You are on page 1of 1

MATERIAL TAKE OFF Doc. No.

18JE05-MTO-ZEN-00-0001 Prepared : IRW


ELECTRICAL COMMISSIONING SERVICE
Rev. No. Rev. : 00 Checked : ADR

INDIVIDUAL TEST - ELECTRICAL POWER PLANT


Date August 21, 2023 Approved : RNH

NO. ITEM DESCRIPTION STANDARD CODE TOOLS MEASUREMENT UNIT VOLUME REMARKS

1 EQUIPMENT TESTING
1.1 CURRENT TRANSFORMER (CT) LOT 1
- Insulation Resistance Test
- DC Secondary Resistance
SPLN K6.001 2014 Pengujian
- Polarity Test Vendor to be prepared & supplied
PLTU
- Ratio Test
- Burden Test
1.2 VOLTAGE TRANSFORMER (VT) LOT 1
- Insulation Resistance Test
- DC Secondary Resistance
SPLN K6.001 2014 Pengujian
- Polarity Test Vendor to be prepared & supplied
PLTU
- Ratio Test
- Burden Test
1.3 CIRCUIT BREAKER (ACB) LOT 1
- Insulation Resistance
SPLN K6.001 2014 Pengujian
- Contact Resistance Vendor to be prepared & supplied
PLTU
- Function test
1.4 LV BUSBAR 400V LOT 1
- Insulation Resistance Test SPLN K6.001 2014 Pengujian
Vendor to be prepared & supplied
- Contact Resistance PLTU
1.5 POWER METER LOT 1
- Uji Function test (0%, 25%, 50%, 75%, 100%) SPLN K6.001 2014 Pengujian
Vendor to be prepared & supplied
PLTU
1.6 RELAY PROTECTION TEST LOT 1
- Uji Karakteristik Relay
SPLN K6.001 2014 Pengujian
- Uji Trip Relay Vendor to be prepared & supplied
PLTU
- Setting and Adjustment
1.7 UJI FUNCTION TEST SYSTEM LOT 1
- Continuity Cable Power
- Megger Cable Power SPLN K6.001 2014 Pengujian
Vendor to be prepared & supplied
- Function Test & Interlock Test PLTU