Professional Documents
Culture Documents
EV
Formulas
Project
Control
www.udemy.com/user/Mohamed-abd-elhakiem/
1. Schedule Performance Index 2.. Cost Performance Index
SPI CPI
EV / PV EV / AC
3. Schedule Variance 4. Cost Variance
SV CV
EV-PV EV-AC
5. Estimate to complete 6.. Estimate At Completion
ETC EAC
BAC-EV ETC+AC
7. Variance At Completion 8. To Complete Performance index
VAC TCPI
BAC-EAC (BAC-EV) / (BAC-AC)
www.udemy.com/user/Mohamed-abd-elhakiem/
EV
FORMULA GUIDE!
3. Schedule Variance
SV
=
EV - PV
SV: measure EV against PV
if SV >0 the progress ahead the plan
if SV =0 the progress equal the plan
if SV <0 the progress behind the plan
www.udemy.com/user/Mohamed-abd-elhakiem/
EV
FORMULA GUIDE!
4. Cost Variance
CV
=
EV - AC
CV: measure EV against AC
if CV >0 under budget
if CV =0 the same budget
if CV <0 Over Budget
www.udemy.com/user/Mohamed-abd-elhakiem/
EV
FORMULA GUIDE!
5. Estimate to complete
ETC
=
BAC-EV
ETC: measure the budget of the remained works
www.udemy.com/user/Mohamed-abd-elhakiem/
EV
FORMULA GUIDE!
6. Estimate At Completion
EAC
=
ETC+AC
ETC: measure the estimate budget at the end of the project.
www.udemy.com/user/Mohamed-abd-elhakiem/
EV
FORMULA GUIDE!
7. Variance At Completion
VAC
=
BAC-EAC
ETC: measure the difference between the project budget and the
estimate budget at the end of the project.
www.udemy.com/user/Mohamed-abd-elhakiem/
EV
FORMULA GUIDE!
TCPI
=
(BAC-EV) / (BAC-AC)
ETC: measure
the difference between the project budget and the progress achieved
Against
the difference between the project budget and the actual cost
if TCPI >1 Over Budget
if TCPI =1 the same budget
if TCPI <1 under budget
www.udemy.com/user/Mohamed-abd-elhakiem/
Question Answer
Time Are We Ahead or Schedule Variance SV = EV - PV >0
Wise behind schedule? Ahead
<0
Behind
How efficiently are we Schedule SPI = EV / PV >1
using time? Performance Index Ahead
<1
Behind
When are we likely to Time Estimate at EA = OD / SPI Delay
finish work? Completion C,t amount
www.udemy.com/user/Mohamed-abd-elhakiem/
www.udemy.com/user/Mohamed-abd-elhakiem/
www.udemy.com/user/Mohamed-abd-elhakiem/
Practice Example
www.udemy.com/user/Mohamed-abd-elhakiem/
Practice Example
The difference between the value of what you accomplished and the
value of what you actually paid is the Cost Variance.
www.udemy.com/user/Mohamed-abd-elhakiem/
Practice Example
Finally
Performance in terms of time is also poor,
www.udemy.com/user/Mohamed-abd-elhakiem/
Thank you
for your tim e and a ttention.
If you have any questions or would like to
learn more about planning best practices,
please feel free to reach out to us.
planning experts
www.udemy.com/user/Mohamed-abd-elhakiem/
Project Control Courses
(Claims, Risk, Reporting, Planning, scheduling)
EOT Procedures.
https://www.udemy.com/course/construction-claims-21-major-point
******************************************************************************************
Dynamic Dashboard &Reporting.
Interactive Dashboards & EVM.-Arabic
https://www.udemy.com/course/earnedvalue2019
******************************************************************************************
Planning and Scheduling Professional.
PSP Study Guide
https://www.udemy.com/course/planning
YouTube:
https://www.youtube.com/c/PlanningandSchedulingProfessional
Udemy:
https://www.udemy.com/user/mohamed-abd-elhakiem
Facebook:
https://www.facebook.com/Planning.courses
E-mail:
epaacademy@yahoo.com
Tel.:
+2 012 10 82 88 77