Professional Documents
Culture Documents
PIPING DEPARTMENT
INDEX
1.0 INTRODUCTION OF VESSELS AND TANKS
9.0 OUTPUTS
1.1 Definition
When any chemical change takes place due to the pressure and temperature inside the
equipment is called Vessel. Vessel may be a fractionating tower, in which separation takes
place. Fractionating tower may be called as Fractionating Columns. Vessels are given
names according to their function they perform.
1.2 Types
Vessel may be Process, Storage Vessel and Storage Tanks, mainly we can define as under:
1.3.1 Process Vessel: A container for handling chemical change for liquid and
gas.
a. Fractionating Column
• Generally vertical
• Containing trays or packing
• For extraction purpose
b. Reflux Accumulator
• Generally horizontal
• Without internals
• Collect & transmit back to fractionating column
c. Reactor
• Vertical and contains catalyst
• May have agitator arrangements
d. Regenerators
• Generally vertical and contains catalyst from reactor
• Use to restore the catalyst of reactor
The crude oil is the mixture of hydrocarbon compounds with wide range of boiling
points from 100^F (38^C)
to 1400^F (760^C).
Separation or distillation, is
a process by which a liquid
mixture is partially
vaporized. The vapors are
then condensed, separating
the individual components
of the mixture. As temp. of
crude oil raised, the initial
boiling point (IBP) is
reached. As boiling
continue, the temp raises.
The lightest material
Butane is first product on
just below the 100^F (38^C). The heavier product are produced above 100^F
(38^C)
FLUOR NEW DELHI OFFICE
PIPING DEPARTMENT
VESSELS & COLUMN / TOWER PIPING
The evolution of distillation towers is best explained in three basic steps. The batch
shell still process, the continuous shell still process and the fractional distillation
process.
2.3 Fractional
Distillation
Similar to continuous
shell still process, the
Fractional Distillation
process is made up of
several still linked
together in series. The
main difference is that all
the liquid condensate is
returned to the upstream
still.
FLUOR NEW DELHI OFFICE
PIPING DEPARTMENT
VESSELS & COLUMN / TOWER PIPING
As the feed is partially vaporized in the first still, the vapor rise, the travel through
the overhead line, and come in to connect with liquid in the second still. Because
the temperature of liquid is in the second still is lower than the incoming vapors
from the first still, the vapors partially condense. At the same time liquid from
second still enters near the top of the first still. As vapors rise in the first still, they
meet the incoming liquid from the second still. This cause vaporization of the
incoming liquid from the second still and condensation of the rising vapors in the
first still. The same process takes place in all the down stream stills.
Rising vapor in the tower pass through slotted bubble caps and come in to contact
with liquid flowing around the caps. The liquid flows downwards through the
downcomer over and around the bubble caps en route to the next downcomer in this
manner. The light boiling fraction in the down flowing liquid are vaporized due to
the heat from the rising vapors, and heavier boiling fractions in the vapors are
condensed and flow down the towers. This process of vaporization and
condensation throughout the tower allows the feed to separated in to the required
boiling range fractions, which are taken out from the tower at their appropriate
locations.
FLUOR NEW DELHI OFFICE
PIPING DEPARTMENT
VESSELS & COLUMN / TOWER PIPING
The types of tower is based on the two aspects, first service type of the unit like Stripper,
splitter, absorber and vacuum towers etc. second types of internals like trayed and packed.
Shell, head, skirt, skirt vent, skirt access opening, base plate, anchor bolts, anchor bolt
chairs, saddles, mist eliminator, support grids, nozzles, manholes, column davits,
insulation rings, ladders and cages, manhole hinges and davits, platforms and vacuum
stiffening rings etc.
Seal Pans: Flat plate plates bolted or welded to inside the fractionation tower shell below
the downcomer of lowest tray. Used to prevent vapor bypassing up through the
downcomer.
Trays: Trays comes in several types, all with the same purpose to fractionate-out the
lighter hydrocarbon from a liquid. The heavier hydrocarbon will remain in their liquid
state and flow down through downcomer to next tray. The vapor and liquid contact,
which results in fractionation. Types of trays are as under:
Downcomer:
Rectangular flat plate bolted to the shell and trays, inside the fractionation columns.
