Professional Documents
Culture Documents
Planning Application
1.0 Introduction 4.0 Design Proposals – Building 7.0 Statutory Requirements and Waste
Management
1.1 Project Overview 4.1 Building Concept
1.2 Project Team 4.2 Modular Construction 7.1 Access
1.3 The Brief 4.3 Internal Organisation and Adjacencies 7.2 Inclusive Access
1.4 Operational Hours 4.4 Use and Amount 7.3 Fire Strategy
1.5 Planning Context 4.5 Building Massing 7.4 Acoustic Strategy
1.6 Consultations 4.6 Design Concept & Elevational Treatment 7.5 Noise Impact Assessment
4.7 Materials & Colour Palette 7.6 Site Waste Management Plan
2.0 Existing Site 4.8 Elevations 7.7 Archaeological Statement
4.9 Preliminary Visuals
2.1 Site Location 4.10 Internal Views 8.0 Sustainability
2.2 Site Context & History 4.11 Access & Maintenance
2.3 Site Ownership 8.1 Overview
2.4 Site Surroundings 5.0 Structural & Civil Engineering
2.5 Site Analysis 9.0 Summary
2.6 Site Photographs 5.1 Introduction 9.1 Use
2.7 Existing Materiality 5.2 Superstructure 9.2 Amount
2.8 Site Opportunities 5.3 Foundations 9.3 Layout
5.4 Civil Engineering Flood Risk Assessment 9.4 Scale
3.0 Design Proposals - Site 5.5 Foul Sewerage Assessment 9.5 Landscaping & Biodiversity
9.6 Appearance
3.1 Site Layout & Design Considerations 6.0 Building Services
3.2 Building Orientation
3.3 Proposed Site layout 6.1 Energy Efficiency Initiatives
3.4 Car Parking 6.2 Ventilation Systems
3.5 Travel Plan & Transport Assessment 6.3 Domestic Water Services
3.6 Landscape Proposals 6.4 Above Ground Drainage
6.5 Lighting Design
6.6 Power & Data
6.7 Fire Alarm & Detection
Site Address is
The Sweyne Park School, Andrew Lawrence ECC Project Sponsor
Sir Walter Raleigh Drive,
Rayleigh, Rhona Long ECC Schools Organisation Officer
Essex Simon Smith Sweyne Park School Learning Environment Leader
SS6 9BZ
This Report sets out the basis of the design strategy for the new building, developed following the
selection of Pick Everard to lead the design of the project. The purpose of a design and access
statement is to set out the thinking that has resulted in the design submitted in the planning
Design Team
application. It explains how the building’s massing, layout and appearance has developed in response to
the demands of its particular context and brief, and how the resulting building will be easy to use and Project Manager Pick Everard
navigate. Architecture Pick Everard
The structure and content of this Statement also accords with “Guidance on Information
Requirements and Validation” published by the Department for Communities and Local Government.
This Statement should be read in conjunction with the Planning Statement, the Environmental
Statement, completed forms, certificates and other detailed technical reports and drawings submitted
in support of the Application.
It is a long term ambition of Essex County Council to deliver high performance, affordable and high
The normal hours of operation of the building will be aligned to the normal school opening and no
quality teaching spaces. The design is to focus on achieving a modular off-site manufactured solution,
variation of school hours is envisaged as a result of this application.
build elements, to suit a uniform (class) room product which can be assembled into a building and can
be replicated in future projects.
A key deliverable in the design/ project scope is providing accommodation suitable for educating
hearing impaired children who are integrated into the Sweyne mainstream educational model. The
resulting brief has been developed to include some enhancement of the classrooms in order to better
cater for students at the school who have hearing impairments.
The new building proposals are based upon the Draft Viability report Rev C 17.01.2020. The project
scope requires years 7-11 to increase from 1200 + 74 Bulge permanent places to 1350
permanent places increasing capacity by 150 places.
The MEP solution will need to take into consideration Kwh use, running (revenue) cost v’s capital
cost, as it is not a Client requirement to have minimal capital cost and high running cost.
