PHOTOGRAPHIC REPORT

Project Name: Fairmont Krishna Icon Skyscrapers LLP Wakad.


Period: From 15/10/2023 to 31/10/2023.

Photographic report no: FAIRMONT / PR / 17

FAIRMONT WAKAD

Prepared By Verified By

Abhijeet Patil Yogesh Joshi


JUNIOR ENGINEER PROJECT MANAGER
11th slab part-1 steel reinforcement work in progress.

11th slab part-2 steel reinforcement work completed.


11th slab part-3 shuttering work in progress.

11th slab part-2 casting work in progress.


11th slab part-2 casting work completed.

11th slab part-1 steel reinforcement work in progress.


11th slab part-3 shuttering work in progress.

10th floor part-2 column casting work in progress.


10th floor part-2 column casting work in progress.

11th slab part-1 casting work in progress.


11th slab part-1 casting work in completed.

11th Slab part-3 steel reinforcement work in progress.


11th Slab part-3 steel reinforcement work in progress.

11th Slab part-3 casting work in progress.


11th Slab part-3 casting work completed.

10th floor part-1 column casting work in progress.


10th floor part-1 column casting work in progress.

10th floor part-1 column casting work in progress.


12th slab part-2 shuttering work in progress.

3rd floor gypsum work in progress.


3rd floor gypsum work in progress.

4th floor AAC Block work in progress.


4th floor AAC Block work in progress.

4th floor AAC Block work in progress.


5th floor AAC Block work in progress.

5th floor AAC Block work in progress.


3rd floor internal plaster work in progress.

1st floor internal plumbing work in progress.


1st floor toilet dado tile work in progress.

1st floor kitchen counter work in progress.