Professional Documents
Culture Documents
Rate Analysis SI-PR - DNIT Final
Rate Analysis SI-PR - DNIT Final
JE AE AE EE
Junior Engineer Assistant Engineer Executive Engineer
Sub Division Jwalamukhi Dehra Division
HP PWD Jwalamukhi HP PWD Dehra
KM 0/000 TO 24/800
-345
SE
Superintending Engineer
9th Circle HPPWD Nurpur
Distt Kangra
Lead Chart
3 Crushed stone aggregate all size & G-II, G-III 90.0 Gagret
WM crash Barrier 10
13 Local
10
14 Paver Block Local
BASIC RATES
Labour (All Zones)
PM-002 Batch mix HMP 40-60 TPH BM, DBM, SDBC, PM t/h 50.00 per hour 15,000.00
PM-003 Batch type HMP 30/40 TPH BM, DBM, SDBC, PM t/h 35.00 per hour 14,488.00
Concrete mixer 0.28/0.4 cum Mixing of ingradients cum/h 2.50 per hour 350.00
PM-006
PCC Panel Cutting Machine for Cutting in CC Panel rm/hr per hour 1,191.00
PM-012 Hydraulic broom with tractor Surface cleaning sqm/h 1250.00 per hour 528.00
Rate at Plant
SN Description Unit
(Rs.)
1 Aggregate 10 mm cum 950.00
2 Aggregate 20 mm cum 950.00
3 Aggregate 25 mm cum 900.00
4 Aggregate 40 mm cum 900.00
5 Aggregate- Crushable type such as moorum or Gravel for Grading I cum 900.00
6 Aggregate- Crushable type such as moorum or Gravel for Grading II cum 900.00
7 Aggregate- Crushable type such as moorum or Gravel for Grading III cum 900.00
8 45-22.5
9 Aggregate-Grading I 90 mm to 45 mm cum 900.00
10 Aggregate-Grading II 63 mm to 45 mm cum 900.00
11 Aggregate-Grading III 53 mm to 22.4 mm cum 900.00
12 Aluminium sheeting (1.5 mm thick) sqm 0.00
13 Binding Material cum 440.00
14 Angle 50mmx50x6mm kg 0.00
15 Binding wire kg 65.00
16 Bitumen (VG-10) Bulk on 1st Jan 2023 t 42642.00
17 Bitumen (S-90/VG30) t 44942.00
18 Bitumen Emulsion (RS-1) t 50508.00
19 Bitumen Emulsion (SS-1) t 51823.00
20 Emulsion based explosive ( Power Gel 901) kg 66.00
21 Spl. Detonator ( No 8) Each 3.15
22 Safety fuse coil ( 7.32 mtrs.) coil 23.50
23 Cordex (DF) Per 1000 mtr 6600.00
24 Bond stone (400 mm x 150 mm x 150 mm) No. 15.00
or cum 980.00
25 Brick 1st Class No. -
26 Cement tone 6640.00
27 Compensation for earth taken from private land cum 63.00
28 Crushed Stone chipping 13.2 mm nominal size cum 950.00
Crushed Stone Chipping 6.7 mm size 100% passing 11.2 mm and retained on
29 cum 900.00
2.36 mm
30 Elastomeric bearing assembly Nos. 91928.00
31 Epoxy Paint litre 265.00
Rate at Plant
SN Description Unit
(Rs.)
32 Epoxy Primer litre 206.00
33 Filter media cum 500.00
34 Fine aggregate/Crushed sand 2.36 mm to 75 micron cum 950.00
35 Galvanised angle kg 103.00
36 GI Pipe 100 mm dia m 650.00
37 GI Pipe 50 mm dia m 450.00
38 GI wires KG 60000.00
or kg 60.00
39 MS clamps 100 mm dia Nos. 176.00
40 MS Flat / Structural Steel kg 49.00
or t 49000.00
41 MS Sheet Tube (47 mm x 47 mm x 12 SWG Sheet) kg 91.00
42 MS Sheet 1.5 mm thick sqm 1554.00
43 MS Sheet 2 mm thick sqm 1890.00
44 Nuts, Bolts and Rivets t 85900.00
45 Paint (Synthetic Enamel) litre 312.00
46 RCC Pipe NP3 (900 mm dia) m 2000.00
47 RCC Pipe NP3 (1000 mm dia) m 4520.00
48 Red-oxide Primer litre 200.00
49 Road marking paint litre 422.00
50 Sand (Coarse) cum 800.00
51 Sand (Fine) cum 800.00
52 Steel Pipe 50 mm dia m 300.00
53 Steel Reinforcement (HYSD Bars) t 49000.00
54 Stone Boulder of size 150 mm and below cum 700.00
55 Stone spall/ Loose stone filling Cum 500.00
56 Stone Chips 13.2 mm to 5.6 mm PMC cum 900.00
57 Stone for Coarse Rubble Masonry 1st Sort cum 900.00
58 Stone for Coarse Rubble Masonry 2nd Sort cum 900.00
59 Stone for Random Rubble Masonry cum 900.00
60 Stone Screening - Type A 13.2 mm for Grading-1 cum 950.00
61 Stone Screening - Type B 11.2 mm for Grading-2 &3 cum 950.00
62 Water kl 50.00
63 Well graded Granular Base Material - Grading A 2.36 mm below cum 900.00
64 Well graded Granular Base Material - Grading A 26.5 mm to 4.75 mm cum 900.00
65 Well graded Granular Base Material - Grading A 53 mm to 26.5 mm cum 900.00
66 Well graded Granular Base Material - Grading B 26.5 mm to 4.75 mm cum 900.00
Rate at Plant
SN Description Unit
(Rs.)