External works – The viability study notes that although the school is below area with respect to
Building Bulletin 103 a formal agreement exists with Rochford District Council permitting access to
Sweyne Park, adjacent to the school. The park is approximately 57 acres and therefore mitigates the
deficit in playing fields, consequently no additional playing field area is required and no section 77
application should be required.
The site is located within the defined settlement boundary of Rayleigh and on land allocated as
“Educational Land Allocation”, therefore the proposed new classroom block is likely to be considered
acceptable in principle.
Early consultation with the LLFA is advised regarding surface water flood risk constraints and /or
mitigation. A site specific Flood Risk Assessment is undertaken as part of the application and initial
consultation has taken place with ECC SUDS team on 03.06.20.
Relevant Policies
National Planning Policy Framework (NPPF, 2019)
Rochford Local Development Documents:
• Core Strategy (adopted December 2011) sets out the spatial vision, strategic
objectives and core policies up to 2025;
• Allocations Plan (adopted February 2014) sets out site specific policies and land use
allocations over the plan period;
• Development Management Plan (adopted December 2014) sets out detailed policies
for managing development across the District;
Community Engagement
Initially there were concerns in relation to the orientation of the building as it did not conform to the
A public consultation exercise was undertaken for a two week period between 6 July to 20 July 2020. alignment of the existing school buildings. It was explained that within the initial options for the location
Due to the current Coronavirus situation, a public exhibition was not possible. of the building alignment was considered. However, as the existing buildings are 2/3 storeys there is a
requirement to include a fire separation gap between the existing and proposed building. This resulted
in the building being moved further away and aligned with the MUGA pitch as submitted. In addition,
Properties/residents within a 150m radius of the school site were sent a leaflet explaining the details
due to the topography of the site this position provides access for all without the need for a ramp.
of the proposal on 29 June 2020, with an invitation to participate through an online website, with
details provided. Comment forms were available online for completion.
In terms of materials proposed, the Council had apprehensions towards white cladding on a single
storey educational building as this could incur additional maintenance and lack of longevity. The external
A total of 426 leaflets were posted to residents. A summary of the seven responses were received. Of
colours proposed linked back to the existing buildings and the school colours. It was suggested that
the seven responses, five were from local residents and two from parents.
slightly darker colour finishes or raising of the brick plinth would not be so susceptible. The submitted
design and materials reflect the comments received whilst maintaining the schools colour palette, as
The responses amounted to 85.7% supporting the application, with 42.8% of these having some portrayed in the Design and Access Statement.
concerns. These related to being notified of when construction would begin and increased traffic and
parking.
As there is to be a loss of green space, the Council would require mitigation in the form of landscaping.
Due to the proposed orientation of the building there is an opportunity to provide a
Positive comments related to: courtyard between the buildings that allows for soft landscaping.
• Liking the modular design as reduced building noise, pollution and excess traffic in the area during
construction.
• Liking the fact that solar energy is being incorporated.
• The covered walkway being a nice addition for the pupils.
• Whoever are the lucky pupils to learn in this new block, I hope they appreciate their surroundings
and look after it.
There was one objection to the proposal regarding the extra traffic and pollution from the increase in
numbers attending the school.
The School’s Travel Plan will identify mitigation to any issues raised and be assessed as part of the
transport and travel survey. Overall, the traffic and parking comments will be overcome through the
implementation of the revised School Travel Plan, submitted as part of this application.
The site was historically surrounded by agricultural land use from at least 1874. Residential
development began c.1923 and continuous expansion now means that the site is virtually surrounded
by housing. SITE
Site History
2010 2020
The school buildings have The school buildings have
been extended. been extended further.
Glebe Primary
School
Sweyne Park School Existing All Weather pitch
Leisure Centre
Environment
In analysing the existing site, the building massing forms much of the
north east portion of the site. The south west portion of the site
forms the open playing field and all weather pitch.
A dedicated bus drop off and turning circle is located to the south of
the school, off Sir Walter Raleigh Drive and also forms the
emergency access onto the school playing field. It is anticipated that
this will form the Contractor access to the site.
