SCHEDULE PEKERJAAN TEST & COMMISIONING GI 150kV KUALA PEMBUANG

NO 150kV DESEMBER 2021


QTY UNIT REMAKS
PRIMARY EQUIPMENT 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31
CIRCUIT BREAKER
Insulation Resistance
Timing/Keserempakan
3 Sets Menunggu Pengisian Gas SF6
Minimum Voltage Coil
Contact Resistance
Local function
DISCONECTING SWITCH WITHOUT EARTHING
Contact Resistance
Timing Test 6 Sets Menunggu Perbaikan Motor DS
Insulation Resistance Test
Local function Open Close
DISCONECTING SWITCH WITH EARTHING
Contact Resistance
Timing Test 2 Sets Menunggu Perbaikan Motor DS
Insulation Resistance Test
Local function Open Close
CURRENT TRANSFORNMER
Insulation Resistance Test
Ratio and Polarity Test
9 Unit
Saturation Curve Test
Burden Test
Menunggu Relay Proteksi di ON
Primary Test
SURGE ARRESTER
Insulation Resistance Test 9 Unit
Surger Counter Test
CAPACITIVE VOLTAGE TRANSFORMER
Insulation Resistance Test
Ratio and Polarity Test 6 Unit
Resistance Meassurement
Burden Test Menunggu Relay Proteksi di ON

Team 1
Desember 2021
20kV EQUIPMENT QTY UNIT REMAKS
6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31
Vacum Circuit Breaker
Insulation Resistance
Minimum Voltage Coil 7 Sets Menunggu Supervisi Schneider
Contact Resistance
Timing Test
Current Transformer
Ratio and Polarity Test
Insulation Resistance Test
21 Unit Menunggu Supervisi Schneider
Saturation Curve Test
Burden Test
Primary Injection Test
Voltage Transformer
Insulation Resistance Test
8 Unit Menunggu Supervisi Schneider
Ratio, Polarity Test dan winding Resistance
Burden Test
kWH Meter Menunggu Supervisi Schneider dan
7 Unit
Individual Test Settingan Konfigurasi
Digital Meter Menunggu Supervisi Schneider dan
7 Unit
Individual Test Settingan Konfigurasi
Relay Protection Menunggu Supervisi Schneider dan
9 Unit
Individual Testing and Configure As per Setting PLN Settingan Konfigurasi Relay
BUSBAR 20kV
Contact Resistance
3 Busbar Menunggu Supervisi Schneider
HV Test Busbar
IR Busbar
AUXILIARY TRANSFORMER FEEDER CUBICLE
1 Unit Menunggu Supervisi Schneider
Local Operation LBS & ES
POWER CABLE MV
Insulation Resistance 10 Titik
HV Test
AUXILIARY TRANSFORMER
Insulation Resistance
Ratio Per Tab
1 Unit
Winding Resistance
Vector Group
SISTEM TEST
Function Test Local and Interlock 9 Cbcl
Menunggu Supervisi Schneider
Function Indication and alarm 9 Cbcl
Function Trip Relay As per setting PLN 9 Cbcl

Team 1
Team 2