You are on page 1of 19

Earned Value

EV
Formulas

Project
Control

www.udemy.com/user/Mohamed-abd-elhakiem/
1. Schedule Performance Index 2.. Cost Performance Index

SPI CPI
EV / PV EV / AC
3. Schedule Variance 4. Cost Variance
SV CV
EV-PV EV-AC
5. Estimate to complete 6.. Estimate At Completion

ETC EAC

BAC-EV ETC+AC
7. Variance At Completion 8. To Complete Performance index

VAC TCPI
BAC-EAC (BAC-EV) / (BAC-AC)

www.udemy.com/user/Mohamed-abd-elhakiem/
EV
FORMULA GUIDE!

1. Schedule Performance Index


SPI
=
EV / PV
EV: Earned Value = performance% * total budget = progress achieved.
PV: Planned Value = Schedule % * total budget = progress as per plan.

SPI: measure EV against PV


if SPI >1 the progress ahead the plan
if SPI =1 the progress equal the plan
if SPI <1 the progress behind the plan
www.udemy.com/user/Mohamed-abd-elhakiem/
EV
FORMULA GUIDE!

2. Cost Performance Index


CPI
=
EV / AC
EV: Earned Value
AC: Actual Cost of the work done.

CPI: measure EV against AC


if CPI >1 under budget
if CPI =1 the same budget
if CPI <1 Over Budget
www.udemy.com/user/Mohamed-abd-elhakiem/
EV
FORMULA GUIDE!

3. Schedule Variance
SV
=
EV - PV
SV: measure EV against PV
if SV >0 the progress ahead the plan
if SV =0 the progress equal the plan
if SV <0 the progress behind the plan

www.udemy.com/user/Mohamed-abd-elhakiem/
EV
FORMULA GUIDE!

4. Cost Variance
CV
=
EV - AC
CV: measure EV against AC
if CV >0 under budget
if CV =0 the same budget
if CV <0 Over Budget
www.udemy.com/user/Mohamed-abd-elhakiem/
EV
FORMULA GUIDE!

5. Estimate to complete

ETC
=
BAC-EV
ETC: measure the budget of the remained works

www.udemy.com/user/Mohamed-abd-elhakiem/
EV
FORMULA GUIDE!

6. Estimate At Completion

EAC
=
ETC+AC
ETC: measure the estimate budget at the end of the project.

www.udemy.com/user/Mohamed-abd-elhakiem/
EV
FORMULA GUIDE!

7. Variance At Completion

VAC
=
BAC-EAC
ETC: measure the difference between the project budget and the
estimate budget at the end of the project.

www.udemy.com/user/Mohamed-abd-elhakiem/
EV
FORMULA GUIDE!

8. To Complete Performance index

TCPI
=
(BAC-EV) / (BAC-AC)
ETC: measure
the difference between the project budget and the progress achieved
Against
the difference between the project budget and the actual cost
if TCPI >1 Over Budget
if TCPI =1 the same budget
if TCPI <1 under budget
www.udemy.com/user/Mohamed-abd-elhakiem/
Question Answer
Time Are We Ahead or Schedule Variance SV = EV - PV >0
Wise behind schedule? Ahead
<0
Behind
How efficiently are we Schedule SPI = EV / PV >1
using time? Performance Index Ahead
<1
Behind
When are we likely to Time Estimate at EA = OD / SPI Delay
finish work? Completion C,t amount

Cost Are we under or over Cost Variance CV = EV - AC >0


Wise our budget? Under
<0
Over
How efficiently are we Cost Performance CPI = EV / AC >1
using our resources? Index Under
<1
Over
How efficiently must To-Complete TC = BAC / BAC _ Extra
we use our remaining Performance Index PI _EV AC effort
Resources?