The main pedestrian route for pupils and visitors is via Sir Walter
Raleigh Drive, albeit segregated from the vehicular entrance, with
footpaths leading to the school’s main entrance.
Building uses
01 02
3
4
2
03 04
05 06
This creates a distinct style which carries across all school buildings
through the site and provides a strong precedent for the proposed
new build materials.
The proposed site is located on the south east side of the existing
cluster of school buildings. The proposals locate the new block
between the MUGA /All Weather Pitch and the existing school
buildings, away from any residential boundaries.
The site sits within the area protected by the flood berm.
The relationship between the new build and existing school was a key
driver in siting the proposed new build. A covered link is to provide a
dry access route between these buildings, which also connects to a new Existing School Proposed
footpath to tie in the existing egress route to the south east of the main Buildings
building. Covered link
The distance to the existing building considers both contractor access Existing Car All Weather
for this project and ensures a 5 metre wide clear access route is Park Pitch
maintained to allow for safe removal of the sixth form modular units to
support the school’s future development.
When establishing the ideal siting and orientation of the new build a
detailed options appraisal was undertaken to determine the most
appropriate position for the proposal the within the limiting site
constraints.
One of the main drivers was to ensure the fire boundary offset distances
were compliant with Approved Document B and Building Bulletin 100 in
order to establish a safe environment for all building users.
The proposed and agreed building orientation not only offers compliance
with boundary offset requirements in accordance with the relevant
legislation, but also brings a number of other benefits to the scheme:
New Substation
Relocated Storage
Container (Existing)
Existing Main
School Building
Proposed Contractor
Access
The school’s travel plan will identify mitigation to any current issues and
will be assessed as part of the transport and travel survey to achieve
planning consent that will benchmark against current standards.
The planting strip will act as the deterrent from the window boxings
along the building façade. To soften the view from the existing building,
perennial herbaceous and shrubs are introduced to gain seasonal interest
and balance the unity and diversity. Salvia officinalis, Echinacea purpurea,
Persicaria affinis ‘Superba’ and Verbena bonariensis, combining pink and
purple will provide dramatic colour, and plant forms from summer to
autumn. Alchemilla mollis, Hebe albicans ‘Red Edge’ and Deschampsia
cespitosa will provide the plant structure and different foliage texture
throughout the year. The proposed planting species have been carefully
selected to include a range of native floral species which will enhance the
biodiversity of the site, in accordance with the recommendations set out
in the Ecology Report.
Ecology
The habitats survey was conducted by Delta-Simons. The initial site
assessment has identified habitat or potential for bats, badger and
hedgehog and precautionary measures will be taken to mitigate the
effects where possible. Bird nesting boxes will be installed on the
existing school building in accordance with the recommendations listed
in the Ecology Report by Delta-Simons, reference 20-
0793.01_REP_Sweyne-High-School_PEA_2020-06-24.
Arboriculture
A total of one tree and two tree groups have been identified and
assessed in Arboricultural survey within the south-west of the grounds
of the school, whilst none lies within the site boundary, sit close to the
proposed access route. The TG2 and TG3 would not be affected by the
proposal. Appropriate protection measures will be included around T1
to ensure no damage to the tree roots. Trees have been broadly
assessed based on guidance set out within the British Standard 5837:
2012 Trees in Relation to Design, Development and Construction.
Details refer to Arborcultural report by Delta-Simons, reference 20-
0793.01_REP_Sweyne-Park-School_ARB_2020-07-31.
The strong canopy form, spine wall and contrasting white cladding
emphasises the main entrance allowing the architectural elements of the
building to acts as signposts.
The aspiration for the building plan is to achieve a high quality user
experience and spatial flexibility with the use of a reconfigurable planning
module.
