June 2008
3 If yes, check the tag number, no off for each tag no per
boilers, as per bearing schedule
4 Is the offer of bearing inline with the specification sheet i.e
Hor. and vert. Load and horizontal movements, ?
5 Is contract number, vendor’s drawing no, with revision no.
mentioned in vendor’s drawing?
6 Is the bearing drawings inline with bearing schedule and
GA drawings?
7 Is the bearing drawings mention maintained top and bottom
plate dimention and total thickness as per schedule?
8 Is the top plate and bottom plate thickness of bearing
suitable as per vertical load ?
9 Is there mentioned the installation location?
Note: Vendor drawings will be checked only after release of support system of draught
And foundation drawings, Bearing schedule and Bearing specifications .
Name : Name :