Used for directing process liquid and to prevent bypassing the vapor.
FLUOR NEW DELHI OFFICE
PIPING DEPARTMENT
VESSELS & COLUMN / TOWER PIPING
5.0 NOZZLE NOMENCLATURE
Vessel nozzle symbols - Fluor uses a system of nozzle symbols to make it easier to
identify nozzles and couplings. These symbols also indicate the nozzle function.
A. = Inlet Nozzle
B. = Outlet Nozzle
C. = Condensate Nozzle
D. = Drain or Drawoff
E. = *
F. = Feed Nozzle
G. = Level Gage or Gage Glass
H. = Handhole
J. = Pump Out Nozzle
K. = *
L. = Level Instrument Nozzle
M. = Manhole
N. = Reboiler Connection
P. = Pressure Connection
R. = Reflux Nozzle
S. = Steam or Sample Connection
T. = Temperature Connection
V. = Vapor Out or Vent Nozzle
W. = Relief Valve Nozzle
*Symbols "E" and "K" are sometimes used for special nozzles.
6.3 Clearance
• Minimum spacing between two vessels should be one large vessel diameter or
1500 mm to 2000 mm (Project / Client’s requirement)
• Minimum 3.0 m away from piperack for forklift (face of dished end)
6.4 Sources Of Information Required To Start Orientation
INFORMATION SOURCE
Flow Diagrams Piping Design Supervisor or Roller Board
Job Specifications, Drafting Room Piping Design Supervisor and Fluor Daniel
Instructions and Standards Standards, Job Book
Preliminary Job Information Project Manager, Design Coordinator or Piping
Design Supervisor
Flow Diagram Transposition (not Piping Design Supervisor
provided in this lesson)
Vessel Drawing or Vessel Quote Drawing Vessel Design Supervisor or Piping Design
Supervisor
Drum Height Flow Diagram or Process Engineer
Process Nozzle Elevations Vessel Drawing or Process Engineer
Normal Liquid Level and Other Liquid Vessel Drawing, Flow Diagram or Process
Levels Engineer
Instrument Nozzle Elevations Vessel Drawing, Process or Instrument
Engineer, Instrument Standard Drawings
Customer Requirements Customer via Project Manager, Design
Coordinator and Piping Design Supervisor
Plot Plan piping designer supervisor
FLUOR NEW DELHI OFFICE
PIPING DEPARTMENT
VESSELS & COLUMN / TOWER PIPING
6.5 Steps To Accomplish Horizontal Vessel Study
Height of horizontal vessels is shown on the flow diagram. If this requirement is not
on flow sheet, there are the following alternatives:
• Vessel height can be increased to meet the minimum 8'-0" headroom
requirement.
Block the operating aisle with a low suction line. (Not recommended)
• Take the pump out of the pump row and locate it near the vessel so that the
suction line does not cross the operating aisle. The NPSH requirement of any
pumps connected to these vessels should be taken into account.
• Inlet should be at the opposite end of vessel (maximum distance) from the
liquid and vapor outlets to prevent "short circuiting" of the flow.
• Level instruments and boot should be at the opposite end of vessel (maximum
distance) from inlet. The instrument bridle connections are located in the surge
section of the vessel. This end of the vessel is nearest the operating aisle.
• To allow for the horizontal growth due to thermal expansion, anchoring the
vessel at the support nearest the pipeway.
• The inlet is normally located on the end of the vessel away from the pipeway.
This arrangement then locates the level instruments next to the operating aisle
for good accessibility per specification 000.250.50001.
FLUOR NEW DELHI OFFICE
PIPING DEPARTMENT
VESSELS & COLUMN / TOWER PIPING
• For setting up the support legs on a horizontal vessel, a good "rule of thumb" to
follow is:
"D" = Vessel diameter,
"L" = Vessel length tan. To tan.
"S" = Distance from tan. to centerline of support leg
S = L/5
S = D/4
Note: In this case the vessel head acts as a stiffener to the shell.
• Vent is located at the opposite end of the vessel from the steam out and a
maximum distance away.
• The vortex breaker is located at the inside bottom of the vessel on the liquid out
nozzle. Its function is to prevent a whirlpool movement of the liquid at pump
suction nozzle.
