force of the
prestressing steel shall not be less than the value shown on the approved installation drawings. Before
post tensioning operation approval of the tensioning methods, calculations for required applied force,
Page 41 of 46
Construction of Kadamrasul bridge over the river Shitalakhya near Mir Akhter Hossain Ltd.
5No. Gudaraghat of Narayanganj City Corporation (NCCKB)
Project.
expected elongations, sequence of stressing of tendons etc. will be taken. The maximum temporary
tensile stress ( jacking stress) in prestressing steel shall not exceed 80% of the minimum ultimate
tensile strength of the prestressing steel. The prestressing steel shall be anchored in a way that will
result in the ultimate retention of permanent forces, not less than those shown on the approved
installation drawings, but in no case shall the initial stress at the anchors, after anchor set, exceed 70
percent of the specified minimum ultimate tensile strength of the prestressing steel. Permanent force
and permanent stress will be considered as the force and stress remaining in the prestressing steel
after all losses, including creep and shrinkage of concrete, elastic shortening of concrete, relaxation of
steel, losses in post-tensioned prestressing steel due to sequence of stressing, friction and anchorage
slippage.
Each jack used to stress tendons shall be equipped with a pressure gauge for determining the jack
pressure or jack force.
10.6 Calibration
Prior to use for stressing on the project, each jack and its gauge shall be calibrated as a unit by a
testing laboratory approved by the Engineer. Certified calibration calculations and a calibration chart
shall be furnished to the Engineer/inspector for each jack. Recalibration of each jack shall be done at
six-month intervals and at other times requested by the Engineer/Inspector
After curing for at least 7 days, when the girder shall attain minimum cylinder strength of 4000 psi.
which will be confirmed by crushing of test specimen taken during pouring of concrete, the pre-
stressing tendons shall be tensioned.
Straight cables shall be tensioned from one end while curved cables shall be tensioned from both the
ends as per technical specification. The tendon force measured by gauge pressure shall agree within
5% of the theoretical elongation or the entire operation shall be checked and source of error shall be
determined and remedied to the satisfaction of the Engineer/Inspector before proceeding the work.
Elongation shall be measured to the nearest millimeter. If the elongation is less than the anticipated
elongation over 3% of the anticipated elongation, the cables shall be stressed by slight force to
overcome additional friction force.
In the event of more than 2% of the individual strand wires in a tendon break during the tensioning
operation, the strand (strands) shall be removed and replaced
Page 42 of 46
Construction of Kadamrasul bridge over the river Shitalakhya near Mir Akhter Hossain Ltd.
5No. Gudaraghat of Narayanganj City Corporation (NCCKB)
Project.
The cables shall be stressed in sequences listed to minimize the eccentric stressing and to avoid
bending of girder under eccentric load.
Following tools/equipment will be used for post tensioning of girders :-
1. Multiple pre-stressing Jack = 2 nos.
2. Electrically operated Hydraulic Power Pack = 2 nos.
3. Pressure gauge = 2 nos.
4. Chain pulley = 2 sets
The cables shall be initially pulled by 50 KN force to eliminate slag, if any. Then chalk mark shall be
given on the cable at a distance of say 200mm at both ends measured from the face of the girder.
Measurement of elongation shall be taken from both ends for every 50KN increment of Jacking force.
In case of two ends stressing of cable, both ends shall be pulled with equal force. In case of stressing
cable from one end, the cable on the opposite end of the jacking end shall be blocked by pushing the
wedges in the bearing plates/anchorage cones. Elongation of cable at every increment of 50KN force
shall be recorded and plotted in a graph paper. From the extension of plotted line corrected elongation
of cable due to initial 50KN force shall be calculated. Measurement of anchorage losses shall be
taken accurately to determine the losses due to anchorage slippage.
10.8 Grouting
After post-tensioning and anchoring has been completed and accepted, the duct shall be grouted as
per specification. In the interval between post-tensioning and grouting operations , the prestressing
steel shall be protected. After stressing of cables the girder shall be left undisturbed for one day. In
the following day the reference point shall be measured. If no appreciable change in slippage of
tendon is noticed the extended portion of the tendons shall be cut and patch concreting of the end
shall be done.
Grouting shall be carried out on the following day of patch concrete. Before grouting cable shall be
cleaned by flash water through the duct under pressure. Grout shall be prepared by mixing following
materials in the proportion recommended by the manufacturer by grout agitator.
1. Ordinary Portland Cement
2. Potable water
3. Expanding grout admixture.
The grout shall be forced inside the duct from one end using grout pump. Grout shall be pumped
through the holes of anchorage assembly . When thick grout starts to come through the centre holes
of anchorage on the other end the hole on the other end shall be plugged and Grouting shall continue
until sufficient grout pressure is developed inside the duct and the grouting end shall be plugged.
Following tools/equipment will be used for grouting of girders :-
1. Grout pump
2. Grout agitator.
Page 43 of 46
Construction of Kadamrasul bridge over the river Shitalakhya near Mir Akhter Hossain Ltd.
5No. Gudaraghat of Narayanganj City Corporation (NCCKB)
Project.
Page 44 of 46
Construction of Kadamrasul bridge over the river Shitalakhya near Mir Akhter Hossain Ltd.
5No. Gudaraghat of Narayanganj City Corporation (NCCKB)
Project.
Page 45 of 46
Construction of Kadamrasul bridge over the river Shitalakhya near Mir Akhter Hossain Ltd.
5No. Gudaraghat of Narayanganj City Corporation (NCCKB)
Project.
Prior to excavation or filling in slopes, the existing slope surface either above or under water level
shall be surveyed and checked. The slope surface shall be leveled and compacted by using plate
compactor.
Filter fabric non oven geo-textile shall be spread uniformly over the prepared slope or surface.
Minimum 12” filter fabric lap in each direction should be provided.
Riprap with concrete precast block shall be placed over the filter.
Toe wall shall be provided by concrete block to resist sliding of riprap block on the slope surface.
Page 46 of 46