You are on page 1of 11

Job Safety Analysis

RSG-HS-FRM-0001

RED_SEA_GLOBAL

Instructions for completing Job Safety Analysis (JSA) form

Section I -Enter general information about the site and job task.

Section II - Determine whether any of these operations apply to the job task to be performed. Make note of any special training, permit, certification, and risk assessment requirements.

Section III - Identify any human/organizational factors that could impact the ability to perform the work safely.

Break the job down into steps - Be as specific as possible. Write each job step in a new row of column A (Activity/Step). It’s a good idea to leave an extra row between steps in case you
1 need them later. Add additional rows to the table as needed, or if completing the JSA on paper, print additional copies of the sheet to accommodate all job steps.
Determine the hazards associated with each job step and write them in column B (Hazards). Use the examples of hazards provided below to trigger your thinking about different types of
2 hazards and energy sources.
List any control measures that will be taken to ensure that step is done safely in column C (Control Measures). Use the control measure examples and hierarchy provided to trigger your
thinking about different types of controls and their effectiveness at reducing risk. Controls toward the top of the table tend to be more effective at minimizing the severity and/or likelihood
3 of an event than the controls toward the bottom of the table. If this job involves a Life Crucial Operation, continue to step 4. Otherwise, repeat steps 2-3 for each of the job steps identified,
Considering the hazards involved and the control measures that will be in place, determine the worst credible severity of an incident that could result from this job step. Use the severity
4 table provided. Write the severity number in column D (Severity).
Considering the hazards involved and the control measures that will be in place, determine the likelihood that an incident will result from this job step. Use the likelihood table provided.
5 Write the likelihood number in column E (Likelihood).

Multiply the severity number by the likelihood number and enter the product in column F (Risk).
6

Consider the risk rating against the thresholds provided in the Overall Risk Ratings.
7

P Very low and low risk ratings of 1-2. This level is generally considered acceptable provided that all control measures are applied.

Medium risk ratings of 3-9. Medium risk requires a planned approach to control the hazard and applies additional controls if required. Action taken must be documented on the
P
risk assessment form.
High and Very High-Risk ratings of 10-25. For all high and very high risk, Column G (Additional control measures) must be implemented to further reduce the risk to a medium or
P low level. Such activities shall not be proceeded until applying additional control measures. The Construction Director/Manager or facility Manager must personally review the
activities with a High or Very High residual risk score and approve additional control measures by signing off the JSA
Repeat steps 2-7 for each of the job steps identified.
8
Section IV - Provide the name, company, and title of those who prepared and reviewed/approved this form in the signature box provided. The Construction Director/Manager or facility Manager must
review and approve the additional control measures that have a High or Very High-Risk rating before proceeding the task. Additional space is also provided for crew members to sign the JSA if desired.

Reference Table in completing Section III – Job Safety Analysis (Column B – Hazard)
Biological & Electrical Chemical Gravity/Height Mechanical & Motion
Environmental Arc Flash Air Emissions Equipment Tipping/Collapsing Being Thrown Off/Under Equipment
Altitude Buried Utilities Chemical Products; Excavation/Trench Disintegration of Moving Components
Animal Bite/Sting Damage to Leads/Cables •Carcinogenic Falling Objects Driving/Vehicle Traffic
Blood-Borne Pathogens Damage to Switches •Combustible/Flammable Floor Openings/Edges Ejection of Workpiece/Debris
Contaminated Energized Circuits/Conductors •Explosive Grating Removed Entanglement
Food/Water Inadvertent Energization •Toxic Inadequate Support Friction
Insect-Borne Disease Lack of Isolation/Grounding •Corrosive Lack of Access Ladders/Stairs Movement/Shifting
Pests Missing/Damaged Insulation •Reactive Suspended Load Moving Parts
Poisonous Plants Overhead Lines Client/Process Chemicals Unstable/Insecure Materials Pinch/Crush Points
Precipitation Overload of Circuits Lack of Containment Work Above/Below Others Projectiles
Temperature/Humidity Stored Energy (Batteries/Capacitors) Leakage/Spills Work at Height/Fall Hazards Rotating Equipment
Unsanitary Conditions Water Near Electrical Conductors Material Incompatibility Walking/Working Surface; Sharp Edges, Corners, or Points
Weather Produced/Disturbed by Work; •Slippery Shearing
•Asbestos •Uneven Stored Energy (Springs/Accumulators)
•Lead •Obstructed Striking
•Silica •Steep Trapped Between Equipment and Fixed
•Welding Fumes •Moving/Swaying/Pitching Structures
•Dust •Insufficient/Unstable Unexpected/Uncontrolled Movement
Water Discharges
Wastes Generated;
•Hazardous
Pressure Work Environment
•Non-Hazardous
Abrasive Blasting Cluttered
Compressed Gases Confined Space
High Pressure Fluid Damaged Tools/Equipment
Pressure Testing Entrapment
Pressure Erosion
Washing/Blasting Hazardous Atmosphere;
•Oxygen Rich/Deficient
•Contaminants
Ignition Sources
Inadequate Ventilation
Radiation Poor Lighting/Glare Sound Ergonomic
Intense Light Restricted Access/Egress Continuous Noise Awkward Postures/Movement
Lasers Runoff Intermittent Noise Excessive Force/ Exertion
Microwaves Extreme Noise Heavy/Awkward Load
Naturally Occurring Impact Noise Repetitive Motion
Radioactivity Radioactive Same Position
Material Vibration
X-Rays

Job Safety Analysis


Rev.00, 30 March 2023 Page 1 of 2
Job Safety Analysis
RSG-HS-FRM-0001

RED_SEA_GLOBAL

Reference Table in completing Section III – Job Safety Analysis (Column C – Control Measure)

Controls Examples
Elimination
(Remove the hazard altogether)

Substitution
(Replace the material/process with a less
hazardous one)

Engineering/Isolation
(Design effective control measures to protect
people and the environment)

Warning
(Alert people to the hazards)

Administrative
(Provide training, procedures, etc.)