67 Well Graded Material for Sub-Base - Grading I 2.36 mm below cum 900.00
68 PVC pipe per rmt 250.00
69 Corrosion resistant structural steel grating Kg 151.00
70 Well graded granular sub base material of Grading I as per Clause 400.1 cum 600.00
71 Interlocking paver blocks 80 mm thick (M-40 ) Sqm 500.00
72 Aggregate 22.4mm to 2.36mm for WMM Cum 900.00
73 Aggregate 45 mm to 22.4 mm for WMM Cum 900.00
74 Crushed Stone chipping 13.2 mm nominal size for Grading I & Grading II cum 950.00
75 CRMB - 60 t 46362.00
Granular material (Natural occuring, soil gravel mixture / quarry waste,
76 t 300.00
Kankar, laterite, dhandla.)
78 Channel post 150 x 75 x 5 mm,1.8 m long,3 Nos @ 16.4 kg per metre kg 61.00
79 Spacer 150 x 75 x 5 mm channel 0.33 m long,3 Nos @ 16.4 kg per metre kg 61.00
Note: Certified that the market rate of materials has been taken bare rates (without GST)
10 Agg. 45mm to 22.4mm for Wet mix macadum 3.95 1.87 cum 7.39 90.0 664.79 47.15 8.30 900.00 1,620.24
38 Fine aggregate / crushed sand 2.36 mm to 75 micron. 3.95 1.87 cum 7.39 90.0 664.79 47.15 8.30 950 1,670.24
39 Interlocking concrete block 3.95 1.87 sqm 7.39 75.0 553.99 47.15 8.30 500 1,109.44
40 CRMB 3.95 1.00 Tonne 3.95 350.0 1382.50 146.25 128.30 46,362.00 48,019.05
Granular material (Natural occuring, soil gravel
41 3.95 1.87 cum 7.39 10.0 73.87 47.15 8.30 300.00 429.32
mixture / quarry waste, Kankar, laterite, dhandla.)
Note: Certified that the market rate of materials has been taken bare rates (without GST)
A) Loading of Lime Aggregate, Stone Boulder, Brick Agg., Kankar, Building Rubbish, Crushed Sfag, Stone for
masonary by mechanical means including a lead up to 30m.
1.1
Placing tipper at loading point, loading with front end loader excluding time for hulage and return trip
ii. Loading by front end loader 1 cum Capacity @45 cum per houre min 7.33
Ref. to MORD
SN Description of Items. Unit Qty. Rate Amount
spec.
A) Unloading of Lime Aggregate, Stone Boulder, Brick Agg., Kankar, Building Rubbish, Crushed Sfag, Stone for
masonary by mechanical means including a lead up to 30m.
1.2
B) Unloading of earth, Sand, moorum, Manure, Fly Ash by Mechnically means including a lead upto 30m.
ii. Loading by front end loader 1Cum capacity @ 100Cum per hour min 3.3
Ref. to MORD
SN Description of Items. Unit Qty. Rate Amount
spec.
1.4 Loading and Unloading of Cement by manual means including, a lead of upto 30mtr.
Unit = T, Taking out = 10 T
(a) Labour
Mate Day 0.06 437.50 26.25
Mazdoor (Unskilled) Day 1.50 437.50 656.25
(a) Machinery
Truck 10t capacity Hours 1.000 589.00 589.00
Total Cost of 10 T (a+b) 1271.50
Cost of 1 cum 127.15
Say 127.15
Ref. to MORD
SN Description of Items. Unit Qty. Rate Amount
spec.
1.5 Loading and Unloading of Structural Steel, Steel Bar by manual means including, a lead of upto 30mtr.
1 Unit = T, Taking out = 10 T
(a) Labour
Mate Day 0.07 437.50 30.63
Mazdoor (Unskilled) Day 1.80 437.50 787.50
(b) Material
Truck 10t capacity Hours 1.000 589.00 589.00
Total Cost of 10 T (a+b) 1407.13
Cost of 1 cum 140.713
Say 140.70
Ref. to MORD
SN Description of Items. Unit Qty. Rate Amount
spec.
1.7 Unloading of Bitumen Drum by manual means including, a lead of upto 30mtr.
1 Unit = T, Taking out = 10 T
(a) Labour
Mate Day 0.05 437.50 21.88
Mazdoor (Unskilled) Day 1.20 437.50 525.00
(b) Material
Truck 10t capacity Hours 1.250 589.00 736.25
Total Cost of 10 T (a+b) 1283.13
Cost of 1 cum 128.313
Say 128.30
Ref. to MORD
SN Description of Items. Unit Qty. Rate Amount
spec.
1.8 Loading of RCC Hume Pipe 900/ 1000/ 1200 mm dia by mechanically means including a lead of 30 mtr.
Ref. to MORD
SN Description of Items. Unit Qty. Rate Amount
spec.
1.9 Unloading of RCC Hume Pipe 900/ 1000/ 1200 mm dia by mechanically means including a lead of 30 mtr.
Ref. to MORD
SN Description of Items. Unit Qty. Rate Amount
spec.
Loading and Unloading of CC Blocks, Km Stones, 200m Stones, Boundary Pillars, Kerb-Channel, bond stone etc.,
1.10
by manual means including a lead of 30m
1 Unit = cum, Taking out = 5.5 cum
(a) Labour
Mate Day 0.08 437.50 35.00
Mazdoor (Unskilled) Day 2.00 437.50 875.00
(b) Material
Truck 10t capacity Hours 1.500 589.00 883.50
Total Cost of 5.5 cum 1793.50
Cost of 1 cum 326.091
Rate per sqm 26.08728
Say 26.10
Ref. to MORD
SN Description of Items. Unit Qty. Rate Amount
spec.