What will the Estimate to ETC = BAC - EV Remain


remaining work cost? Complete ed cost
What is the project Estimate at EA = AC + ETC Total
likely to cost? Completion C cost
Will we be under or Variance at VA = BAC - EAC >0
over budget? Completion Under
C
<0
Over

www.udemy.com/user/Mohamed-abd-elhakiem/
www.udemy.com/user/Mohamed-abd-elhakiem/

www.udemy.com/user/Mohamed-abd-elhakiem/
Practice Example

If as a project manager, and according to the


schedule and budget approved by the management
and the client,

you were supposed to complete a fence and


garden worth $100,000,
according to the approved plan, an amount of 40
thousand was allocated for the completion of the
fence and 60 thousand was allocated for the
completion of the garden ,

in case of both the fence and 90% of the garden


have been completed,

1 Have you completed the required work?


2 Have you done any other work besides them?
3 How much did my work cost?
4 Did you exceed the amount of 100,000, or maybe you were able to
save part of it?

www.udemy.com/user/Mohamed-abd-elhakiem/
Practice Example

what is the Earned value here


earned value = 40000 + 0.9 multiplied by 60000 = $ 94000.

How much did you actually pay to do this work, which is


the Actual Cost,

so we will ask you for documents to check how much you


paid to complete this, and we found that you paid $ 95000
, hmmm it seems that you are doing poorly in terms of
costs.

How much did you planned to pay to do this work, which is


the planned Value,
The fence and the garden were supposed to be completed
in full, for which we allocated an amount of 100,000, which
is the value that we planned to spend.

Planned Value, then P V = $ 100000


www.udemy.com/user/Mohamed-abd-elhakiem/
Practice Example

Now we can pass our fair judgment on you:


1 Performance in terms of cost,
1st , the Cost Variance.

The difference between the value of what you accomplished and the
value of what you actually paid is the Cost Variance.

C V = earned value E V – planned value P V = 94000 – 95000 = - $1000.

you exceeded the budget by $1000.

2nd , the Cost Performance Index can be calculated as follows C P I =


earned value E V over actual cost A C = 94000 over 95000 =0.99 .

In other words, The performance in terms of costs is a little poor.

www.udemy.com/user/Mohamed-abd-elhakiem/
Practice Example

Now we can pass our fair judgment on you:


2 Performance in terms of Time ,

1st schedule variance,

schedule variance S V = earned value E V –planned P V = 94000 –


100000 = -6000.

Note that this indicator of time, although it is estimated in financial


value, as it expresses, as we said, the value of the delayed work, and
therefore the actual hour in the project was completed less than the
hour according to the original plan.

2nd ,The Schedule Performance Index can be calculated as follows S P I


= Earned value over the planned value = 94000 over 100000 = 0.94.

Finally
Performance in terms of time is also poor,

www.udemy.com/user/Mohamed-abd-elhakiem/
Thank you
for your tim e and a ttention.
If you have any questions or would like to
learn more about planning best practices,
please feel free to reach out to us.

planning experts

Let's build a community of knowledge-


sharing and collaboration.

Please comment on this post with your


thoughts, and share it freely with your
connections!

www.udemy.com/user/Mohamed-abd-elhakiem/
Project Control Courses
(Claims, Risk, Reporting, Planning, scheduling)

Construction Claims Bundle.


 Construction Claims-English
https://www.udemy.com/course/construction_claims

 EOT Procedures.
https://www.udemy.com/course/construction-claims-21-major-point

 Delay Analysis Techniques.


https://www.udemy.com/course/delay-analysis

 Construction Disruption Claims


https://www.udemy.com/course/construction-claims-disruption

 Scheduling tricks, tactics, defense, related to claims


https://www.udemy.com/course/scheduling-tricks
 Forensic Schedule Analysis
https://www.udemy.com/course/forensic

******************************************************************************************
Dynamic Dashboard &Reporting.
 Interactive Dashboards & EVM.-Arabic
https://www.udemy.com/course/earnedvalue2019

 Dynamic Portfolio Dashboards.-English


https://www.udemy.com/course/portfolio-dashboard

******************************************************************************************
Planning and Scheduling Professional.
 PSP Study Guide
https://www.udemy.com/course/planning

 PSP Practice test-English


https://www.udemy.com/course/psp-test

 Primavera risk analysis, Duration uncertainty.


https://www.udemy.com/course/risk2019

 PMI-SP Practice test-English


https://www.udemy.com/course/scheduleingprofessional
Kindly Ask
For
The Discounted Coupons

Eng. Mohamed Abd Elhakiem

YouTube:
https://www.youtube.com/c/PlanningandSchedulingProfessional

Udemy:
https://www.udemy.com/user/mohamed-abd-elhakiem

Facebook:
https://www.facebook.com/Planning.courses

E-mail:
epaacademy@yahoo.com

Tel.:
+2 012 10 82 88 77

You might also like