You are on page 1of 2

Format No.

Checklist for Isometrics APIL-NCR-PPP-CHKL-010

June 2008

Contract / Project Name


Contract / Project No.
Boiler Type
Drawing Nos.

Sl. Checkpoints Status (Tick Remarks


No. if Confirmed)
1 Is title block complete
2 Is revision block complete
3 Is Reference Grid attached applicable?
4 Are details of connection/continuation Isometrics
shown?
5 Is drawing in line with Piping GA / Layout?
6 Are following parameters as per P&Ids?
7 Insulation thickness, reduction in insulation
indicated in isometric shown?
8 Design Temperature
9 Design Pressure
10 Test pressure (DIN or ANSI)
11 Material of Construction
12 Nominal Diameter
13 Wall thickness
14 Is new MTO extracted and checked for variation?
15 Are supports & support functions in line with
stress analysis?
16 Is support spacing as per piping guidelines?
17 Is marked-up P&ID ready?
18 Are the following details shown?
19 Elevations throughout the Pipe Route
20 Slope of the Line, Flow Direction
21 High-point Vents & Low-point Drains & their
necessity
22 KKS for Pipes, Valves & In-Line Components
23 Dimensions of Specialty components acc. to
Component Dwgs.
Are the following as per piping guidelines?
24 Location & orientation of Valve
25 Location & orientation of Instruments
(temperature points, pressure points, flow meter
etc.)
26 Is eqp. nozzle identity details (nozzle no., rating,
description etc.) shown?
27 Are distances from Ref. Axis (Grid) shown?
28 Are scope (vendor, area, building, discipline etc.)
break sufficient and indicated in marked up
P&ID?
29 Are reasons for any hold shown?
30 Are special connection fittings for instruments

Checked by Approved by Date: Sh. 1 of 2


Signature : Signature :

Name : Name :
Format No. :

Checklist for Isometrics APIL-NCR-PPP-CHKL-010

June 2008

used?
31 Upstream/downstresm distances of
valves/components etc.
32 Language specific issues (eg. in Deutsch,
Spanish etc.)

Checked by Approved by Date: Sh. 2 of 2


Signature : Signature :

Name : Name :