PPE
Less (Personal Protective Equipment)
Effective

Reference Table in completing Section III – Job Safety Analysis (Column E –


Reference Table in completing Section III – Job Safety Analysis (Column D –Severity)
Likelihood)

Impact On Chances of
Severity Level Likelihood Level Probability
Occurrence
People Equipment / Property

Extensive losses of high value


equipment/property Likely to occur within the next 1
Almost year.
Major 5 Single / Multiple fatalities 5 0 in 100
Loses exceeding SAR 3,750,000; or Certain More than 80% chance of
Major unplanned impact on budget and occurring
schedule

Losses of equipment/property that


cannot be readily replaced; or Likely to occur within the next 2
Injury or illness resulting in
years.
Significant 4 permanent total or partial Likely 4 0 in 1,000
Losses exceeding SAR 375,000; or More than 60% and less than 80%
disability
Significant unplanned impact on project chance of occurring
budget

Loss of equipment that can be readily


Likely to occur and may do so
Injury or illness resulting in replaced; or
within the next 3 years.
Modrate 3 medical treatment or temporary Possible 3 1 in 10,000
More than 40% and less than 60%
disability/loss of function Losses exceeding SAR 37,500; or
chance of occurring
Minor impact on the budget

Unlikely to occur and may do so


Loss of equipment that can be readily
Injury or illness requiring first-aid within the next 5 years.
Minor 2 replaced, or Rare 2 1 in 100,000
treatment only More than 20% and less than 40%
Losses less than SAR 37,500
chance of occurring.

Extremely unlikely to occur within


Negligible 1 Near Miss/no harm Unlikely 1 the next 5 years. 1 in 1,000,000
equipment or property
Less than 20% chance of occurring

Reference Table in completing Section III – Job Safety Analysis (Column F – Risk)
Risk Matrix
Very Low Low Medium High Very High
Severity
Likelyhood 1 2 3-9 10-16 20-25
1-Negligible 2-Minor 3–Moderate 4-Significant 5-Major
Medium Hgh High High High High and Very High-Risk ratings of 10-25.
5 – Almost Certain
(5) (10) (15) (20) (25)
Additional control measures must be implemented to further reduce the High
Medium Medium High High High
4 – Likely and very high risk to acceptable level.
(5) (5) (12) (16) (20)

3 – Possible
Medium Medium High High Note: The Construction Director/Manager or Facility Manager must personally
-5
(5) (5) (12) (15) review the activities with a High or Very High residual Risk score and approve
Low Medium Medium Medium High
2- Rare suitable additional control measures by signing the JSA.
(2) (5) (5) (8) (10)
Very Low Low Medium Medium Medium
1 – Unlikely
(1) (2) (5) (4) (5)

Job Safety Analysis


Rev.00, 30 March 2023 Page 2 of 2
Job Safety Analysis
RSG-HS-FRM-0001

RED_SEA_GLOBAL

Section I – General Information


Emergency Procedure

Energency Contact Name Energency Contact Phone Number

Primary Contact Magzoub Mustafa Primary Contact 59 690 1035

Secondary Contact Syed Saddam Secondary Contact 54 582 3228

Details

Company Name
Program / Facility / Operations Turtle Bay Village TBV / Red sea Global Abdul Mohsen Al Tamimi Contracting Company
Date
Project Name / Facility Details RO3-CO2CO2 TURTLE BAY-PKG 05 1/20/2024
Category
JSA /Risk Assessment Title Installation of Air Curtain New Revised

Specific Location Village Center, Professional & Non-Professional Neighbourhood Centers. Building NA

JCB Telehandler, Forklift,Mobile scaffold platform,, Platform Ladders, Hand held power
Plant Tools & Equipment Required Area
tools, manual Handling tools, PPE's.
--

Work Scope/Description Installation of Air Curtain at Village Center, Professional & Non-Professional Neighbourhood Centers.

Section II – Does this job require any of the following operations?