Haulage excluding loading and unloading
1.12 1
Haulage of RCC Hume Pipe 900/ 1000/ 1200 mm dia
Unit = per pipe, Taking out = 8 Tonne load and lead
10 KM = 9 pipes
Case 1 : Surface Road
Speed with Load 25 Km per hour
Speed by Returning empty 35 km per hour
(a) Machinery
Tipper 5.5 cum / 10 Tonne Capacity Hulage with Load Hours 0.40 570.00 228.00
Empty Return Trip Hours 0.29 570.00 165.30
Cost for 9 Pipes 393.30
Cost per Pipe 43.7
Rate per meter 17.48
Say 17.50
Excavation in hilly area in Ordinary Rock by mechanical means not requiring blasting
Excavation in hilly area in Ordinary Rock not requiring blasting by mechanical means including cutting &
2.2 1600 & 300
trimming of side slopes and disposal of excavated earth with a lift up to 1.5 mtr & up to a lead of 20m as per
clause 1603.1
Earth work in excavation for structure as per drawing and technical specification clause 305.1 including setting
2.5 300 out, construction of shoring and bracing removal of stumps and alter deterious material and disposal upto a
lead of 50mtres dressing of sides and bottom of back filling in trenches with excavated suitable materials
1 Ordinary soil Upto 3 mtr depth, Unit = Cum, Taking out = 10cum
(a) Labour
Mate Day 0.32 437.50 140.00
Mazdoor (Unskilled) Day 8 437.50 3500.00
(b) Total of Labour (a) 3640.00
Add 12.5% (Over head @ 2.5% + Contractor Profit @ 10%) on ( b ) 455.00
Total Cost of 10 cum 4095.00
Cost of 1 cum 409.5
Add 1% Labour cess 4.10
Total for 1 cum with all inclusion 413.60
Say 413.60
Ref. to MORD
SN Description of Items. Unit Qty. Rate Amount
spec.
Compacting original ground supporting subgrade
Loosening of the ground upto a level of 300 mm below the subgrade level, watered, graded and compacted in
2.6
layers to meet requirement of Tables 300.1 and 300.2 for subgrade construction as per Technical
Specification Clause 303.5.2.
Unit = Cum, Taking output = 600 cum
(a) Labour
Mate Day 0.24 437.50 105.00
Mazdoor (Unskilled) Day 6 437.50 2625.00
(b) Machinery
Tractor with ripper attachment hour 10.00 687.00 6870.00
Motor grader for grading hour 6 3,513.00 21078.00
Water tanker 6 kl capacity hour 4 500.00 2000.00
Three wheel 80-100 kN Static Roller @ 70 cum per hour hour 8.6 1,100.00 9460.00
(c) Total of Labour and Machinery (a+b) 42138.00
Add 12.5% (Over head @ 2.5% + Contractor Profit @ 10%) on ( c ) 5267.25
Total Cost of 600 cum 47405.25
Cost of 1 cum 79.009
Add 1% Labour cess 0.79
Total for 1 cum with all inclusion 79.80
Say 79.80
Ref. to MORD
SN Description of Items. Unit Qty. Rate Amount
spec.
Back filling behind abutment, wing wall and return wall and return wall complete as per drawing and technical
2.8
specification clause 1204.3.8
1 Unit = Cum, Taking out = 10cum
(a) Labour
Mate Day 0.28 437.50 122.50
Mazdoor (Unskilled) Day 10.00 437.50 4375.00
Bhisti Day 0.40 437.50 175.00
(b) Material
Geanular Material cum 12.00 429.32 5151.78
(c) Total of Labour and Machinery (a+b) 9824.28
Add 12.5% (Over head @ 2.5% + Contractor Profit @ 10%) on ( c ) 1228.04
Total Cost of 10 cum 11052.32
Cost of 1 cum 1105.232
Add 1% Labour cess 11.05
Total for 1 cum with all inclusion 1116.28
Say 1116.30
i) Ordinary soil
Mechnical Means
Unit = Per Cubic Metre
Taking output = 260Cubic Metre
a) LABOUR:
Mate Day 0.80 437.50 350.00
Mazdoor (unskilled) Day 20.00 437.50 8750.00
Total 9100.00
b) MACHINERY:
Dozer D-50 @ 100 Cum per Hour Hour 6.00 1740.00 10440.00
Front end loader Hour 6.00 1321.00 7926.00
Total Rs. 18366.00
Net Total (a+b) 27466.00
Add 12.5% (Over head @ 2.5% + Contractor Profit @ 10%) on ( c ) 3433.25
Total Cost of 10 cum 30899.25
Cost of 1 cum 118.843
Add 1% Labour cess 1.19
Total for 1 cum with all inclusion 120.03
Say 120.00
Ref to
Sr.
MoRD Description Unit Qty Rate Amount
No.
Speci.
8.3 1600 & Excavation in Hilly Area in ordinary rock not requiring blasting by mechanical
(iv) 300 means including cutting and trimming of slopes and disposal of cut material with
a lift upto 1.5 metre and a lead upto 20 metre as per Technical Specification
Clause 1603.2
Ref. to MORD
SN Description of Items. Unit Qty. Rate Amount
spec.
P/L C.C. 1:5:10 (one cement : five sand : ten graded stone agg. 40mm nominal size) , mechanically mixed
placed in foundation compacted by vibration and curing complete ensuring non segregation confirming of
3.1
HP:PWD specification including the cost of form work and hauling of material hand mixing in all leads and lifts
by all modes of transportation and as per the entire satisfaction and direction of Engineer-in-Chagre.
Normal Mix 1:5:10 (Mech. Mix), Unit = cum, Output-1 cum
(a) Labour
Mate Day 0.08 437.50 35.00
Masson 1st class Day 0.1 603.17 60.32
Mazdoor (Unskilled) Day 1.63 437.50 713.13
Bhisti Day 0.27 437.50 118.13
(b) Material
Cement Tonne 0.13 7064.94 918.44
Course sand Cum 0.47 1401.20 658.56
20mm aggregate Cum 0.24 1670.24 400.86
40mm aggregate Cum 0.65 1620.24 1053.15
(c) Machinery
Machinery concrete mixed 0.4/0.28 cum capacity fitted with
Hours 0.4 350.00 140.00
water measuring device and preferably also with load cell.
