You are on page 1of 1

Format No.

Checklist for Bearing Drawings APIL-NCR-NPP-CHKL-005

June 2008

Contract / Project Name


Contract / Project No.
Boiler Type
Drawing Nos.

Sl. Checkpoints Status (Tick Remarks


No. if Confirmed)
1 Is bearing schedule completed with thermal movements in
respective direction and basic design parameter ?
2 Is the bearing offer supplied with drawings and documents?

3 If yes, check the tag number, no off for each tag no per
boilers, as per bearing schedule
4 Is the offer of bearing inline with the specification sheet i.e
Hor. and vert. Load and horizontal movements, ?
5 Is contract number, vendor’s drawing no, with revision no.
mentioned in vendor’s drawing?
6 Is the bearing drawings inline with bearing schedule and
GA drawings?
7 Is the bearing drawings mention maintained top and bottom
plate dimention and total thickness as per schedule?
8 Is the top plate and bottom plate thickness of bearing
suitable as per vertical load ?
9 Is there mentioned the installation location?

10 Is the bearing be easily placed in the support location?

11 Is the bearing ordered along with fasteners?

12 Is the co-efficient of bearing is very less? And what is that


value?
13 Are the stoppers included with the bearing ?

14 Have you check the bearing materials and fixing


mechanism?

Note: Vendor drawings will be checked only after release of support system of draught
And foundation drawings, Bearing schedule and Bearing specifications .

Checked by Approved by Date: Sh. 1 of 1


Signature : Signature :

Name : Name :