✓ Requires formal/special training n Requires certification or Competent/Qualified Person designations

Requires a permit/form/report ∆ Life Crucial Operations = Requires full Risk Assessment

Details YES Details YES

Aerial Lifts ✓ ∆ Cranes - Critical lift ✓ n ∆

Confined Space ✓ n ∆ Hot Work ✓


Loading/Unloading
Dismantling and Demolition n ∆
Material
Electrical Hazards ✓ n ∆ Noise Exposure ✓
Powered Industrial
Excavation/Trenching ✓ n ∆ ✓ n ∆
Trucks
First Line Breaks ✓ n ∆ Radiation Area Work ✓ n
Grating/Floor Plate/ Guardrail
∆ Respiratory Hazards ✓
Removal
Hazardous Energy Control ✓ n ∆ Roof Work ✓ n ∆
Hazardous Materials
✓ n Scaffolding ✓ n ∆
Asbestos & Lead Work
Hazardous Materials
✓ n Site/Vehicle Traffic ∆
Crystalline Silica & Cadmium
Hazardous Waste Operations ✓ Steel Erection n ∆

Heavy Equipment ✓ n ∆ Work at Height (> 6 ft) ✓ n ∆

Rigging, & Cranes ✓ n ∆ Other

Section III– Job Safety Analysis

(D) (E) (F) (G) (H) (I) (J)


(B) Severity Likelihood Risk Additional Control Measures Severity Likelihood Risk
(A) (C)
Hazards
Activity Step Control Measures
Ensure the Implementation of "No permit, No
work" system.
Obtain valid Permit-to-work (Genaral work
Permit_ RSG-HS-FRM-0093). A competent person & HSE Representative
for scaffold erection RSG-HS-FRM-0042_ Roof shall monitor the activities & personnel
Access Permit shall be followed. Conduct joint site inspection.
Lack of communication. For loading / ofloading Green Work Authorized personnel to be conduct training to
Secure the necessary Work Permits Working without valid Permit-to- checklist_RSG-HS-FRM-0026. 2 2 4 2 1 2
workforce prior performing specific task.
work. All potential hazards/control measures must be Conduct toolbox talk meeting to the
described to workers. workforce regarding safe system of work.
RA must be briefed to whole crew and have Use suitable tool/PPE for the right job.
record with their initials.
Ensure that all persons have attend Excavation &
Trenching Safety Training.

involve and communicate all the ralevent parties


Selecting the Area Lack of communication.
prior to select the area for test. 2 1 2
(For installation of air curtain(s)) Un-approved drawing / layout.
The drawing / layout must be approved by RSG.

Job Safety Analysis


Rev.00, 30 March 2023 Page 1 of 18
Job Safety Analysis
RSG-HS-FRM-0001

RED_SEA_GLOBAL

Follow the instructions under RSG-HS-


Pre-task planning must be held RSG-HS-
GEN 0006_Guideline_ Safe Use of Mobile
ADM 0009.
Devices in
All drivers must be trained and a valid Driving
Vehicles.
license holder.
Daily vehicle checklist to be conducted &
Over speeding. All vehicles shall be fitted with audible reverse
available in the vehicle.
Collision with vehicle, objects & alarms.
Mobilization of Personnel, Vehicles, Appropriate signage must be displayed.
pedestrians. All drivers shall use the seat belt while driving. 2 2 4 2 1 2
Equipment & materials Mandatory & job-specific PPE
Un-secure load. Pedestrians shall be at a safe distance from
Ensure competent Banks man for all vehicle
Use of mobile devices while driving.. moving vehicles.
movement
High visibility vests shall be worn by all workers
Secure loads and equipment properly with
operating close to vehicles.
strap belts
Clear traffic signs shall be provided at the work
Vehicle shall be reverse parked in the
site
designated parking place at the site.

Follow the manual handling techniques Eliminate the need of manual handling.
under_RSG-HS-COS-0006 _ Loading Unloading Divide the load into parts.
Ergonomics. and Manual Handling. Use mechanical aids to reduce the manual
Work related upper limb Think before lifting! Is it heavy (above 35 pounds handling.
2 2 4 2 1 2
disorder.Muscle stress. [15.9 kilograms]) Is it large or awkward. Ensure the provvision of frequent rest breaks
Musculoskeletal disorder MSD's. Where is the center of gravity? Can you manage during the job to reduce the work exposure.
it alone. Ensure the proper PPE's under the reference _
Use the strong muscles and bones of your legs RSG-HS-COS-0001.

Follow RSG-HS-FRM-0040 form for machinery


inspections.
Un-inspected machinery, tools &
Ensure that the tools must not be shattered.
equipments. 2 1 2
Right tool for right job.
Himemade tools
Ensure that the tool must not be damaged and
fit for use.

Scaffold erection must be carry out under the


RSG-HS-FRM-0046_ Scaffold Checklist.
Ensure the complicance of ladder requirements
under RSG-HS-COS-0008_Scaffolds and Portable
Ladders. section 4.6.7, 4.6.8 & 4.6.9.
Ensure the proper protection with railing
Avoid working at height if possible.
system, and toe-board.
Fall of materials. The scaffolders must have valid 3rd party
Tools must be inspected, and must not be
Lack of railing system. shattered. certificate / card.
Un-inspected platform. Laddars must be secured from top & bottom Ensure the provision of guardrails &
Collapse of structure. sides to maintain the stability. toe boards.
Use of unsuitable, damage and faulty Ladder shall be raised at least one meter above the Implement the fall arrest system.
materials. landing platform and should be secure at three scaffolding shall be tagged and inspected
Scaffold Erection / Dismantling 3 2 6 2 1 2
Unsecured ladder slipping. locations. andapproved by the competent person at the
Overloading of platform and board. Materials, clamps shall not drop or through:, start of each working day.
Loose joints, clamps. ensure the use of properbag. All tags shall be maintained at the scaffold
Loose materials and clamps should not be kept access point, show the date of scaffold
Lack of competency.
unattended on the working platform.
Lack of resources inspections, by whom, and be weather-
Proper signage must be displayed to identify the risks
Lack of communication. resistant.
and hazards.
Advance & inspected PPE's to be provided
Notify supervision immediately if a scaffold is
damaged, weakened, or otherwise deficient.
A red tag should be displayed at eye level on the
scaffolding during erection and modification to
indicate that the scaffolding is under construction and
should not be used.