(d) Total of Labour, Material and Machinery (a+b+c) 4097.58
(e) Add for Form Work @4% on cost of (a+b) 158.30
(f) Total of (d+e) 4255.89
Add 12.5% (Over head @ 2.5% + Contractor Profit @ 10%) on ( c ) 531.99
Total Cost of 1 cum 4787.88
Add 1% Labour cess 47.88
Total for 1 cum with all inclusion 4835.76
Say 4835.75
P/L C.C. 1:4:8 (one cement : four sand : eight graded stone agg. 40mm nominal size) , mechanically mixed
placed in foundation compacted by vibration and curing complete ensuring non segregation confirming of
3.2
HP:PWD specification including the cost of form work and hauling of material hand mixing in all leads and lifts
by all modes of transportation and as per the entire satisfaction and direction of Engineer-in-Chagre.
Normal Mix 1:4:8 (Mech. Mix), Unit = cum, Output-1 cum
(a) Labour
Mate Day 0.08 437.50 35.00
Masson 1st class Day 0.1 603.17 60.32
Mazdoor (Unskilled) Day 1.63 437.50 713.13
Bhisti Day 0.27 437.50 118.13
(b) Material
Cement Tonne 0.17 7064.94 1201.04
Course sand Cum 0.47 1401.20 658.56
20mm aggregate Cum 0.65 1670.24 1085.65
40mm aggregate Cum 0.24 1620.24 388.86
(c) Machinery
Machinery concrete mixed 0.4/0.28 cum capacity fitted with
Hours 0.4 350.00 140.00
water measuring device and preferably also with load cell.
(d) Total of Labour, Material and Machinery (a+b+c) 4400.68
(e) Add for Form Work @4% on cost of (a+b) 170.43
(f) Total of (d+e) 4571.11
Add 12.5% (Over head @ 2.5% + Contractor Profit @ 10%) on ( c ) 571.39
Total Cost of 1 cum 5142.50
Add 1% Labour cess 51.42
Total for 1 cum with all inclusion 5193.92
Say 5193.90
Unit= Tonne, Taking output = 75 cum (172.50 t), (100 x 3.75 x 0.200)
(a) Labour
Mate Day 7.00 437.50 3062.50
Mason (1st class) Day 5.00 603.17 3015.85
Mason (2nd class) Day 5.00 494.67 2473.35
Mazdoor (Unskilled) Day 129.00 437.50 56437.50
Mazdoor (Skilled) Day 6.00 437.50 2625.00
Surveyor Day 2.00 603.17 1206.34
Mazdoor (Semi-Skilled) Day 6.00 437.50 2625.00
Bhisti Day 14.00 437.50 6125.00
Blacksmith for cutting of dowel bars including removal of
Day 1.00 437.50 437.50
burrs, fabrications & fixing of dowel bars.
(b) Material
Crushed stone coarse aggregates, grading will be as per
Clause 1501.2.4.1 (Table 1500.1) of specifications @ 0.90 cum 67.50 1620.24 109365.86
cum/cum of concrete
Sand as per IS:383 and conforming to Clause 1500.2.4.2 @
cum 33.75 1401.20 47290.50
0.45 cum/cum of concrete
Cement @ 310 kg/cum of concrete t 26.25 7064.94 185454.68
Polythene sheet 125 micron sqm 412.50 25.00 10312.50
Mild steel dowel bar 25 mm dia of grade S 240. 500 mm long
20 Nos. at culvert/bridge slab and at construction joint
including 5 per cent wastage.
(4 x 20 x 0.500) + 5 per cent wastage = 42 m @ 2.80 kg per
kg 117.60 49.32 5800.14
m = 117.6 kg.
Bitumen primer @ 200 ml per joint for 23 joints t 0.01 51454.05 257.27
Bituminous sealant 800 ml per joint for 23 joints litre 19.00 190.00 3610.00
Jute rope 12 mm dia including 5 per cent wastage m 90.00 10.00 900.00
Debonding strips 3.75 m (length) x 10 mm (width) x 5 mm
(thick) cut-out of rubber filler board or similar material m 90.00 12.00 1080.00
including 5 per cent wastage
Polythene sheathing, covering 2/3rd dowel bars (20x23) and
No. 483.00 60.00 28980.00
tight fit including 5 per cent wastage
Plasticizer 0.5 per cent by weight of cement litre 122.00 135.00 16470.00
Curing compound (if used) @ 0.33 litre per sqm litre 131.25 60.00 7875.00
Water for curing kl 18.00 69.75 1255.50
Joint filler board 20 mm thick as per IS:1838
sqm 3.00 490.00 1470.00
(4 x 3.75 x 0.200 = 3 sqm)
(c) Machinery
Concrete mixer 0.28 / 0.4 cum capacity (6 mixers) with weigh
hour 36.00 350.00 12600.00
batcher and suitable capacity calibrated water tank
Needle vibrator hour 9.00 100.00 900.00
Screed vibrator hour 9.00 100.00 900.00
Plate vibrator hour 9.00 100.00 900.00
Concrete joint cutting machine for initial & final cuts hour 4.00 1296.00 5184.00
Water tanker 6 kl capacity hour 5.00 500.00 2500.00
Air Compressor (1 hour initial + 1 hour final) hour 2.00 488.00 976.00
(d) Formwork @ 3% of (a+b+c) 15662.68
(d) Total of Labour, Material and Machinery (a+b+c) 537752.17
Add 12.5% (Over head @ 2.5% + Contractor Profit @ 10%) on ( c ) 67219.02
Total Cost of 75 cum 604971.19
Cost of 1 cum 8066.28
Add 1% Labour cess 80.66
Total for 1 cum with all inclusion 8146.94
Say 8146.95
Ref. to MORD
SN Description of Items. Unit Qty. Rate Amount
spec.
