PROJECT NAME - MINGALAR YANKIN PUBLIC RENTAL HOUSING PROJECT

BUILDING NOS - C-80/C-802/C-803 ( GRAND LOTUS CONSTRUCTION CO.,LTD )

TEAM MEMBER - U BO SANN

PROJECT MANAGER - U YAR ZAR MOE

WORK PROGRAMME

DECEMBER JANUARY FEBRUARY MARCH APRIL MAY JUNE


Sr.
PARTICULAR
No
3rd Wk4th Wk1st Wk2nd Wk
3rd Wk4th Wk1st Wk2nd Wk3rd Wk4th Wk1st Wk2nd Wk3rd Wk4th Wk1st Wk2nd Wk3rd Wk4th Wk1st Wk2nd Wk3rd Wk4th Wk1st Wk

5-Storeyed RCC Building

S
1 Site Cleaning+Survey+Marking
A
S
2 Site Store & Labour Camp
A
S
3 Staking Works for Preparation of Foundation
A
S
4 Earthwork Excavation for Footing
A
S
5 Sandfilling & (1:3:6) Lean Conc Work for Footing
A
S
6 Footing & Short Column Production Work
A
S
7 (1:2:4)Concrete Work for Footing
A
S
8 (1:2:4)Concrete Work for Short Column
A
S
9 Earthwork Excavation for RW
A
S
10 (1:3:6) Lean Conc Work for RW
A
S
11 Brick Work for RW
A
S
12 Ground Beam Prduction Work
A
S
13 (1:2:4)Concrete Work for Ground Beam
A
S
14 Back Filling Work
A
S
15 4 1/2" tk 1:3:6 Concrete Footing (GF)
A
S
16 GF to 1st Floor Column (Production & Conc Work)
A
S
17 1st Floor Beam & Slab (Production & Conc Work)
A
S
18 1st to 2nd Floor Column (Production & Conc Work)
A
S
19 2nd Floor Beam & Slab (Production & Conc Work)
A
S
20 2nd to 3rd Floor Column (Production & Conc Work)
A
S
21 3rdFloor Beam & Slab (Production & Conc Work)
A
S
22 3rd to 4th Floor Column (Production & Conc Work)
A
S
23 4th Floor Beam & Slab (Production & Conc Work)
A
S
24 4th to Roof Floor Column (Production & Conc Work)
A
S
25 Roof Floor Beam & Slab (Production & Conc Work)
A
S
26 4-1/2" thk Brick Walling Work (GF & 1st Floor)
A
S
27 4-1/2" thk Brick Walling Work ( 2nd Floor)
A
S
28 4-1/2" thk Brick Walling Work ( 3rd Floor)
A
S
29 4-1/2" thk Brick Walling Work ( 4th Floor Top Roof)
A
S
30 Plastering Work - External Walling
A
S
31 Plastering Work - Internal Walling
A
S
32 1-1/2" thk Floor Topping Work (All Floor Area)
A
S
33 Glazed Tile Work
A
S
34 Roof Frame,Roofing & Ceiling Work
A
S
35 Window Leaves Fitting
A
S
36 Door Leaves Fitting
A
S
37 Irongrill Work
A
S
38 Painting Work (Emusion & Enamel)
A
S
39 Electrical Installation
A
S
40 Sanitary Installatin
A
S
41 Plumbing Work
A

42 Ground Tank,Septic Tank & Apron and Drain Work

S
43 Site Clearing Work
A

Programme

Progress
JUNE JULY AUGUST SEPTEMBET
Work
Work % of
Done REMARK
Done % Total
2nd Wk3rd Wk4th Wk1st Wk2nd Wk3rd Wk4th Wk1st Wk2nd Wk 3rd Wk4th Wk of Item
3rd Wk4th Wk1st Wk2nd Wk

1% 100% 1%

1% 100% 1%

1% 100% 1%

2% 100% 2%

2% 100% 2%

2% 100% 2%

2% 100% 2%

2% 100% 2%

2% 100% 2%
1% 100% 1%

3% 100% 3%

3% 100% 3%

3% 100% 3%

2% 100% 2%

2%

2% 100% 2%

3% 66.67% 2%

2% 33% 0.67%

3%

2%

3%
2%

3%

2%

3%

3%

2%

2%

3%

4%

4%

4%

2%

4%

2%

2%

1%
4%

4%

4%

1%

100% 31.67%