Job Safety Analysis


Rev.00, 30 March 2023 Page 2 of 18
Job Safety Analysis
RSG-HS-FRM-0001

RED_SEA_GLOBAL

work be done on the ground avoiding


exposure to working at height, if possible.
The worker must be competent to carry out the physical barriers such as guardrails and
job. lockable gates be erected to prevent
Fall of Personnel. The activity must be carry out under the close unauthorised access.
Ergonomics. supervision. fall arrest system such as overhead rail
Serious personal injury (Multiple Follow the manual handling techniques systems or multiple anchor points to cover the
broken bones). under_RSG-HS-COS-0006 _ Loading Unloading 2 2 4 working area and personal harnesses with 2 1 2
Slip, trip & fall. and Manual Handling. lanyard shock absorbers or self-retracting
Lack of competency. Ensure the provision of full body harness to lifelines be used to minimise the risk of injury
Lack of supervision. avoide personal falling. should a fall occur
Ensure the use of tool lan-yard to secure the signage be implemented to control
tools. unauthorised access or warn of the dangers in
the area of work.
Suitable PPE's to be provided.

RSG-HS-FRM-0034_ Pre-Mobilization Inspection


Report - Construction Equipment and Light
Loading / unloading of air curtain(s) and Un-inspected machinery and Vehicles must be followed.
other materials. equipments. The machinery must be inspected routinely by a
(By help of; Poor maintenance. competent person and a checklist must be 2 1 2
1- Forklift. Machinery break-down. followed.
2- JCB Telehandler.) Hydraulic failure. Proper maintenance must be carried out to
avide any machinery break-down and hydraulic
failure on site.

Never stand or work under the suspended load.


Movement must be in site speed limit to avoide
any over-turning.
Suspended Load. Always move under the instruction of a flagman
Collision with other vehichle. / banksman to avoid any collision with other
1- FORKLIFT Over-turning. vehicles at work site. 2 2 4
Over-loaded. Know the load before loading, do not exceed the
Un-secured load. permissable load limit.
The load must be secured properly before
making any movement fron one place to
another.

There must be separate zone(s) for the


machinery and pedestrians movement.
There must be proper segraded pedestrians walk
Area can be barricaded to avoide any un-
ways provided to avoide any accident.
Collision with pedestrians. authorized entry to prevent accident.
Make it clear where the forklift can and can’t go. 2 2 4 2 1 2
Proper signage must be displayed and
Using direct signs for the people walking around
designated flagman to be provided with the
can save a lot of accidents from happening.
machine to ensure the safe movement and to
prevent any collision with pedestrians.

Ensure that the operator understands how to


add the attachments safely for the best results.
Attachement hazard Before using any attachments, be sure that they 2 1 2
have been well maintained and inspected before
use.

Always mark where the forklift can and cannot


go.
If there are any lower ceilings, mark their height
Overhead Obstructions 2 1 2
for the operator.
Different sized forklifts will know what the size
of their machine is.

You will want to ensure that the floors are clear


and clean before allowing any moving machinery
Floor/ground condition to roam about the facility. Housekeeping is 2 1 2
crucial to maintain proper safety.
Potholes to be protected properly.

Job Safety Analysis


Rev.00, 30 March 2023 Page 3 of 18
Job Safety Analysis
RSG-HS-FRM-0001

RED_SEA_GLOBAL

Eliminate the need of manual handling.


Ergonomics. Follow the manual handling techniques
Divide the load into parts.
Back pain and back injuries. under_RSG-HS-COS-0006 _ Loading Unloading
Use mechanical aids to reduce the manual
Work Related upper Limb Disorder and Manual Handling.
handling.
WRULD's. Where is the center of gravity? Can you manage
3 2 6 Ensure the provvision of frequent rest breaks 2 1 2
Musculoskeletel disorder MSD's. it alone.
during the job to reduce the work exposure.
Sustained awkword posture. Maintain good housekeeping to avoide any
Ensure the proper PPE's under the reference
Muscle atress. tripping.
RSG-HS-COS-0001.
Slip, Trip & fall. Use the strong muscles and bones of your knees.

Ensure all working personnel to


undergo mandatory training to enhance
knowledge on the activity.
Ensure site in-charge construction team
The operator must have a valid SAUDI driving
are full time in supervision until the
Lack of Training; license and 3rd party training certificate
completion of the activity.
Miscommunication according to the operated machinery. 2 2 4 2 1 2
HSE Team to ensure all workers are
Lack of Supervision Ensure operation checklist is available
done safety induction prior to
and conducted prior to commencement
commence work at the job site.
of activity.
The task must be carried out under the
supervision.

Crushing hazard decals are clearly displayed on


the machine. A backup alarm and a horn are
Crushing, Shearing, Collision: fittedto warn of movement. A revolving beacon
(between boom & frame) option is fitted to Australian units. Safe
(Underneath attachment when operatingprocedures are placed in the
2- JCB TELEHANDLER boom is being lowered) operator’s manual. 2 2 4
(Moving parts). A back-up alarm and a horn are fitted to warn of
movement.
A revolving beacon option is fitted to units.

