I. Situation Overview
DSWD DROMIC Report #1 on the Flooding Incident in Zamboanga City as of 01 February 2023, 6PM | Page 1 of 2
IV. Response Actions and Interventions
1. Standby Funds
• ₱923.49 million Quick Response Fund (QRF) at the DSWD Central Office.
• ₱5 million available at DSWD FO IX.
b. Other Activities
DATE ACTIVITIES
01 February 2023 • DSWD FO IX closely monitors the situation and coordinates with the
officials of the affected areas for relevant updates and any request
of relief augmentation.
• All Quick Response Team (QRT) members are on standby for
possible deployment to the affected areas.
*****
The Disaster Response Operations Monitoring and Information Center (DROMIC) of DSWD-DRMB is closely
coordinating with DSWD FO IX for significant disaster response updates and assistance provided.