Weep Hole
Providing weepholes in brick masonary/ stone masonary/ plain reinforced concrete abutment, wing wall,
4.1 600 retaining wall/ breast wall with 100mm dia. PVC pipe extending through the full width of the structure withh
slope of 1(v) : 20 (h) towards drawing face complete as per drawing and technical specification clauses 614,
709, 1204.3.7.
Unit = Nos., Taking out = 30 Nos.
(a) Labour
Mate Day 0.08 437.50 35.00
Masson 1st class Day 0.1 603.17 60.32
Mazdoor (Unskilled) Day 1.63 437.50 713.13
(b) Material
PVC pipe 100mm dia including wastage @ 5% Avg length of
weep holes is taken as one metre for the purpose of RM 31.50 250.00 7875.00
estimating in cement mortor 1:3
Cement Mortar 1:3 Cum 0.05 5520.63 276.03
(c) Machinery
Machinery concrete mixed 0.4/0.28 cum capacity fitted with
Hours 0.4 350.00 140.00
water measuring device and preferably also with load cell.
(d) Total of Labour, Material and Machinery (a+b+c) 9099.47
Add 12.5% (Over head @ 2.5% + Contractor Profit @ 10%) on ( c ) 1137.43
Total Cost of 30 nos 10236.90
Cost of 1 no 341.23
Add 1% Labour cess 3.41
Total for 1 cum with all inclusion 344.64
Say 344.65
Sub Analysis (Cement Mortar 1:3)
4.1.1 Cement Mortar 1:3
Unit = Nos., Taking out = 3 Nos.
(a) Labour
Mate Day 0.04 437.50 17.50
Mazdoor (Unskilled) Day 0.9 437.50 393.75
Bhisti Day 0.08 437.50 35.00
(b) Material
Cement Cum 0.51 7064.94 3603.12
Sand Cum 1.05 1401.20 1471.26
(c) Total of Labour, Material and Machinery (a+b) 5520.63
Say 5520.60
Providing and laying of boulder apron laid in wire crates with 4mm dia GI wire conforming to IS:280 and IS:4826
4.2 600 in 100 mm x 100 mm mesh (woven diagonally) including 10 percent extra for laps and joints laid with stone
boulders weighing not less than 25 kg each as per drawing and technical specification Clause 1301
4.3 1200 Drainage spouts complete as per drawing and technical specifications Clause 1209
Unit = Nos., Output-1 No.
(a) (i) Labour for fabrication
Mate Day 0.02 437.50 8.75
Blacksmith, Welder etc. (Skilled) Day 0.02 603.17 12.06
Mazdoor (Unskilled) Day 0.20 437.50 87.50
(ii) Labour for fixing in position
Mate Day 0.01 408.33 4.08
Mason (1st Class) Day 0.01 408.33 4.08
Mazdoor (Unskilled) Day 0.20 408.33 81.67
Add @ 5 per cent of cost of material and labour (a+b) for
electrodes, gas cutting, sealant, anti-corrrosive bituminous 83.83
paint, mild steel grating etc.
(b) Material
Corrosion resistant structural steel grating including 5 per cent
kg 4.00 49.32 197.28
wastage
G I pipe 100 mm dia m 1.00 1286.90 1286.90
(d) Total of Labour, Material and Machinery (a+b+c) 1766.16
Add 12.5% (Over head @ 2.5% + Contractor Profit @ 10%) on ( c ) 220.77
Total Cost of 1 no of Drainage Spout 1986.93
Cost of 1 cum 1986.93
Add 1% Labour cess 19.87
Total for 1 cum with all inclusion 2006.80
Say 2006.80
Ref. to MORD
SN Description of Items. Unit Qty. Rate Amount
spec.
Scarifying Existing Bituminous Surface to a Depth of 150 mm by Mechanical Means
4.5 Scarifying the existing bituminous road surface to a depth of 150 mm and disposal of scarified material with a lift
upto 3 m and lead upto 1000 m as per Technical Specification Clause 301.4.
Unit = sqm, Taking output = 100 sqm
(a) Labour
Mate Day 0.01 437.50 4.38
Mazdoor (Unskilled) Day 0.25 437.50 109.38
(b) Machinery
Tractor with ripper attachment @ 60 cum per hour Hours 0.25 687.00 171.75
Front end loader 1 cum bucket capacity @ 50 cum per hour Hours 0.3 1,281.00 384.30
Tipper 5.5 cum capacity, 4 trips per hour Hours 0.68 570.00 387.60
(c) Total of Labour and Machinery (a+b) 1053.03
Add 12.5% (Over head @ 2.5% + Contractor Profit @ 10%) on ( C ) 131.63
Total Cost of 100 sqm 1184.66
Cost of 1 sqm 11.847
Add 1% Labour cess 0.12
Total for 1 cum with all inclusion 11.97
Say 11.95
Dismantling of Structures
Dismantling of existing structures like culverts, bridges, retaining walls and other structure comprising of
4.6 masonry, cement concrete, wood work, steel work, including T&P and scaffolding wherever necessary, sorting
the dismantled material, disposal of unserviceable material and stacking the serviceable material with all lifts
and lead of 1000 m as per Technical Specification Clause 202.
Unit = cum, Taking output = 1.25 cum
(a) Labour
Mate Day 0.15 437.50 65.63
Blacksmith Day 0.25 603.17 150.79
Mazdoor (Unskilled) Day 3.5 437.50 1531.25
(b) Machinery
Tractor with Trolly Hours 0.27 581.00 156.87
(c) Total of Labour and Machinery (a+b) 1904.54
Add 12.5% (Over head @ 2.5% + Contractor Profit @ 10%) on ( C ) 238.07
Total Cost of 1.25 cum 2142.61
Total Cost of 1 cum 1714.086
Add 1% Labour cess 17.14
Total for 1 cum with all inclusion 1731.23
Say 1731.25
Ref. to MORD
SN Description of Items. Unit Qty. Rate Amount
spec.
