MANHOLE JOB RATE AT UBL GHQ BR RAWALPINDI

S/NO DESCRIPTION UNIT NO L B H QANTY BOQ RATE Rs AMOUNT REMARKS


1 Manhole near Grid A
a excavation Cft 4' 4' 5' 80 2.1 17/Cft 1360
b P/L lean conc under foundation Cft 4' 4' 0.33' 5.28 4.1 200/cft 1056
c Brick masonary work 9'' thick Sft 2 3' 4.33' 25.98 6.1 250/sft 6495
Sft 2 2' 4.33' 17.32 6.1 250/sft 4330
d P/L conc 1:2:4 in benching Cft 1 1.5' 2' 0.33' 0.99 4.3 370/cft 366.3
e Plaster work Sft 2 1.5' 4' 12
2 2' 4' 16
total 28 7.1 36/sft 1008
f P/L conc 1:2:4 in RCC slab Cft 1 3' 3.5' 0.25 2.62 4.3 370/cft 969.4
TOTAL Rs 15584.7
S/NO DESCRIPTION UNIT NO L B H QANTY BOQ RATE Rs AMOUNT REMARKS
2 Manhole near Grid C
a excavation Cft 1 4' 5' 5.5' 110 2.1 17/Cft 1870
b P/L lean conc under foundation Cft 1 4' 5' 0.33' 6.6 4.1 200/cft 1320
c Brick masonary work 9'' thick Sft 2 4.5' 5' 44 6.1 250/sft 11000
Sft 2 1.5' 5' 15 6.1 250/sft 3750
d P/L conc 1:2:4 in benching Cft 1 3' 1.5' 0.33' 1.48 4.3 370/cft 549.45
e Plaster work Sft 2 3' 4.75' 28.5
2 1.5' 4.75' 14.25
total 42.75 7.1 36/sft 1539
f P/L conc 1:2:4 in RCC slab Cft 1 3' 4.5' 0.25 3.375 4.3 370/cft 1248.75
Total Rs 21277.2
S/NO DESCRIPTION UNIT NO L B H QANTY BOQ RATE Rs AMOUNT REMARKS
3 Manhole near Sokage pit
a excavation Cft 1 5' 5' 7.5' 188 2.1 17/Cft 3196
b P/L lean conc under foundation Cft 1 5' 5' 0.33' 8.25 4.1 200/cft 1650
c Brick masonary work 9'' thick Sft 2 4.33' 7' 60.62 6.1 250/sft 15155
Sft 2 3' 7' 42 6.1 250/sft 10500
d P/L conc 1:2:4 benching Cft 1 4.33' 4.5' 0.33' 6.43 4.3 370/cft 2379
e Plaster work Sft 2 2.83' 7' 60.62
Sft 2 4.5' 7' 63
total 123.62 7.1 36/sft 4450
f P/L conc 1:2:4 in RCC slab Cft 1 4.33' 4.5' 0.25 4.87 4.3 370/cft 1802
Total Rs 39132
S/NO DESCRIPTION UNIT NO L B H QANTY BOQ RATE Rs AMOUNT REMARKS
4 Manhole inside Duct
a excavation Cft 1 3' 4' 6.75 81 2.1 17/Cft 1377
b P/L lean conc under foundation Cft 1 3' 4' 0.33' 3.96 4.1 200/cft 792
c Brick masonary work 9'' thick Sft 1 3' 6.42' 19.26 6.1 250/sft 4815
Sft 2 2' 6.42' 25.68 6.1 250/sft 6420
d P/L conc 1:2:4 benching Cft 1 3' 2' 0.33' 1.98 4.3 370/cft 732.6
e Plaster work Sft 1 3' 6.42' 19.26
2 2' 6.42' 25.68
total 44.94 7.1 36/sft 1617.84
f P/L conc 1:2:4 in RCC slab Cft 1 2.5' 2.5' 0.25 1.56 4.3 370/cft 578.12
Total Rs 16332.56

5 Mainhole Septic tank


Brick masonary work 9'' thick Sft 2 3' 5' 30 6.1 250/sft 7500
// Sft 2 1.5' 5' 15 6.1 250/sft 3750
Plaster work Sft 2 3' 5' 30
Sft 2 1.5' 5' 15
Sft Total 45 7.1 36/sft 1620
Total Rs 12870
S/NO DESCRIPTION UNIT NO L B H QANTY BOQ RATE Rs AMOUNT REMARKS
1 Total Weight of Steel of 04 No cover slab of
Mainholes KG 49.75 5.1 135/Kg 6716
0
0
SUMMARY 15585
Total cast of Mainhole No 1 1 21277
Total cast of Mainhole No 2 1 39132
Total cast of Mainhole No 3 1 16333
Total cast of Mainhole No 4 1 Grand Total Rs 99043