Fully adjustable seating provides a comfortable


environment for the operator. Safe operating
Ergonomics
procedures and limitations are provided at the
control station and in the operators manual.

Never stand or work under the suspended load.


Movement must be in site speed limit to avoide
any over-turning.
Suspended Load. Always move under the instruction of a flagman
Collision with other vehichle. / banksman to avoid any collision with other
Over-turning. vehicles at work site. 2 2 4
Over-loaded. Know the load before loading, do not exceed the
Un-secured load. permissable load limit.
The load must be secured properly before
making any movement fron one place to
another.

There must be separate zone(s) for the


machinery and pedestrians movement.
There must be proper segraded pedestrians walk
Area can be barricaded to avoide any un-
ways provided to avoide any accident.
Collision with pedestrians. authorized entry to prevent accident.
Make it clear where the forklift can and can’t go. 2 2 4 2 1 2
Proper signage must be displayed and
Using direct signs for the people walking around
designated flagman to be provided with the
can save a lot of accidents from happening.
machine to ensure the safe movement and to
prevent any collision with pedestrians.

Ensure that the operator understands how to


add the attachments safely for the best results.
Attachement hazard Before using any attachments, be sure that they 2 1 2
have been well maintained and inspected before
use.

Always mark where the forklift can and cannot


go.
If there are any lower ceilings, mark their height
Overhead Obstructions 2 1 2
for the operator.
Different sized forklifts will know what the size
of their machine is.

Job Safety Analysis


Rev.00, 30 March 2023 Page 4 of 18
Job Safety Analysis
RSG-HS-FRM-0001

RED_SEA_GLOBAL
Ensure all working personnel to
undergo mandatory training to enhance
knowledge on the activity.
The operator must have a valid SAUDI driving
Lack of competency of license and 3rd party training certificate
Operator. according to the operated machinery.
flagman Flagman must be trained to carry out the task 2 1 2
Miscommunication safely.
Lack of Supervision Ensure operation checklist is available
and conducted prior to commencement
of activity.
The task must be carried out under the
supervision.

Avoide working at height, if there is another


RSG-HS-COS-0002_Work at Height to be
way to perform safely.
followed for safe operation.
Provide the proper fall arrest system (guard
Ensure proper working platform with complete
railings & toe-boards) to avoid any materials
fall protection.
Work at Height. falling.
Ensure the scaffold platform is properly erected
Falling objects. The platform must be inspected and tagged by
Installation of air curtain with "Safe to use" tag..
Un-inspected platform. a competent person (certified scaffold
(by use of Mobile access tower - light Ensure castor wheels are locked and out rigger 3 2 6 2 1 2
Collapse of structure. inspector).
weight) in place..
Un-expected movement of platform. The wheels must be properly locked to
Work materials strictly not allowed to be stored
Over-loaded platform. prevent any un-expected movement of
on platform except for working tools.
platform during the operation.
Always comply with the WLL & man loading
Ensure the provision of advanced PPE's (Tool-
capacity.
Lanyard, full-body-harness, hard hat with chin
Scaffold access must be free from obstruction.
strap, hand gloves)

Ensure ladders are on a level, stable surface


and that the upper section of the ladder is in
Ensure that the ladder is placed on a level, stable
front of the bottom section when facing the
surface.
worker.
Select the right type of the ladder for safe
There are three grades or types of ladders.
operation (platform ladder).
Un-even surface. Grade 1AA and, grade 1A are recommended
Do not pull or move ladders from side to side, as
Poor selection of ladder. to carry out the job safely.. Ensure you are
over time this movement can cause ladders to
Un-inspected ladder. 2 2 4 using the type of ladder that is appropriate for 2 1 2
become less stable and more wobbly.
both the work environment and the job at
Ladder must be inspected by competent person
hand.
only.
Ladder inspection should be carried out before
Choose a step ladder that is about 3 feet shorter
and after use. Any visible damage must be
than the highest point you will be working, as
reported, and damaged ladders must be
this ensures a more stable base.
disused until they can be repaired.

under RSG-HS-COS-0008_Scaffolds and Portable


The ladder securely fixed to prevent slipping
ladders.
outwards or sideways or securely footed at all
Laddars must be secured from top & bottom
times.
Use of Platform ladder sides to maintain the stability.
Fall from height. Person must hold the ladder while another
(During installation of Air curtain just in Ladder shall be raised at least one meter above
Falling objects. 2 2 4 operative working on it. 2 1 2
case there is no access for mobile the landing platform and should be secure at
Materials should not be placed above the
platform) three locations.
thread of ladders/step ladders.
Ensure the use of tool-lanyard to avoide any
Do not carry any materials in one hand while
falling of hand tools and wear the tools handling
climbing or getting down from ladder.
belt to carry safe & secure tools.

Ensure ladders are on a level, stable surface


and that the upper section of the ladder is in
Ensure that the ladder is placed on a level, stable
front of the bottom section when facing the
surface.
worker.
Select the right type of the ladder for safe
There are three grades or types of ladders.
operation (platform ladder).
Un-even surface. Grade 1AA and, grade 1A are recommended
Do not pull or move ladders from side to side, as
Poor selection of ladder. to carry out the job safely.. Ensure you are
over time this movement can cause ladders to
Un-inspected ladder. 2 2 4 using the type of ladder that is appropriate for 2 1 2
become less stable and more wobbly.
both the work environment and the job at
Ladder must be inspected by competent person
hand.
only.
Ladder inspection should be carried out before
Choose a step ladder that is about 3 feet shorter
and after use. Any visible damage must be
than the highest point you will be working, as
reported, and damaged ladders must be
this ensures a more stable base.
disused until they can be repaired.

