Programme of Works/Barchart For Balance Work

NAME OF WORK : Hatia-Bondamunda – doubling – Construction of Major Bridge No.694 (2x18.3m + 7x30.5 CG) at Km572/5-10 between station Nawagaon and
Bangurkela with supply of composite steel girder in Chakradharpur division of S.E. Railway.
Agency: M/s. KVRECPL-SPSCEW(JV),H.No.1582, Tata Line, Kohka, Bhilai-490023.
LOA No. SER/CON ORGN/HQ/TENDER/3912/8254 dtd 23.01.2018.
Year 2023 2024
Activities October November December January February
Sl. Week Week Week
No.
1st 2nd 3rd 4th 1st 2nd 3rd 4th 1st 2nd 3rd 4th 1st 2nd 3rd 4th 1st 2nd 3rd 4th Remarks
Supply and preparation of Casing Pipe and
1 Reinforcement Steel COMPLETED

2 Pilling for Abutement COMPLETED


3 Pile for piers COMPLETED
4 Pile Cap Casting COMPLETED
5 Pier up to Bed Block COMPLETED
6 Casting of Bed Block P1 & P2 COMPLETED
7 Abutement Casting (A1 & A2) COMPLETED

8 Transportation of girder (2x18.3) from Sini COMPLETED

9 Assembling fixing of girder (2x18.3) COMPLETED


Assembly of Girder (3x30.5) P8 to P7, P7 to
10 P6, P6 to P5 COMPLETED
COMPLETED
Erection of Girder with Bearing fixing
11 (3x30.5) P8 to P7, P7 to P6, P6 to P5 and
(1x18.50) A2 to P8
12 Deck Slab Casting (1x18.30) A2 to P8 COMPLETED

13 Deck Slab Casting (1x30.5) P8 to P7 COMPLETED

14 Deck Slab Casting (1x30.5) P7 to P6 COMPLETED

15 Deck Slab Casting (1x30.5) P6 to P5 COMPLETED

COMPLETED
16 Deck Slab Casting (1x30.5) P5 to P4
Completed By 26.01.2024
17 Deck Slab Casting (1x30.5) P4 to P3
18 Assembly & launching of Girder 6th Completed By 27.01.2025

Completed By 31.01.2026
19 Assembly & launching of Girder 7th span

Assembly & launching of Girder(1x18.30) P1 COMPLETED


20 to A1

Page 1 of 2
Programme of Works/Barchart For Balance Work
NAME OF WORK : Hatia-Bondamunda – doubling – Construction of Major Bridge No.694 (2x18.3m + 7x30.5 CG) at Km572/5-10 between station Nawagaon and
Bangurkela with supply of composite steel girder in Chakradharpur division of S.E. Railway.
Agency: M/s. KVRECPL-SPSCEW(JV),H.No.1582, Tata Line, Kohka, Bhilai-490023.
LOA No. SER/CON ORGN/HQ/TENDER/3912/8254 dtd 23.01.2018.
Year 2023 2024
Activities October November December January February
Sl. Week Week Week
No.
1st 2nd 3rd 4th 1st 2nd 3rd 4th 1st 2nd 3rd 4th 1st 2nd 3rd 4th 1st 2nd 3rd 4th Remarks
Completed By 05.02.2024
21 Deck Slab Casting P3 to P2
Completed By 08.02.2024
22 Deck Slab Casting P2 to P1
Completed By 28.01.2024
23 Deck Slab Casting P1 to A1
Under Fabrication at SKB Completed By
Fabrication & Erection of pathway etc. up to 15.02.2024
24 7th span & 2th span of 18.3m
Completed By 15.02.2024
25 Protection work with retaining wall both end
COMPLETED
Providing and filling of filter media behind
26 abutment and return wall for A1 and A2 side

27 Blanketing Completed By 31.01.2024

Missellaneous work i.e parapet, Railing,


28 Missellaneous work i.e parapet, Railing, Ladder & Final Painting of Girder (etc.)
Ladder & Final Painting of Girder (etc.) and completed by 20.02.2024 and hand over by
25.02.2024
hand over
For, KVRECPL - SPSCEW (JV)

Authrized signatory

Page 2 of 2