Ref. to MORD
SN Description of Items. Unit Qty. Rate Amount
spec.
Dismantling of flexible pavements and disposal of dismantled materials up to a lead of 1000 metres, stacking
5.2
serviceable and unserviceable materials separately
(i) Gravel/Soil aggregate base/sub base Nominal Maximum size Grading 80mm (table 2.3 of IRC SP 77-2008),
Using Existing Scarified WBM material
Construction of Gravel /Soil aggregate base/sub base Nominal Maximum size Grading 80mm as per table 2.3
of IRC SP 77-2008 spreading in uniform layers with Tractor mount appropriate grading arrangements on
5.4
prepared surface, mixing by mix place method at OMC with Tractor mount appropriate rotavator attachment
and compaction with three wheel 80- 100kN static Roller capacity to achieve the desired density, complete as
per Specification contained in Para 2.2, 3.6 and 3.7 of IRC SP 77-2008 (Using Existing Scarified WBM
material)
(i) Gravel / Soil Aggregate base/ sub base Nominal Maximum size grading 80mm (table 2.3 of IRC SP 77-2008)
Construction of Gravel / Soil Aggregate base/ sub base Nominal Maximum size grading 80mm (table 2.3 of IRC
SP 77-2008) spreding in uniform layers with Tractor mount appropriate grading arrangements on prepared
5.5
surface, mixing by mix place method at OMC with Tractor mount appropriate rotavator attachment and
compaction with three wheel 80- 100kN static Roller capacity to achieve the desired density, complete as per
Specification contained in Para 2.2, 3.6 and 3.7 of IRC SP 77-2008 (Using Fresh material)
Bituminous Concrete
Providing and laying 25mm thick bituminous concrete with 100-120 TPH batch type hot mix plant producing
onn average output 75 tones per hour using crushed aggregates of specified grading-II premixed with
bituminous with binder VG-10 @ 5.4 to 5.6 percent of mix and filer i.e. 129.50 kg. per cum as per job mix
5.8
formula transporting the hot mix to site of work,laying with hydrostatic paver finisher with sensor control to the
required grade. level and alingment, rolling with smooth wheeled, vibratory and teandem rollers to achieve the
desired commpaction as per MORTH specification clause No. 509 complete in al respect including repair of pot
holes (for which nothing shall be paid extra) as per direction of Engineer-in-Charge.
Unit = Cum, Taking output = 191 cum (450 tonnes)
(a) Labour
Mate Day 0.84 437.50 367.50
Mazdoor (Skilled) Day 5 437.50 2187.50
Mazdoor (Unskilled) Day 16 437.50 7000.00
(b) Material
I) Bitumen VG-30 @ 5.5percent of weight of mix tonne 24.75 46,599.1 1153326.49
Aggregate, Total Weight of Mix = 450 tonnes, Weight of Bitumen = 24.30 tonnes,
Weigth of aggregate = 450-24.30 = 425.24 tonnes, taking density of aggregate = 1.5 ton/cum
Volume of Aggregate = 283.5 cum
13.2-10mm(30%) cum 85.050 1,620.24 137800.99
10-5mm 25 per cent cum 70.875 1,670.24 118377.91
5mm and below 43 per cent cum 121.905 1,670.24 203610.00
Filler @ 2 per cent of weight of aggregates tonne 8.505 7,064.94 60087.31
(c) Machinery
Batch mix HMP @ 75 tonner per hour, Hr 6 15,000.0 90000
Paver finisher hydrostatic with sensor control @ 75 cum per
Hr 6 4,300.0 25800
hour
Generator 250 KVA Hr 6 1,160.0 6960
Front end loader 1 cum bucket capacity Hr 6 1,281.0 7686
Tipper 10 tonne capacity tonne.km 450 x L 3.54x19 30267
Add 10% of cost of carriage to cover cost of loading and
3026.7
unloadingon 1597.50
Smooth wheeled roller 8-10 tonners for initial break down
Hr 6.0x0.65* 1,432.0 5584.8
rolling.
Vibratory roller 8 tonnes for intermediate rolling. Hr 6.0x0.65* 1,800.0 7020
Finish rolling with 6-8 tonnes smooth wheeled tandem roller. Hr 6.0x0.65* 1,432.0 5584.8
(d) Total of Labour, Material and Machinery (a+b+c) 1864686.99
Add 12.5% (Over head @ 2.5% + Contractor Profit @ 10%) on ( d ) 233085.87
Total Cost of 191 cum 2097772.86
Cost of 1 cum 10983.104
Add 1% Labour cess 109.83
Total for 1 cum with all inclusion 11092.93
Say 11092.95
Ref. to MORD
SN Description of Items. Unit Qty. Rate Amount
spec.
Tack Coat
Providing and applying Tack coat with bitumen Emulsion (RS-I) using Emulsion distribution @ 0.25 to 0.30
5.10
Kg/sqm on the prepared surface dry and hungry bituminous surface cleaned with hydraulic broom as per
technical specification clause -503.
Unit = sqm, Taking output of cost 1750 sqm.
(a) Labour
Mate Day 0.04 437.50 17.50
Mazdoor (Un Skilled) Day 1 437.50 437.50
(b) Material
Bitumen straight run (RS-I) @ 0.275 Kg/ Sqmt. Tone 0.48 51,454.1 24697.94
(c) Machinery
Hydraulic broom @ 1250 Sqm/Hr. Hr 1.4 528.0 739.2
Air compressor 210 cfm Hr 1.4 488.0 683.2
Bitumen 80/100 presser distributer @ 1750sqmt/Hr Hr 1 1,569.0 1569
(d) Total of Labour, Material and Machinery (a+b+c) 28197.44
Add 12.5% (Over head @ 2.5% + Contractor Profit @ 10%) on ( d ) 3524.68
Total Cost of 1750 sqm 31722.12
Cost of 1 sqm 18.127
Add 1% Labour cess 0.18
Total for 1 sqm with all inclusion 18.31
Say 18.30
Ref. to MORD
SN Description of Items. Unit Qty. Rate Amount
spec.
