1. SCOPE

This Technical delivery condition covers the requirements of Air receiver vessel Dished Ends fabrication.

2. DESIGN CODES

The following codes in their latest edition including their addenda at the time of fabrication shall form the
basis for fabrication, inspection, testing and acceptance of dished ends.
(a). Construction - ASME Boiler and Pressure Vessel code Sec. VIII, Div-1, Edition 2019.
(b). Materials - ASME Boiler and Pressure Vessel code Section II, Edition 2019.

3. GENERAL FABRICATION

The completed Dished Ends shall meet the requirements given in the drawing and as applicable codes.

 Forming of heads shall be carried out by machine by cold forming in such a way to preserve the
specified material properties and to produce a regular finish.
 Dished Ends type is Torispherical (refer attached DWG no. B2020-101-500-001_sht.3 of 5)
 Material will be free issue from ARC Energy with MTC.
 Dished Ends designed for only internal pressure.
 Dished Ends layout is to check for centerline, height, and other dimensions as per drawing.
 Dished Ends should be seamless construction without center hole.
 Thickness specified are minimum, after forming and fabrication.
 UG-79 (d) shall be complied
(2) The reduced weld thickness, at any point, shall not be less than the design thickness of the
component.
(3) The reduction in thickness shall not exceed 1/32 in. (1 mm) or 10% of the nominal thickness of
the adjoining surface, whichever is less.
 The preparation of edges to be welded shall be done by machining, chipping, grinding, cold
shearing, Oxy-acetylene flame cutting or a combination of these.
 Chipping shall be followed by grinding to a smooth and regular finish.
 Oxy-acetylene flame cutting done in any circumstances shall be followed by machining or grinding
to eliminate any discoloration of material affected.
 Tolerance as per UG-81. Vendor need to submit their documents before manufacturing.
 Vendor need to confirm the thickness reduction percentage on the dished ends forming.

Copyright© Arc Energy Industries Page 1 of


2
ARC ENERGY INDUSTRIES
St No.114, Section N Block 10, Lot 6.
Jubail, Saudi Arabia. 35729.

TECHNICAL DELIVERY CONDITION


Form No.: QM-F-34 Rev. No: 00 Effective Date: 9/27/2020
Name of Material : Dished End Forming Client : For Demonstration
Tag No. : 001 Job No : ARC – ASNB – 1
Document No. : B2020 – TDC – DEF – 005 Doc. Rev. No : 00

 Vendor need to confirm the blank diameter.


 UG-79 (c) When the vessel shell section, heads, or other pressure boundary parts are cold formed
by other than the manufacturer of the vessel, the required certification for the part shall indicate
whether or not the part has been heat treated (see UCS-79, UHA-44, UNF-79, and UHT-79).

4. INSPECTION AND TEST

The ARCEI shall be responsible for performing all the inspection and visual inspection and testing required
as per this specification.

 The stages of inspection shall be as per ASME.


 Visual inspection to be carried out with customer representative.
 Magnetic particle / Dye penetration examination shall be carried out on the outside and inside
surface including edges of heads in knuckle zone, after forming for detection of cracks.

5. PACKING

Larger diameter equipment of small thickness shall be provided with an adequate number of struts
positioned inside the equipment to prevent ovality effect while being handled.
These struts shall not be removed until the equipment’s is placed in position at job.
Edge preparation to be protect from the physical damage.
Ensure the wooden blank for the dished ends bottom side for safe transportation.

6. SHIPEMENT

All dispatches of equipment shall be done in accordance with the relevant terms of the purchase order.

Rev No. Description Prepared Approved Date


REVISION STATUS

Prepared By: Approved By: Accepted By:


Details:
(Design Engineer) (Engineering Manager) (AI)
Name: M. Azarudeen R. Prabhakaran

Signature:

Date: 27.09.2020 27.09.2020

Copyright© Arc Energy Industries Page 2 of