The holistic design approach has been developed to ensure the external
and internal design is fully integrated and considered. The adopted
design aesthetic is ‘simple order’ to be executed with high quality
materials and well considered architectural interface details. We have
taken this approach to:
Modular construction is a process in which a building is constructed off-site, under controlled factory
conditions, using the same materials and designing to the same codes and standards as conventional
buildings– but in about half the time. Buildings are produced in “modules” that when put together on site,
reflect the identical design intent and specifications of highly sophisticated site-built facilities – without
compromise. They can be built and arranged in any shape or style similar to a traditionally built building.
Where possible, module sizes throughout the design have been standardised in order to create more
efficiency both in the design of details and also the cost. The proposed module sizes are:
3950mm x 7840mm
3950mm x 11060mm
Benefits
Some of the benefits of modular construction are listed below:
• Safer: high proportion of factory construction, means less hazardous working time on site.
• Greater flexibility, reuse and relocatable: Modular buildings can be disassembled and the modules
relocated or refurbished for new use, reducing the demand for raw materials and minimizing the amount
of energy expended to create a building to meet the new need.
• Faster return on investment: faster delivery time means capital investment can start earning.
• Lighter: Less weight in overall construction, enables installation in locations with poor ground bearing
conditions.
• Minimal ground investigation: lightweight nature of buildings ensures less ground preparation with simple
pad foundations.
• Less Material waste: When building in a factory, waste is eliminated by recycling materials, controlling
inventory and protecting building materials.
• Improved air quality: Because the modular structure is substantially completed in a factory-controlled
setting using dry materials, the potential for high levels of moisture being trapped in the new construction
is eliminated. This would also contribute positively towards Carbon Neutral 2025 plan.
New Build
6no. General Classrooms : 55 m2
Staff Office : 28 m2
WC’s : 31 m2
Storage : 15 m2
Entrance Lobby : 8 m2
Circulation : 101 m2
Plant : 20 m2
Basic massing of single storey elements against existing Monopitch roof form creates potential for additional
building heights, highlights the central circulation spine within. A pitched roof provides the opportunity for PV glazing to the north elevation and a south facing roof for
The Flat roof directly corresponds to the adjacent existing on the south face. PVs. Overhanging eaves can help provide solar shading
buildings. to the south elevation
Definition of Masses
The simple form of the proposed single storey element enables the block to be visually defined by
dividing the elevational treatment into its three main uses; teaching, ancillary and entrance. This
provides the opportunity for differing cladding arrangements to create definition and visual contrast
between the lighter elements of the teaching spaces in relation to the darker and more solid
ancillary element.
Proportions
The driver behind the elevational treatment of the new build block is to use solid and void elements
to show direct relationships to internal functions. An analysis of the base elevation - building on
window placement requirements - has created a framing to the classroom window with a coloured
panel placement above to reference the existing school façade. Whilst the solid elevational
treatment reflects the ancillary spaces (plant, WCs and storage) behind. These features sit
proportionally within the elevation to highlight teaching space locations and provide a repetitive
rhythm to the longer elevations.
The use of both consistent cladding arrangements and varying widths aims to articulate the
elevation by creating depth and interest to the facade, whilst clearly defining and reflecting the
internal functions within.
The contrast of the light/dark palette defines the teaching and ancillary
spaces allows the building to stand alone in it’s own right, whilst not
detracting from the existing school character. The dark grey cladding
Coloured metal cladding panel
allows the lighter entrance lobby to be clearly defined to aid Colour: Dark Grey
wayfinding.
The proposed rainscreen cladding panels are low maintenance and Engineering brick plinth
Colour: Buff
hard wearing, able to withstand the external elements and ensure
longevity.
