You are on page 1of 2

COMPANY 2616-ENG (03/99)

SAUDI ARABIAN OIL COMPANY


3. CONTRACTOR shall provide lean concrete under foundations
and grade beams.

4. CONTRACTOR shall construct foundations, grade beams, slab


on grade, steps, reinforced cement concrete frames comprising
of columns and beams, roof slab, pump foundations and parapet
as shown on project drawing.

5. CONTRACTOR shall provide welded wire fabric in grade slab as


shown on project drawings.

6. CONTRACTOR shall provide isolation joints, construction joints


and control joints as shown on the project drawings.

7. CONTRACTOR shall provide protective coating APCS-10 on


concrete surfaces below grade.

8. CONTRACTOR shall provide 3 TONS ELECTRIC OVERHEAD


CRANE and supporting element as shown on the project
drawing # HA176681-001 & 002

9. CONTRACTOR shall provide concrete lintel beams and


canopies for opening in CMU wall as shown on Architectural
drawings.

C. PARKING SHED

DISCIPLINE
ENGINEER
ALL DISCIPLINE 1. CONTRACTOR shall excavate to required depth to construct
DATE:
05/03/18
foundations and shall compact the grade as shown on the
PROJECT
ENGINEER project drawings.
MOHAMED BEKHIET

DATE:
06/03/18 2. CONTRACTOR shall provide lean concrete under foundations.
CERTIFIED
Rabee E. Zakaria

06/03/18
3. CONTRACTOR shall construct foundations and pedestal as
DATE: shown on project drawing.
CONSTRUCTION
AGENCY
ABDULRAOUF
A.GHAZWI 4. CONTRACTOR shall provide protective coating APCS-10 on
DATE:
06/03/18
concrete surfaces below grade.
OPERATIONS
SULIMAN M.
KHAYYAT 5. CONTRACTOR shall supply and install parking shed through an
06/03/18
DATE: approved vendor and shall construct parking shed as per
detailed provided by vendor. CONTRACTOR to coordinate with
approved final parking shed vendor drawings for anchor bolt
locations and details and keep the embedded items in place
before casting of concrete.

6. CONTRACTOR to prepare shop drawing showing anchor bolt


locations & details based on vendor drawings and shall be
approved by COMPANY prior to construction.

CONSTRUCTION SCOPE OF WORK- PRIVATE SCHOOLS DWG.TYPE PLANT NO. INDEX DRAWING NO. SHT. NO. REV. NO.

PACKAGE 3 - INFRASTRUCTURE AND SITE DEVELOPMENT DOC


A18 A HE-176328 16
SOUTH DHAHRAN HOME OWNERSHIP AJYAL INC I OF 00
DHAHRAN SAUDI ARABIA JO/EWO 28-00014-0005 40
EDSD/2616-0399.doc
COMPANY 2616-ENG (03/99)

SAUDI ARABIAN OIL COMPANY


7. CONTRACTOR shall verify parking shed foundation design as
per support reaction furnished by parking shed vendor & shall be
approved by COMPANY prior to construction.

D. LIGHTING POLES

1. CONTRACTOR shall excavate to required depth to construct


foundations and shall compact the grade as shown on the
project drawings.

2. CONTRACTOR shall provide lean concrete under foundations.

3. CONTRACTOR shall construct foundations and pedestal as


shown on project drawing.

4. CONTRACTOR shall provide protective coating APCS-10 on


concrete surfaces below grade.

5. CONTRACTOR shall coordinate with lighting pole vendor and


install lighting poles as per detailed provided by vendor.
CONTRACTOR to coordinate with approved final lighting pole
vendor drawings for anchor bolt locations and details and keep
the embedded items in place before casting of concrete.

DISCIPLINE
ENGINEER
6. CONTRACTOR to prepare shop drawing showing anchor bolt
ALL DISCIPLINE locations & details based on vendor drawings and shall be
DATE:
05/03/18
approved by COMPANY prior to construction.
PROJECT
ENGINEER
MOHAMED BEKHIET 7. CONTRACTOR shall verify lighting pole foundation design as
DATE:
06/03/18 per support reaction furnished by vendor & shall be approved by
CERTIFIED COMPANY prior to construction.
Rabee E. Zakaria

06/03/18
DATE:
CONSTRUCTION
AGENCY E. FENCE FOR SOCCER FIELD
ABDULRAOUF
A.GHAZWI
06/03/18
DATE:
OPERATIONS
SULIMAN M.
1. CONTRACTOR shall excavate to required depth to construct
KHAYYAT foundations and shall compact the grade as shown on the
06/03/18
DATE: project drawings.

2. CONTRACTOR shall provide lean concrete under foundations


and grade beams.

3. CONTRACTOR shall construct foundations, grade beams and


coping beam as shown on project drawing.

4. CONTRACTOR shall provide expansion joints as shown on the

CONSTRUCTION SCOPE OF WORK- PRIVATE SCHOOLS DWG.TYPE PLANT NO. INDEX DRAWING NO. SHT. NO. REV. NO.

PACKAGE 3 - INFRASTRUCTURE AND SITE DEVELOPMENT DOC


A18 A HE-176328 17
SOUTH DHAHRAN HOME OWNERSHIP AJYAL INC I OF 00
DHAHRAN SAUDI ARABIA JO/EWO 28-00014-0005 40
EDSD/2616-0399.doc

You might also like