The area must be identified and the associate


Other hazards associated with the air Un-identified area.
drawing must be communicated with RSG team 2 1 2
curtain installation process. Lack of communication.
for approval and continue the work.

Ensure the proper PPE's to handle the materials ,


Sharp Edges. hand protection must be worn to avoid any 2 1 2
injury woth the sharp edges.

Job Safety Analysis


Rev.00, 30 March 2023 Page 5 of 18
Job Safety Analysis
RSG-HS-FRM-0001

RED_SEA_GLOBAL

Ergonomics. Eliminate the need of manual handling.


Work related upper limb Always mark where the forklift can and cannot Divide the load into parts.
disorder.Muscle stress. go. Use mechanical aids to reduce the manual
Musculoskeletal disorder MSD's. If there are any lower ceilings, mark their height handling.
2 2 4 2 1 2
Back pain and back injuries. for the operator. Ensure the provvision of frequent rest breaks
Sustained awkword posture. Different sized forklifts will know what the size during the job to reduce the work exposure.
Muscle atress. of their machine is. Ensure the proper PPE's under the reference _
Slip, Trip & fall RSG-HS-COS-0001.

Do not energize tha facility until the connections


are in place.
If the area is energized, isolate the concerned
area from electric power supply.
Electrical Hazards:
After the isolation of the area, Lock-out Tag-out
Electrc shock.
LOTO must be implemented to control the 2 2 4
Electrical burn.
electrical hazards.
Electrical fire & explosion.
The process must be communicate with all the
ralevent parties.
Ensure the provision of suitable fire
extinguishers in place.

Portable power tools shall be stored


in clean and dry conditions.
Where possible, potentially hazardous
Training would be required in all aspects
portable power tools, including all power drills
mentioned here – and refresher training –
(240v), are substituted or replaced with less
maybe in the form of tool-box talks.
hazardous alternatives.
Provide machine guards for dangerous parts of
Portable power tools shall not be left
the equipment.
lying around the work area where
Machine guards are properly maintained (not
they could be damaged.
missing ordamaged).
Portable Power Tools Hazards; Do not wear loose clothing, jewelry, tie, or
Portable power tools shall be equipped with
Entanglement gloves when operating a machine. Keep all
properly functioning constant pressure switches
Trapping loose clothing buttoned up, or tucked in.
or controls that will shut off the power when the
Collision / Impact Strong Firm frip to handle the drill.
pressure is released (i.e., a
Crushing Cords, cables, etc., shall be
“dead man” switch).
Use of portable power tools: Piercing/injection/stabbing/puncture positioned where they are not likely
Power tools shall not be equipped
Use of battery powered drills Friction/ abrasion 3 2 6 to be damaged (e.g., run overhead) 2 1 2
with trigger locks.
Use of portable grinders Shearing/severing or shall be otherwise protected from
The operating control on hand-held
Cutting damage (e.g., running them inside
power tools shall be located to
Drawing in impact resistant conduit or using
minimize the possibility of inadvertent
Ejection of particles abrasion resistant supply leads).
operation.
Burn Use of the electrical cord for hoisting
Before they are set down, rotating
or lowering power tools is
portable power tools shall be switched off and
prohibited.
held until the rotation has completely stopped.
HS Team will ensure all portable
They shall not be stopped by grasping the
power tool are inspected any
rotating assembly.
damaged/defects prior to use.
Power tools shall be disconnected from the
Ensure all source of power
power source before changing bits, blades,
connection are meet the power tool
cutters or wheels.
manufacture rated capacity to
prevent shortage or overrated
power.

training must be provided to minimise


Follow the manual handling techniques
exposure to these hazards and risks.
Ergonomics. under_RSG-HS-COS-0006 _ Loading Unloading
Operators are required to remove all
Slips, Trips, Falls and Manual Handling.. 2 2 4 2 1 2
jewellery, tuck in loose clothing and tie back
Lack of competency. Place the cable properly to avoid the tripping.
long hair.
Ensure the proper PPE's
All approved personal protective equipment
(PPE) is used where required.

Job Safety Analysis


Rev.00, 30 March 2023 Page 6 of 18
Job Safety Analysis
RSG-HS-FRM-0001

RED_SEA_GLOBAL

Portable power drills are regularly inspected


and maintained to help minimise the risk of
exposures to these hazards.
All portable power tool maintenance is
documented and tagged.
Pre-use check of drill prior to start the activity. Exposure to noisy ITD workshop environments
Wear mask to avoid inhalable dust. is monitored and evaluated regularly for all
Noise. The cables must be insolated properly. workers.
Dust, Fumes and Vapours. Guards & safety devices must be in place and Worker training is provided to minimise
Vibration. working condition. exposure to these hazards.
Lighting. Suitable fire extinguisher must be placed in area. 2 2 4 All ducted dust and fume extraction systems 2 1 2
Un-inspected tools / equipment. Emsure the implementation of color coding are connected and operational, fully
Explosion and Fire system. maintained and cleaned as required.
Ensure the use of ear plugs / ear muf to reduce Good lighting is provided to all workspaces
the exposure of noise. and this is maintained on a regular basis.
Fluorescent tubes are checked and replaced as
required.
Take frequesnt rest breaks during the job to
reduce the work exposure.
All approved personal protective equipment
(PPE) is used where required.