4.8 Elevations
4.8 Elevations
KEY:
1. White Cladding 2. Dark Grey Cladding 3. Feature Blue Cladding 4. Buff Brick Plinth 5. PPC Aluminium Louvres 6. PPC Aluminium Glazing 7. Dark Grey Canopy 8.0 PPC Aluminium Parapet Coping 9. Landscaping
1 3 5 6 9 8 2 7 4
KEY:
1. White Cladding 2. Dark Grey Cladding 3. Feature Blue Cladding 4. Buff Brick Plinth 5. PPC Aluminium Louvres 6. PPC Aluminium Glazing 7. Dark Grey Canopy 8.0 PPC Aluminium Parapet Coping 9. Landscaping
7 2 6 3 8 5 1 4
In accordance with the requirements of CDM 2015 legislation, due regard to the ongoing maintenance of
the proposals has been made during the design process. This ensures that a simple and pragmatic approach
is incorporated for construction access and ongoing maintenance. Strategic decisions have been made as
follows:
A ground floor plant room, external Air Source Heat Pump compound and new sub-station, house all
principal plant and incoming services. These spaces have direct access from external hard-standing areas.
The Air Source Heat Pump compound will be positioned along the northern elevation and will comprise of
a fully screened external plant enclosure to provide safety and enhance aesthetics.
PV arrays will be provided to the roof and will be fully guarded by a 1.1m high parapet. A roof access
hatch with drop down ladder and handrail is proposed to ensure safe access.
Contractor access is proposed via Sir Walter Raleigh Drive and through the existing bus turning circle.
The location of the contractor compound will be determined by the appointed contractor during the later
design stages. Temporary ground protection will be required in these areas, in the form of a temporary
haul road, for transportation of modular units and other contractor deliveries and suitable root protection
will be required to ensure the protection T1 in accordance with the Arboricultural report.
Indicative contractor
access route
5.1 Introduction
Pick Everard have been appointed to allow for initial costing of the Sweyne Park School new build and wall to sleeper wall location. The sleeper walls comprise of 215mm thick blockwork with a
provide a basic performance specification for modular construction. The construction methodology, type minimum compressive strength of 7.4N/mm2 and they are supported on the strip foundations.
and design are the contractor’s choice however, general philosophies for substructure design for costing Complete design of the beam and block floor system to be according to specialist manufacturer’s
have been detailed in this report. The superstructure design must focus on a modular construction, details.
providing uniform batch construction that can be assembled on-site and can potentially be re-used on
future projects. The modular building support details to the foundations are currently unknown. Therefore, a
reinforced concrete upstand which will run the perimeter of the building has been allowed for in
The following document addresses the basic criteria for the structural design of the project through
the design. The upstand will provide a fixing surface for the modular columns and the cladding, if
performance specification. It describes the relevant design guides, superstructure design philosophy where
applicable and substructure design philosophy. required. Refer to general notes on the drawing 139534-PEV-XX-FD-DR-S-1011.
The Contractor is to develop the design providing a structural solution which complies with the Canopies above the entrances of the building should be designed by the superstructure designer
employee’s requirements. The employee’s requirements have been set out by the architect and any and should comply with the architect’s requirements (cantilever canopy). Additional pad and strip
structural proposal presented in this document satisfies these requirements. footings have been provided to accommodate additional superstructure components.
Should the tendering Contractor, consider alternate structural proposals resulting in a significant change to Covered Walkway
the overall building size; this must be reported back to the Employers Agent identified in the contract The current Architectural proposal is for a cantilever open sided canopy with glazed roof
documentation as soon as reasonably possible during the tender period. finishes. It is the contractor’s responsibility to complete a detailed design or provide a
proprietary solution that meets the architect’s requirements. Onerous deflection limits will be
5.2 Superstructure
required due to sensitive cladding.
Classrooms
The single storey educational building is to be modular construction. It is the contractor’s responsibility to An initial frame analysis of the canopy has been completed with glazing loads to determine the
propose the construction methodology, type, and complete detailed designs of the building ensuring they
foundation reactions to inform the substructure design for the cost plan. Under this solution a
meet all Architectural, Structural, and M&E requirements.
fixed base will be required to resist the moment from the cantilever canopy.
The modular construction has been assumed as a steel frame with bays at 3.5m centres and columns at
grid intersections. The typical modular bay is approximately 3.5m x 7.5m. Some bays are approximately 4m
long, refer to architect drawings. This layout for the modular buildings allowed for point loads to be
determined and mass concrete pads to be designed.
