FINAL REPORT
CORROSION COUPON REPLACEMENT
AT PT BAYU BUANA GEMILANG CIKARANG
22 AUGUST 2019
PT Wilson Walton
Indonesia
Table of Contents
1. INTRODUCTION......................................................................................................... 2
3. REFERENCES.............................................................................................................. 2
4. DISCUSSIONS ............................................................................................................ 2
5. FINDING ................................................................................................................... 3
5.1. Corrosion Coupon Retrieved from 4” Pipe BV Sinar Jaya. ................................................................... 3
5.2. Corrosion coupons retrieved from 6“ Pipe BV Kandang Ayam. ............................................................ 5
5.3. Corrosion Coupon Retrieved from 12“ Scrubber 32 Tegal Gede. ......................................................... 7
5.4. Corrosion coupons retrieved from 6“ Scrubber 24 Mulia Industry..................................................... 13
5.5. Summary of All Corrosion Rate Data at BBG facilities ........................................................................ 16
6. CONCLUSIONS......................................................................................................... 17
7. RECOMMENDATIONS .............................................................................................. 17
Page 1 of 17
Corrosion Monitoring Services
Corrosion Coupon Replacement
at PT. Bayu Buana Gemilang Cikarang
August 22, 2019
1. INTRODUCTION
Under Contract No BBG‐KAB/PO/VII/19/001 awarded by PT. Bayu Buana Gemilang, PT.
Wilson Walton Indonesia (WWI) performs corrosion monitoring services at BBG
Cikarang Pipeline. During August 22, 2019 , WWI has replaced corrosion coupon at
BBG Cikarang facilities.
This report outlines scope of work, field finding, discussion of field finding, and
conclusions and proposed recommendations regarding to this visit.
2. SCOPE OF WORK
Scope of work of this visit is to replace corrosion coupon by online operation using
special tools (retriever RSL and service valve) at BBG Cikarang facilities.
3. REFERENCES
NACE RP0775‐2013 Preparation, Installation, Analysis, and Interpretation of
Corrosion Coupon in Oilfield Operations
RohrbackCosasco Systems Corrosion Management Solution 2010 Product Catalog
4. DISCUSSIONS
Corrosion coupon testing consists of the exposure of a small specimen of metal (the
coupon) to an environment of interest for a period of time to determine the reaction
of the metal to the environment. Corrosion coupons are used to evaluate
corrosiveness of various systems, to monitor the effectiveness of corrosion mitigation
programs, and to evaluate the suitability of different metals for specific systems and
environments.
A calculation of the average corrosion rate from weight loss coupon can be found in
the following formula:
Material of strip and ladder coupon is a carbon steel material with UNS no: G10180
where metal density of coupon is 7.86 g/cm3 and coupon’s surface area 5.2in2 for
strip and 3.4 in2 for ladder.
Page 2 of 17
Corrosion Monitoring Services
Corrosion Coupon Replacement
at PT. Bayu Buana Gemilang Cikarang
August 22, 2019
Qualitative categorization of carbon steel corrosion rates for oil production systems
guidelines for interpretation of measured corrosion rate can be found in the following
table.
5. FINDING
In accordance with the scope of work, the following verifications and observations
were made during this field visit:
Figure 1. Corrosion coupons retrieved from 4” Pipe Box Valve Sinar Jaya,
Cikarang Barat, before cleaning.
Page 3 of 17
Corrosion Monitoring Services
Corrosion Coupon Replacement
at PT. Bayu Buana Gemilang Cikarang
August 22, 2019
Figure 2. Corrosion coupons retrieved from 4” Pipe Box Valve Sinar Jaya,
Cikarang Barat, after cleaning .
Page 4 of 17
Corrosion Monitoring Services
Corrosion Coupon Replacement
at PT. Bayu Buana Gemilang Cikarang
August 22, 2019
Figure 3. Corrosion coupons retrieved from 6“ Pipe Box Valve Kandang Ayam,
Cikarang Barat, before cleaning.
Page 5 of 17
Corrosion Monitoring Services
Corrosion Coupon Replacement
at PT. Bayu Buana Gemilang Cikarang
August 22, 2019
Figure 4. Corrosion coupons retrieved from 6“ Pipe Box Valve Kandang Ayam,
Cikarang Barat, after cleaning.
Page 6 of 17
Corrosion Monitoring Services
Corrosion Coupon Replacement
at PT. Bayu Buana Gemilang Cikarang
August 22, 2019
Figure 5. Corrosion coupons retrieved (Top Position) from 12“ Scrubber 32 Tegal Gede,
Cikarang Selatan, before cleaning .
Page 7 of 17
Corrosion Monitoring Services
Corrosion Coupon Replacement
at PT. Bayu Buana Gemilang Cikarang
August 22, 2019
Figure 6. Corrosion coupons retrieved (Top Position) from 12“ Scrubber 32 Tegal Gede,
Cikarang Selatan, after cleaning.
