You are on page 1of 2

DESIGN REVIEW STATUS

Client: BAKER HUGHES Date: Jan 8th,2024


Consultant: LEMASTERS ARABIA Project No.: CP023-006
Contractor: WESCON Discpline Architectural

BAKER HUGHES OIL FIELD SERVICESAND EQUIPMENT REGIONAL HUB


SPARK, EASTER REGION , SAUDI ARABIA

Submittal Completeness
Completed Not Completed
If not, Specify
1- Drawings Does not show the relation between the building and the surrounding
2- Missing drawings for all stairs/ramps and elevators
3- Finishing Schedule is not available in most of the drawings
4-Wall sections shall be provided.
5- Miscellaneous enlarged details for all architectural components
6- Project Specifications
7- Materials data sheets
8- Bill off Quantities

Compliance With Applicable Codes and Standards


SBC
MODON
SPARK
Life and Safety
Others
If Others, Specify

Eventhough the package is in compliance with applicable codes and standards, please refere to attached comments for some areas of concerns
Design Drawings Compatibility
Compatible Not Compatible
If not, Specify

Refere to attached comments for some areas of mismatching between the drawings

Compliance of Life Safety Requirements


Complied Not Complied
If not, Specify

Eventhough the package is in compliance with applicable Life Safety standards, please refere to attached comments for some areas of concerns

Cost Effectiveness
Optimized Design Cost Can be Reduced
If Cost Can be Reduced, Specify
1- Use the steel fiber indutrial concrete floor for all buildings by which the 150mm thick screed and epoxy paint above the flooring can be
eleminated.
2- Change the steel framing systems for all small span and single floor building to a concrete system
3- Convert all double layer cavity insulated CMU external walls of 300mm THK to 200mm THK pre insulated units