The foundation design assumed that the superstructure’s structural form is a steel framed structure.
Superstructure column locations were determined based on architectural grid intersections. These
column locations suit the current architectural scheme. If the architectural layout of the modular building
changes at the next stage, the foundation scheme will require amendments as well, as the locations of the
point loads from the superstructure will change.
The roof structure was assumed to comprise cold formed purlins supported on the modular structure.
Finishes were considered as lightweight panels.
The ground floor slab comprises a precast beam and block floor system with a 300mm ventilated void
below. The precast beams are 225mm deep and have a maximum span of 4.2m. They span from sleeper
SWEYNE PARK SCHOOL | DESIGN AND ACCESS STATEMENT | AUGUST 2020 Covered Walkway
5.0 STRUCTURAL AND CIVIL ENGINEERING
Mechanical ventilation has been provided to all classrooms, Office Accommodation and Circulation A new mains cold water supply is provided to the new building extending from the site boundary pulsed
Corridors utilising Mechanical Heat Recovery Units. These offer full fresh air with no recirculation, and meter point and serves all sanitaryware and drinking water points from the building entry point in the
have operating efficiencies up to 98%. A typical classroom will use up to one million litres of fresh air per Ground Floor Plantroom. The incoming mains water supply incorporates a secondary water meter on
hour, which shall be filtered and heated to meet the design temperature and CO2 control of each space. entry and acts as a leak detection system monitored by the building management control system, which
The configuration allows easy access from below the ceiling through access points to allow filter changes logs the water usage through both meters and sets an alarm when they fall out of range suggesting a leak in
and routine maintenance of the low Watt fans. the primary supply pipework from the site boundary, which would normally go un-noticed for a period of
time costing lost revenue.
The mains cold water also feeds the domestic hot water system, which comprises a buffer storage vessel
which is provided with an indirect heating coil fed from the air source heat pump system, providing a very
efficient water heating system. When temperatures are low in winter outside the lower performance of
the heat pumps is covered by the photovoltaic panels which serve to offset some of the inefficiencies in
cold weather.
The hot water is controlled via the building management control system and located in the plantroom is
easily access for routine inspection and maintenance. The plantroom layout has allowed for the removal of
any piece of equipment without disturbance to other items of plant and ancillary equipment.
Ventilation serving the corridors will act as make up air to the toilet extraction system with heat being 6.4 Above Ground Drainage
recovered and put back through the corridors, ensuring the WCs are always negative in pressure to the Above ground waste systems are provided connecting from all items of sanitaryware and discharged to the
corridors. below ground drainage system. Access points for maintenance and inspection will be provided as dictated
under British Standards and Building Regulations.
The office is also ventilated and heated using a ceiling void mounted mechanical heat recovery unit and also
controlled locally from room sensors.
The design intent is to conceal as much of the above ground drainage waste pipework as possible using
riser boxings and UPS Service voids, which shall incorporate integral access points.
Lighting to office areas is via a retractable switch where switch on is manual, but if left on will automatically
switch off after detecting no occupancy in a given time.
Cold to Warm
External lighting on timeclock and photocell control provides pathway illumination all round and
illumination to covered walkways, with override switch control. The lighting design externally will be
designed for very low light pollution levels.
As part of the proposed scope of works the development of The Contractor is to engage a specialist to complete the design installation and commissioning
the new building on site, it will require new power supply.
Therefore, the design intent is to select and install new LV In line with Building regulation and BS 5839 the new building will be provided with provision for fire alarm
distribution boards into the new building to meet the demand and detection.
of the power and lighting requirements. The distribution
boards will be fitted with digital metering to ensure The strategy for the new building is to isolate these and resupply the new building without adversely
monitoring of electrical energy in use in line with TM39 and affecting other areas of the site. A new main fire alarm panel will be provided in the main entrance to the
Technical Annex 2G. building, with links to the existing site wide system.