Figure 7. Corrosion coupons retrieved (Middle Position) from 12“ Scrubber 32 Tegal Gede,
Cikarang Selatan, before cleaning.
Page 8 of 17
Corrosion Monitoring Services
Corrosion Coupon Replacement
at PT. Bayu Buana Gemilang Cikarang
August 22, 2019
Figure 8. Corrosion coupons retrieved (Middle Position) from 12“ Scrubber 32 Tegal Gede,
Cikarang Selatan, after cleaning.
Figure 9. Corrosion coupons retrieved (Bottom Position) from 12“ Scrubber 32 Tegal Gede,
Cikarang Selatan, before cleaning.
Page 9 of 17
Corrosion Monitoring Services
Corrosion Coupon Replacement
at PT. Bayu Buana Gemilang Cikarang
August 22, 2019
Figure 10. Corrosion coupons retrieved (Bottom Position) from 12“ Scrubber 32 Tegal Gede,
Cikarang Selatan, After cleaning.
Page 10 of 17
Corrosion Monitoring Services
Corrosion Coupon Replacement
at PT. Bayu Buana Gemilang Cikarang
August 22, 2019
Page 11 of 17
Corrosion Monitoring Services
Corrosion Coupon Replacement
at PT. Bayu Buana Gemilang Cikarang
August 22, 2019
Page 12 of 17
Corrosion Monitoring Services
Corrosion Coupon Replacement
at PT. Bayu Buana Gemilang Cikarang
August 22, 2019
Page 13 of 17
Corrosion Monitoring Services
Corrosion Coupon Replacement
at PT. Bayu Buana Gemilang Cikarang
August 22, 2019
Description after cleaning Relatively smooth surface and no severe metal loss
Page 14 of 17
Corrosion Monitoring Services
Corrosion Coupon Replacement
at PT. Bayu Buana Gemilang Cikarang
August 22, 2019
Description after cleaning Relatively smooth surface and no severe metal loss
Based on table.2 until 5b above a summarized corrosion rate at 4 four locations at BBG facilities is as
follows:
Page 15 of 17
Corrosion Monitoring Services
Corrosion Coupon Replacement
at PT. Bayu Buana Gemilang Cikarang
August 22, 2019
Average corrosion rate of all retrieved corrosion coupons are categorized as low average
corrosion rate (˂ 1.0 mpy) as per NACE RP0775‐2013. It appears that the fluid was not
corrosive. Failure risk caused by thinning is relatively Low
6"BV FJ802 0.15 Low LL895 0.08 Low RX525 0.05 Low
1 Kandang
Ayam FJ803 0.14 Low LL894 0.08 Low RX523 0.05 Low
4" BV FJ800 0.39 Low LL754 0.12 Low RX526 0.07 Low
2 Sinar
Jaya FJ801 0.4 Low LL891 0.18 Low RX521 0.09 Low
6"
Scrubber ‐ ‐ ‐ LL893 0.12 Low RX522 0.29 Low
3
24 Mulia
Keramik ‐ ‐ ‐ LL892 0.02 Low RX524 0.31 Low
BT 105 MT437 RS314
( Top ) 0.18 Low ( Top ) 0.55 Low ( Top ) 0.11 Low
BT 106 MT438 RS317
( Top ) 0.15 Low ( Top ) 0.56 Low ( Top ) 0.10 Low
BT 104 MT436 RS313
(Middle) 0.26 Low (Middle) 0.61 Low ( Middle ) 0.14 Low
12"
BT 107 MT435 RS316
4 Scrubber
(Middle) 0.27 Low (Middle) 0.61 Low ( Middle ) 0.13 Low
32
BT 102
RS315
(Bottom MT433
(Bottom)
) 0.3 Low (Bottom) 0.62 Low 0.16 Low
BT 103
RS318
(Bottom MT434
(Bottom)
) 0.3 Low (Bottom) 0.62 Low 0.18 Low
Page 16 of 17
Corrosion Monitoring Services
Corrosion Coupon Replacement
at PT. Bayu Buana Gemilang Cikarang
August 22, 2019
From the all corrosion rate data at table and graph above, corrosion rate are
categorized as low average corrosion rate (˂ 1.0 mpy) as per NACE RP0775‐2013.
6. CONCLUSIONS
1. Four (4) points of corrosion coupon monitoring installed at BBG facility were
successfully replaced.
2. Corrosion rates for all retrieved corrosion coupons at BBG Cikarang facility are
categorized as low average corrosion rates with no localized corrosion found at all
of the retrieved corrosion coupons surface.
7. RECOMMENDATIONS
Based on the conclusions, our recommendation is as follows:
1. Perform regular monitoring of corrosion rates for every location at least every 6
months.
2. Provide corrosion monitoring spare parts such as corrosion coupon, Teflon primary
packing, and Viton O‐ring for anticipate any replacement parts during replacement
program.