Panel Cutting in Concrete Pavement
Panel cutting in concrete pavement in squre panels of 1.2M x 1.2M (Maximum panel) sizes sawing in straight
5.13
line up to 1/3rd depth from surface including labour and hireage of cutting machine inclusive of taxes under
R&D projects in PMGSY
1 Unit = Rm, Taking output = 100m panel length
(a) Labour
Mazdoor (Skilled) Day 1 437.50 437.50
Mazdoor (Unskilled) Day 1 437.50 437.50
(b) Machinery
Cutting Machine hour 6.00 1,191.0 7146.00
(d) Total of Labour, Material and Machinery (a+b+c) 8021.00
Add 12.5% (Over head @ 2.5% + Contractor Profit @ 10%) on ( d ) 1002.63
Total Cost of 100 m 9023.63
Cost of 1 m 90.236
Add 1% Labour cess 0.90
Total for 1 cum with all inclusion 91.14
Say 91.15
Cement Treated Crushed Rock or combination as per clause 403.2 and table 400.4in Sub base/ Base
Providing, laying and spreading Material on a prepared sub grade, adding the designed quantity of cement to
5.15 the spread Material, mixing in place with rotavator, grading with the motor grader and compacting with the road
roller at OMC to achieve the desired unconfined compressive strength 4.5 to 7.0 N/mm 2 7-days of curing as
per IRC-SP-72-2015, IRC-37-2018 and SP-89 (part II) 2018 and to form a layer of sub-base/base.
Providing and Laying of Closed Graded Premix Surfacing (Mixed Seal Surfacing) material of 25 mm thickness
by hot mix plant using crushed stone aggegates of 13.2 mm to 0.09 mm (Type B) as per table 500.15 of
specification 509 of MoRD, premix with bituminous binder 60/70 grade (S65, VG-30 Bulk) @23.75 kg per 10
5.16 sqm area, including cost of materials (excluding seigniorage) and transporting the Hot Mix to work Site, laying
with mechanical paver finisher to the required grade, level and alignment, rolling with smooth wheeled roller 8
to 10 Tonnes as per MorD specification 509 complete to finished item of work in all respects as directed by
Engineer in charge
Stabilization of in-situ (existing pavement crust) or soil or otherwise sub base/ base course up to the required
depth by cold in-situ recycling using cement and chemical additives /otherwise: Providing pulverizing, spreading,
milling and mixing of chemical additives at the appropriate rate as per job mix design in accordance with IRC-SP-
72-2015 , IRC-37-2012 & 2018 and IRC SP 89 (part II) 2018. Cementitious additive @ rate of minimum 5 - 7% and
CCS/CS additive should be spread on the existing pavement using a mobile truck mounted containerized cement/
additive spreader with micro processor controlled weighing and spreading system. The additive spreader shall
7.20 have variable working width sufficient to cover whole pavement lane. The in-situ stabilization process shall be
carried out by a mobile and self propelled stabilizer / reclaimer of working width of 2.4 m and with minimum engine
horse power of 440 kw with a variable working depth up to 50 cm. The resultant stabilized mix then would be
profiled to the required grade, level and thickness using motor grader and the mix would be compacted using 20
tonne pad foot roller in combination with smooth wheel roller to achieve desired proctor density as per IRC 37-
2012 & 2018 and complete in all respect and curing with water as required including all materials, labour and
machinery etc.
The entire insitu rocess would be carried out in single pass with milling and pulverising of damaged asphalt
pavement / soil/ aggregates / soil-aggregate mixture to the desired depth and with simultaneous addition of
additives and water with machine integrated spray bars fitted on the wheeled self-propelled and vibratory pad foot
roller to achieve the desired proctor density in all respects. The tandem roller be followed by Pneumatic Tyre
Roller. The minimum unconfined compressive strength (UCS) of stabilized sub base/ base should be 4.5 to 7 MPa
after 7 / 28 days of curing as per IRC-SP-72-2015 , IRC-37-2012 & 2018 . Also durability aspects (wet-dry cycles)
of stabilized sub base should be satisfied as per IRC 37-2012 & 2018 and IRC SP 89 (part II) 2018. The gradation
mixes and materials should be as per IRC 37-2012 & 2018 and IRC SP 89 (part II) 2018. The train of equipment's
to be used are binder spreader- water Tanker- Additive Truck- Recycler- Padfoot Roller (20 Tonne) + Single Drum
M15 RCC BOUNDARY PILLARS Reinforced cement concrete M15 grade boundary pillars of standard design
8.1
as per IRC:25-1967, fixed in position including finishing and lettering but excluding painting
Unit = each, Output-57 Nos.
M-15 grade of the boundary stone cum 1.25 4065.25 5081.56
Steel reinforcement kg 79.80 49.32 3935.81
Excavation in soil cum 10.72 120.00 1286.40
Lettering, each 10 cm high (per letter per cm high) per letter 2280.00 1.20 2736.00
(a) Labour
Mate Day 0.57 437.50 249.37
Mazdoor (Unskilled) Day 14.25 437.50 6234.38
(b) Material
Stone spall cum 11.97 837.61 10026.19
(c) Machinery
Tractor-trolley hour 0.4 581.00 232.40
(d) Total of Labour, Material and Machinery (a+b+c) 29782.11
Add 12.5% (Over head @ 2.5% + Contractor Profit @ 10%) on ( d ) 3722.76
Total Cost of 57 nos of Boundary Pillars 33504.87
Cost of 1 nos of Boundary Pillars 587.80
Add 1% Labour cess 5.88
Total for 1 cum with all inclusion 593.68
Say 593.70
Sub Analysis (Cement Mortar 1:3)
8.1.1 Cement Mortar 1:3
Unit = Nos., Taking out = 3 Nos.