LV Submains will be routed as shown on layouts via suitably rated / sized cabling complete with protective The new system in the building will be provided to meet category L2 system, complete with addressable
devices in accordance with 18th edition wiring regulations, to serve the following plant and equipment: - zone alarms and automatic detection including provision for void detection where void exceeds 800mm as
reflected on the layouts.
General Lighting and power distribution boards to serve all areas
Mechanical services plant and equipment
Fire alarm system
ICT equipment within office/hub Room
Supplies to specific loads including intruder, CCTV and large items of equipment
All low voltage switchgear, distribution boards, containment and cabling will incorporate an allowance of
10% spare capacity. Local distribution boards will be located strategically to be out of reach from the
pupils, all submains cables to and from these boards shall be thermosetting insulated, armoured cables
having low emission of smoke and fumes (LSZH). Wiring and cable containment will be run via dedicated
voids and risers via high level basket / trays /trunkings to facilitate the needs of the user.
General small power and data as reflected on the layouts will be provided in classroom, office, circulation
areas and plant room in line with the ESFA requirements outlined in the ADS and will need to be
coordinated with the final FF&E layout.
The building will be provided with a CAT 6a structural cabling installation. Cables will be installed from a The fire alarm will be covered by remote monitoring via connection back to the existing site wide system.
centrally located patch panel in the office/hub and will terminate in RJ45 data outlets. Provision of small All wiring associated to the fire alarm system will be run in suitably rated fire resisting cables, installed within
power throughout the buildings will comprise of twin socket outlets, single socket outlets and switched or dedicated basket / cable trays.
unswitched fused connection units. Installation will generally be flushed mounted with the exception of
where the sockets are defined as within dado trunking. Total 59 data outlets CAT6a are to be provided in Fire alarm detection devices will be installed in line with the ADS and requirements outlined in the Technical
the new building. Annex 2G, to ensure smoke or heat detection is applied correctly by means of alarm notification via
sounders and flashing beacons.
In addition to general power and teaching wall detail the Office/Hub space will be provided with dedicated
electrical supplies to suit the rating of the anticipated cabinets requirements, each circuit feeding ICT Wherever practical fire alarm break glass and call points will be located to ensure less prone to malicious
equipment will be designed with High Integrity Earthing. activation.
As part of the overall data allowance for the new build the scope must include for the provision of high- Intruder Alarm
level data points to suit all fixed CCTV which is to be installed within areas as shown on the drawings.
To assist the security measures of the site the new building will be fitted with provision for intruder alarm
The data installation will be installed in a cable basket/trunking and conduit installation. The building will be and detection, with the main panel (keypad) being located within the entrance, there must be an interlink
provided with access to Wi-Fi via building positioned wireless network transmission point, in line with with all site wide buildings.
Heat map produced by ICT specialist during the next stage.
7.1 Access
With the proposal located on the site adjacent to the existing buildings, it was
important to consider direct links to existing access points and desire lines. The
level nature of the site and proximity to existing buildings enables level access
routes to the provided throughout the scheme, offering full accessibility to all
users.
Existing access to the site itself provides suitable permeability from multiple
approaches and is deemed sufficient, as a result the existing access routes remain
unchanged.
There is one main entrance, located to the south to the proposed new build,
which serves as the teacher and pupil entrance. An additional entrance is located
directly opposite to the east, providing alternative access to the external locker
banks. . Level access will be provided at these entrances. These also operate as
fire escape exits, with a further fire escape exit to the north of the building at the
far end of the teaching corridor, this exit is also provided with level access. Secure plant access
The pedestrian access routes to building will be well lit and highlighted through Secondary
dedicated wayfinding. The lighting strategy is described in the Building Services Fire Exit
section.
Maintenance access to the roof is provided via a fold down stair from within the
corridor circulation space.
Secure plant access
Secondary entrance
providing access to
external locker banks
Lighting, finishes and colour schemes are to follow ‘best practice’ with reference to the need to those with requirements, with internal acoustic design criteria set in reference to BB93 and external acoustic design
visual impairment. criteria set in reference to BS 4214:201. Additionally, the Client requires that the development adheres to
the British Association of Teachers of the Deaf (BATOD) guidance. These are largely consistent with the
BB93 requirements, but where there is divergence, the more onerous design criterion has generally been
adopted.
