QUANTITY

SURVEYING
MODULE 3
Module 3
EXCAVATION
- the act or process of
digging, especially when
something specific is being
removed from the ground
- volume based
Example
Computed Undisturbed Soil Volume = 500m³
Cost Excavation = Volume x Cost
No. CHB = 500m³(₱ 20.00/m³)
No. CHB = ₱ 10,000.00
Cost with Transport of Haul = Volume x Cost
No. CHB = 500m³(₱ 300.00/m³)
No. CHB = ₱ 150,000.00