Visual checks are made of all portable power


drill, their electrical switches, plugs and power
leads, etc.
Electrical safety inspections, testing and tagging,
etc. are completed regularly.
Portable power drill are to be used only where
there is a RCD safety trip switch connected?
Warning “Danger” tags (or similar) are affixed to
all portable power tools under repair or
Electrical Hazards. 2 1 2
maintenance preventing workers from using
them.
Electrical maintenance on all portable power
tools is documented.

The requirements for the safe use of


Defective hand tools conditions such non powered hand tools include:
as: Selecting the appropriate or
Split shafts on tools such as on suitable tool for the task;
a hammer or an axe; Ensuring that the users carry out regular
Loose heads on tools, inspection of the HSE Team will ensure constant inspection all
Handles missing from files; tools; hand tools prior to used.
Using hand tools for manual activities such Burred or mushroomed heads Introducing a program of Ensure all defect/damaged tools will be
as; on chisels; routine maintenance and replacing those tools 2 2 4 removed from site 2 1 2
Using of hammer and chizel. Blunt blades on chisels, saws or that are immediately.
knives; found to be defective; Ensure proper storage and keeping of tools
Split handles on tools; bent Arranging for storage facilities for the tools to be after use are do practice always
spanners or spanners with available.
splayed jaws; Training the users in the safe use and inspection
Worn sockets and screwdrivers; of hand tools.
and corroded tools Do not use defective tools.
Home-made tools are not allowed

Ensuring that the worker is self-paced and


provide appropriate rest break for the heat
Ensure that required training & education stress condition.
provided and undertaken by supervisors, First Provide rest shelter and water on site prior of
aider and employees. activity at site.
Ensuring engineering controls measures HSE Dept. to monitor on daily basis for the
Heat stress. implemented to eliminate the risk of heat weather condition at site.
Working in adverse weather condition Heat exhaustion. exposure as far as reasonably practicable. 2 2 4 HSE Dept. to identify the Heat Index danger 2 1 2
Heat stroke. Take appropriate action upon developing category on daily basis.
symptoms of heat cramps, heat exhaustion or A standby qualified first aider/site Nurse and
heat stroke. first aid kit must be available at site.
Ensure designated rest shelter have sufficient Ensure supply of water daily, to provide
drinking water station. abundant supply of water at site.
Ensure site with proper monitoring and using
kestrel equipment heat stress program.

Job Safety Analysis


Rev.00, 30 March 2023 Page 7 of 18
Job Safety Analysis
RSG-HS-FRM-0001

RED_SEA_GLOBAL
Ensure all workers follow the use of clothing Ensure appropriate PPE’S to be use when
when temperature working to outside temperature working to outside.
Administrative controls like acclimatization,
Exposure to extreme Cold temperature, and humidity monitoring, flagging 3 2 6 Ensure site with proper monitoring and using 2 1 2
system etc. should be in place kestrel equipment heat stress program.

Work is strictly prohibited during lightning and Ensure all workers working at site with proper
project personnel are not allowed to stay shelter in place.
outdoor. Stop work immediately if Lighting
If safe building structures are not accessible, /thunderstorm and notify the transport
employers should guide workers to hard-topped foreman for the standby of BUS as shelter at
metal vehicles with rolled up windows. Remain site.
Lighting /thunderstorm 3 2 6 2 1 2
in the vehicle for at least 30 minutes after In any case of emergency, a standby vehicle at
hearing the last sound of thunder. site radio or cell phone to contact directly.
After hearing thunder, do not use corded All emergency contact list must provide to all
phones, except in an emergency. Cell phones driver/s.
and cordless phones may be used safely.

Ensure work is strictly prohibited during heavy Ensure all workers working at site with proper
rains and project personnel are not allowed to shelter in place during the rain.
work/stay outdoor. Always be vigilant of the flooding in the area,
If water accumulated or the area is flooding due look for the high location if flooded or call for
to rain, wait to subside before resuming the an emergency.
work. Ensure on any presence of water in excavated
If water is present in the excavation, de-watering area don’t allow any worker/s to resume the
Heavy Rain 3 2 6 2 1 2
shall be performed by installing submersible works.
pumps or equivalent should land survey work is Provide appropriate protection for the
urgent. excavation to prevent erosion of excavated
If raining, sandbag shall be positioned on the works.
surrounding of the excavation to prevent
rainwater flowing in the excavated area.