Under the Site Waste Management Plans Regulations 2008 there is a requirement to appoint a principal An Archaeological desk-based assessment has been produced to support the planning application. Refer to
document ref: Sweyne Park School DBA
contractor and produce a suitable construction phase site waste management plan prior to
commencement of any site works.
8.1 Overview
The design of the building must support the wellbeing of building users, perform at the highest
standard, and be adaptable to changing climates and future demands. This will be a durable and
flexible building that will stand the test of time.
The proposed building will adopt a ‘Fabric First’ approach and will benefit from low U-values, high
standards of air tightness and daylighting. The daylight design attempts to provide a well-balanced,
glare free visual environment. Additionally, the following will be implemented.
• High efficiency lighting design and associated controls.
• Lighting will be dimmable to maximise potential benefit of daylight use.
• All lighting will use LED technology, this will minimise energy in use and optimise system life.
The proposed accommodation is to be located over a single storey (ground floor). The maximum height of
9.1 Use: the single storey teaching block proposed is be 4.93m above ground level.
Developing upon briefing requirements for an expansion to the existing school, the use of the
proposed new build is educational in order to enhance the existing provision. Therefore, this does 9.5 Landscape & Biodiversity
not amend or add any new building uses to the site, however it does allow the school to operate to While the majority of the surrounding area to the specific development area within the site are given over
requirements through additional provision of indoor teaching spaces. to large opening spaces in the form of playing fields and an all weather pitch, the courtyard created by the
proposed building provides opportunity to landscape this area and introduce an attractive soft planting
9.2 Amount strip to the west elevation. The proposed planting scheme will help soften the outlook from the existing
The proposal is for a single storey building, providing an overall gross internal area of 568m2 (gross school building, providing year-round interest and colour. The proposed planting species have been
external area: 605m2). The amount of provision has been determined by shortfalls highlighted by an carefully selected to include a range of native floral species which will enhance the biodiversity of the site,
initial school viability study. These spatial requirements have subsequently been assessed and in accordance with the recommendations set out in the Ecology Report.
arranged to provide the school with an efficient layout to satisfy operational requirements.
The initial site assessment has identified habitat or potential for bats, badger and hedgehog and
9.3 Layout precautionary measures will be taken to mitigate the effects where possible. Appropriate protection
measures will be included around T1 to ensure no damage to the tree roots. Bird nesting boxes will be
The building design is simple and efficient rectangular form aligned to the adjacent all weather pitch
installed on the existing school building in accordance with the recommendations set out in the Ecology
on a south-east axis. The plan form accommodates a central spine corridor double banked with
Report.
classrooms, a staff office and WCs are located close to the building entrance to provide passive
supervision. A large, external canopy defines the main entrance to the south and provides
protection for the banks of external lockers located either side of the generous lobby, a secondary 9.6 Appearance
access/egress point is located directly opposite the main entrance, with a further emergency exit As detailed in Section 4.7, the limited palette of high-quality materials proposed for the new build block at
located at the far end of the teaching corridor. The east elevations provide external access to the Sweyne Park School provides the sophistication desired by a secondary school building. The high quality,
secure plant room, with an additional external plant compound location to the north of the building. low maintenance materials and robust, efficient detailing respond to the local setting and provide the
Access to the roof is gained via roof hatch and drop down stair in the central corridor. school with a maintainable building for years to come. The proposed building form and scale creates
architectural prominence without overwhelming the adjacent context. The features implemented across
the elevations have been used to define internal functions and differentiate the two clear functions of the
teaching and ancillary spaces. This results in a contrast in both cladding colour choices and also
architectural language to suggest playful introductions of colour to highlight primary elements. A
prominent canopy clearly highlights the entrance to aid wayfinding and pupil movement. An area of subtle,
low maintenance landscaping and the creation of a triangular courtyard space initiates place-making
between the new and existing buildings.