(a) Labour
Mate Day 0.08 408.33 32.67
Masson 1st class Day 0.1 583.33 58.33
Mazdoor (Unskilled) Day 1.63 408.33 665.58
Bhisti Day 0.27 408.33 110.25
(b) Material
Cement Tonne 0.28 6363.20 1749.88
Course sand Cum 0.48 977.72 469.30
40mm aggregate Cum 0.48 1024.03 491.54
20mm aggregate Cum 0.24 1074.03 257.77
10mm aggregate Cum 0.08 1124.03 89.92
(c) Machinery
Machinery concrete mixed 0.4/0.28 cum capacity fitted with
Hours 0.40 350.00 140.00
water measuring device and preferably also with load cell.
Total of Labour, Material and Machinery (a+b+c) 4065.24
Say 4065.25
Ref. to MORD
SN Description of Items. Unit Qty. Rate Amount
spec.
Providing and applying two coats of ready mix paint including primer coat of approved brand on steel surface
8.6 after through cleaning of surface to give an even shade as per drawing and Technical Specification Clause
1701
Unit = sqm, Taking output = 10 sqm
(a) Labour
Mate Day 0.25 437.50 109.38
Painter (Ist class) Day 0.6 494.67 296.80
Mazdoor (Unskilled) Day 0.4 437.50 175.00
(b) Material
Red-oxide Primer as per specifications litre 0.6 200.00 120.00
Paint ready mixed approved brand litre 1.25 312.00 390.00
Total of Labour, Material and Machinery (a+b) 510.00
Add @ 1 per cent on cost of material for scaffolding wherever
(c) 5.10
required
(d) Total of Labour, Material and Machinery (a+b+c+d) 1606.28
Add 12.5% (Over head @ 2.5% + Contractor Profit @ 10%) on ( e ) 200.78
Total Cost of 10 sqm 1807.06
Cost of 1 sqm 180.71
Add 1% Labour cess 1.81
Total for 1 sqm with all inclusion 182.52
Say 182.50
(ii) Cement concrete M-15 grade, Item No 5.1 Cum 0.126 4065.25 512.22
Painting angle iron post with primer and two coats of expoxy
(iii) sqm 0.46 265.00 121.90
paint.
(a) Labour
Mate Day 0.1 437.50 43.75
Mazdoor (Unskilled) Day 0.25 437.50 109.38
(b) Material
Support of MS sheet tube 47mmx47mm x12 SWG Sheet
Kg 12.4 91.00 1128.40
3050 mm long
Angle iron 50x 50x 6mm for hold fast including 5% wastage. kg 1.06 0.00 0.00
1.5mm thick MS sheet duly painted with stove enameled
sqm 0.67 0.00 0.00
paint etc.
Add 3% of cost of MS sheet tube 12 SWG & angle iron
33.85
toward cost of fabrication drilling holes nuts, bolts etc.
(c) Machinery
Tractor with trolley Hours 0.08 581.00 46.48
(e) Total of Labour, Material and Machinery (a+b+c+d) 2048.09
Add 12.5% (Over head @ 2.5% + Contractor Profit @ 10%) on ( e ) 256.01
Total Cost of 1 Traffic Sign 2304.10
Add 1% Labour cess 23.04
Total for 1 sign board with all inclution 23.04
Say 23.05
Angle iron 50 x 50 x 6 mm for hold fast including 5% wastage kg 1.06 91.00 96.46
Angle iron 50 x 50 x 6 mm for hold fast including 5% wastage kg 1.06 91.00 96.46
Angle iron 50 x 50 x 6 mm for hold fast including 5% wastage kg 1.06 91.00 96.46
Angle iron 50 x 50 x 6 mm for hold fast including 5% wastage kg 1.06 91.00 96.46
Angle iron 50 x 50 x 6 mm for hold fast including 5% wastage kg 1.06 91.00 96.46
Angle iron 50 x 50 x 6 mm for hold fast including 5% wastage kg 1.06 91.00 96.46
Angle iron 50 x 50 x 6 mm for hold fast including 5% wastage kg 1.06 91.00 96.46
2 No. MS tubes 75mmx75mm of 12 SWG sheet 2650mm long Kg 90.55 91.00 8240.05
Unit = mtr.
Taking output 7.5 mtrs.
(a) Labour
Mate Day 0.07 437.50 30.63
Masson 1st class Day 0.2 603.17 120.63
Majdoor (Unskilled) Day 1.6 437.50 700.00
Total 851.26
(b) MATERIAL
Cement Tonne 0.03 7,064.94 186.74
Course sand Cum 0.04 1,401.20 56.05
RCC Pipe NP3 concrete pipe i/c Rmt. 7.5 3,218.23 24136.69
collar at site
24379.48
Total 25230.73
(c) Over heads & C.P. (a+b+c) & CP 4875.8951
@20%
30106.63
(d) Add 1% Labour cess 301.066296
Add 18 % GST 5419.193328
35826.89
Cost for 7.50 mtrs. 4776.92
Say Rs. 3762.85/-
#REF! #REF!
#REF! #REF!
#REF! #REF!
Analysis of Rate
Sr. Reference to Description Unit Quantity Rate
No. MORD (Rs.)
Specification
s
55,362.69
Total:- 66,072.69
d) Overheads & CP @ 20% 13,214.54
on (a+b+c)
79,287.23
Add 1% Labour Cess 792.87
Add GST multiplying factor ( .2127) 16,864.39
Cost of 1250 sqm = a+b+c+d+e 96,944.50
Rate per sqm = (a+b+c+d+e)/1250 77.56
Say Rs. 71.85