6.10.1 Orientation
A Vessel Orientation will determine the location and orientation of:
• The preferred range of orientation allows entry into the vessel over the tray.
Entry over the downcomer could be a safety concern as well as a hindrance to
personnel.
• Manhole orientation over a two-pass tray is more limited than that of a single
tray. Entry over the downcomer is generally not acceptable, but still may be
considered an option when faced with a design situation where other options
are less desirable
• The size of the manhole is usually determined by the Vessel Design Group.
• Manhole covers are much too heavy for plant operators or maintenance
personnel to lift. A manhole cover davit or hinge is used to hold the cover
after it has been unbolted. Orient manhole to swing away from ladder leading
to lower level. Manhole cover shall swing 100o without obstruction.
• The elevations of manholes are set by tray arrangement and spacing.
Consideration shall be given to raising or lowering manholes one tray to
provide the most economical ladder and platform arrangement.
• Hinged manholes can also be used for a bottom entry, i.e., reactors
• Nozzles
• Ladder and platforms
• Davit
FLUOR NEW DELHI OFFICE
PIPING DEPARTMENT
VESSELS & COLUMN / TOWER PIPING
FLUOR NEW DELHI OFFICE
PIPING DEPARTMENT
VESSELS & COLUMN / TOWER PIPING
This practice in conjunction with practice 000 250 2650, shall be used as a layout and in
an effort to assure uniformity in the arrangement of the various vessel components. For
example, all ladders, manholes, platforms, level controllers and gauge glasses shall have
similar orientation whenever economically feasible.
1.0 Manholes refered to in practice 000 256 4055 shall be provided for access and
inspection of vessel ends, trays, bubble caps and internal piping as required.
1.1 Manhole orientation is dependent on tray arrangement, access* and
maintenance area for vessel. For access and maintenance considerations refer
to practice 000 250 2650
2.0 Reboiler nozzles shall be oriented by tray arrangement, type of Reboiler and/or
piping flexibility requirements.
3.0 Process nozzle orientations shall meet process requirements specified on the flow
diagrams. Elevations are generally as specified on the vessel drawings.
Consideration shall be given to minor nozzle elevational adjustments and
variations from the feed and draw-off methods shown. To provide the maximum
economical arrangement.
3.1 Reflux, feed and inter cooler nozzles shall be oriented relative to the tray
downcomers as shown.
4.0 Instrument and sample connections shall be oriented by tray and access
considerations.
4.1 Liquid temperature and sample connection points are normally taken in the
downcomer area of the tray below. If process conditions permit, sample or
temperature points may be varied one tray to allow maximum economy in the
ladder and platform arrangement.
4.2 Vapor temperature and sample connection points are normally located in the
area behind the downcomer.
4.3 Refer to practice 000 250 2650 paragraph 7.0 for access considerations.
FLUOR NEW DELHI OFFICE
PIPING DEPARTMENT
VESSELS & COLUMN / TOWER PIPING
• Vessel Trim
Vessel trim is a term used to identify piping, instrument, and
valves connected to the following connections on vessels:
- Vents
- Drains
- Steam-out
- Relief valves
- Instruments including level controllers and gages
- Many of the internals and valves attached to nozzles of
vessels are very heavy. When maintenance is required,
they must be removed and lowered to grade.
FLUOR NEW DELHI OFFICE
PIPING DEPARTMENT
VESSELS & COLUMN / TOWER PIPING
A vessel davit is
usually provided in the
following cases:
• The vessel exceeds
a height of 30 feet
above grade.
• The vessel is not
accessible with an Austin-Western or equivalent mobile
crane.
• The vessel is not in a structure or grouped with other
vessels where other lifting facilities are provided.
6.10.4. Clearances
• The following clearances are from the P.D.G. -Technical Practice
000.250.2040 "Arrangement of Equipment" and "Equipment and Pipeway
Clearances" section, and Attachment 3: "Space Allocation at Support
Columns."
• The minimum clearance for a forklift or similar equipment is 6'-0"
horizontal by 8'-0" vertical.
For portable manual equipment operation provide 3'-0" horizontal by 8'-
0" vertical
• The minimum clearance for mobile equipment access (hydraulic cranes,
trucks, etc.) is 10'-0" horizontal by 10'-0" vertical .