Work is strictly prohibited during sandstorm and Ensure all workers working at site with proper
project personnel are not allowed to stay shelter in place during sandstorm.
outdoor. Provide appropriate wearing of face mask
Wear medical facemasks or use wet towel or during sandstorm at site otherwise stop the
gauze during sandstorms outdoors. work and wait for further notice to proceed.
Wear eyeglasses preferably airtight goggles or Provide appropriate use of safety glasses,
face shield to protect your eyes from blowing contact lenses are not allowed during working
dust or sand. at site.
Avoid wearing contact lenses in areas prone to Ensure all workers to stay indoor (car or office
sandstorm. building) unless it is necessary to go out.
Avoid rubbing eyes to prevent eye infection. If Conduct maintenance of office and
Sandstorm eyes become irritated, rinse with water. 3 2 6 accommodations to sealed properly and 2 1 2
Stay indoor (car or office building) unless it is prevent sands enter inside the room/office,
necessary to go out. Drive with caution or stop on the shoulder of
Ensure office and accommodations if sandstorm the road until the sandstorm remain calm.
proof (properly sealed). Be vigilant of another vehicle near you during
When driving, drive slowly with caution when the zero visibility on roads at site.
visibility is very low. Ensure you parked in right place during this
Pull over completely to a safe place off the sandstorm to prevent any collision with other
paved portion of the roadway during low oncoming vehicles.
visibility.

Remove banding, crate material, nails, paint Ensure all unwanted materials to be disposed
bottle, etc. and dispose of properly. properly on designated location skip bins.
Proper planning and look ahead by Discipline Prioritize the housekeeping scheduled on or
Supervisor/Foreman. before the activity on daily basis on site.
Prior to commencing work, as part daily Construction Team shall be accountable for all
progress, he shall plan for: the materials and pre-arranged staging
Housekeeping resources - hauling equipment location area to prevent any materials
(loader / dump truck / forklift) and dedicated scattered on the surroundings.
Poor Housekeeping. crew.
Housekeeping Lack of proper planning Regular collection of rubbish, every end of shift 2 2 4 2 1 2
Lack of resources at minimum
Waste skips / covered metal trash bins /
disposable trash bags, etc.
Temporary staging area of scrap materials
Pre-arranged staging area for construction
materials, tools / equipment
Access for personnel and equipment
Barricades / signs required

Debris and other unnecessary materials shall be Ensure all waste materials to be disposed
discarded from site. properly on timely manner especially the
Empty drinking bottles and wet garbage from hazard materials.
excess food should be properly disposed at A designated garbage bins to be provided for
designated bins and hauled out daily. segregated waste are to be followed.
Accumulation attracts Portable Toilets should be maintained on Daily Assigned Housekeeper to ensure Toilets are
disease carrying Basis. maintained with checklist on daily signed by
2 2 4 2 1 2
insect and animals Trash and garbage shall only be disposed of at his supervisor.
Not sanitized Toilets approved sites as designated by RED SEA or local Ensure approved third-party garbage collector
Environmental damaged municipality. to be collected on site.
All unwanted materials at the site should be Any hazard materials on site especial care for
disposed of especial hazard materials. the environmental impact and disposed
properly.

Job Safety Analysis


Rev.00, 30 March 2023 Page 8 of 18
Job Safety Analysis
RSG-HS-FRM-0001

RED_SEA_GLOBAL
Proper planning and look ahead by Discipline Ensure proper planning and look ahead by
Supervisor. Prior to his activities he shall: construction team of any activity at site.
Familiarize himself and his team with the site- Ensure to comply with RSG-HS-ADM-0007
specific emergency procedure. (Emergency Preparedness and Response) of
Know the actual locations of nearest safe any emergency protocol.
assembly areas. Conduct toolbox talk with his Follow the STOP Work or Evacuation Alarm, as
crew on emergency procedure. an instruction from Site ERT / HSE, of any
See to it that safe access route is available from emergency protocol.
work area towards the nearest safe assembly Conduct emergency training drills in
area. Be familiar with the prevailing wind against coordination with RED SEA/SC for the
the locations of nearest safe assembly points. At awareness by all workers on site.
least 2 safe assembly points in opposite Ensure emergency contact list to be posted at
directions shall be known to the crew from each site and keep up to date the contact list.
work location. Provide training to all workers on how to
Be familiar with site specific Emergency contact the details in the emergency contact
Lack of proper
Response Plan (ERP) and requirements of this list.
planning / emergency
document. Understand / comply with RSG-HS- Ensure the provision of Emergency contact list
readiness /
Emergency Preparedness ADM-0007 (Emergency Preparedness and 2 2 4 available at site. 2 1 2
awareness of safe
Response). Upon hearing site STOP Work or
evacuation procedure.
Evacuation Alarm, or receipt of an instruction
Lack of resources
from Site ERT / HSE, Discipline Supervisor shall
lead his crew to ensure following actions are
taken: Stop work, Alarm others, Shutdown all
machines e.g., generator, welding machines,
etc.. Check wind direction
Proceed to nearest safe assembly area in cross
wind direction. Participate in the headcount,
report missing person (if any)
Stay at safe assembly area, remain attentive, do
not engage in any unauthorized activity, wait for
further instruction. All site personnel to
participate in training drills. Conduct emergency
training drills in coordination with RED SEA/SC.

Section IV – Approval and Signatures


Prepared by Company Position
Syed Saddam AMT Health & Safety Manager

Initial Review and Approval by Company Position


Eslam Elmawafy AMT QC Manager

Note: All High and Very High residual risk ratings (10-25) require review and approval by Construction Director/Manager/Facility or Operations Manager before starting work to ensure that the additional
controls are adequate to execute the task safely.

Final Review and Approval by Company Position Date

Magzoub Mustafa AMT Construction manager


st

Reviewed by Crew Company Position

Job Safety Analysis


Rev.00, 30 March 2023 Page 9 of 18

You might also like