The height of the vessel skirt is to determine with the help of N.P.S.H.
(Net Positive Suction Head). This is the height of a column of liquid
(head) necessary to keep the bottoms out pump suction primed.
6.10.9 Clearances
• Minimum spacing between two vessels should be one large vessel,
diameter or 1500mm to 2000mm (Depending upon Project / Client's
requirements)
• Minimum 3.0m away from the piperack for forklift (face of dished end)
FLUOR NEW DELHI OFFICE
PIPING DEPARTMENT
VESSELS & COLUMN / TOWER PIPING
FLUOR NEW DELHI OFFICE
PIPING DEPARTMENT
VESSELS & COLUMN / TOWER PIPING
8.1.4 Instruments
• All the instruments valves should be operable from grade / platform /
ladder or portable ladder (project specific)
• Instrument nozzles should be located pipe way side
• Or away from inlet side to get the correct measurement
• Bridle cane is used to place two or more instrument nozzles on it. Instead
of putting individual nozzle on equipment
• LG should be on visible location
• LG & LT nozzle elevations should be 150mm below / above the min /
max. liquid level
FLUOR NEW DELHI OFFICE
PIPING DEPARTMENT
VESSELS & COLUMN / TOWER PIPING
8.1.7 Vent
• Located opposite end of the vessel steam and inlet
8.1.9 Manway
• Manway should be oriented access side
• Away from rack
• Generally 18" NB in diameter
• Many can be oriented opposite from rack top of the vessel or side of the vessel
• Up to 4.5m elevation of bottom of manway to platform is required
FLUOR NEW DELHI OFFICE
PIPING DEPARTMENT
VESSELS & COLUMN / TOWER PIPING
8.2.5 Instruments
• All the instruments valves should be operable from grade / platform /
ladder or portable ladder (project specific)
• Instrument nozzles should be located such that it will be easily accessible
for correct measurement
• Bridle can be used to place two or more instrument nozzles on it
• LG should be on visible location as close to ladder and platforms.
• LG & LT nozzle elevations should be 150mm below / above the min /
max. liquid level
FLUOR NEW DELHI OFFICE
PIPING DEPARTMENT
VESSELS & COLUMN / TOWER PIPING
FLUOR NEW DELHI OFFICE
PIPING DEPARTMENT
VESSELS & COLUMN / TOWER PIPING
8.2.7 Vent
• Located on top of the vessel or any safe location as required.
9.0 OUTPUTS
• Nozzle orientations and ladder and platforms orientations
• Vessel support clips locations and orientation
• Squad checks of vessel and other discipline drawings.
• Dressed vessel package
• Stress and final iso’s
FLUOR NEW DELHI OFFICE
PIPING DEPARTMENT
VESSELS & COLUMN / TOWER PIPING
10.0 SUPPORTS
• Final / latest P&ID - compare your copy with roller board before starting checking
• Final / master copy of vendor drawing
• Check nozzle elevation, size and rating
• Check BOM, FW location, support location and type of support with stress sketch.
• Check routing following in DRV
• Check supports should be properly placed on structure / MPS steel before releasing
the isometric
• Check valve accessibility and operability
• Spool PC length as per JIM (ship box size)
• Check job book for correctness of all data / modeling at various stages.
Reference:
1. Process & Utility Piping Design, Layout & Drawing – practice 000.250.50001,
000.250.2650,000,250.2651 and 000.250.2660
2. Instrument Piping – practice – 000.250.2701, 2702, 2705, 2710, 2711, 2720, 2730,
2740, 2750, 2752, 2790 & lesson 3 of Piping design layout training
3. Piping Design Layout Training – Lesson 1,3, 4 and 7.
4. Valve accessibility and clearances – practice 000.250.2031
5. Process Plant Layout and piping Design (Ed Bausbacher & Roger Hunt)
FLUOR NEW DELHI OFFICE
PIPING DEPARTMENT
VESSELS & COLUMN / TOWER PIPING
HAPPY LEARNING
FLUOR NEW DELHI OFFICE
PIPING DEPARTMENT
VESSELS & COLUMN / TOWER PIPING
THANKS