S. No.

Work/Activity Description TDC


1 Top Slab Casting of 1st Box Completed
2 Top Slab Casting of 2nd Box 07-01-2024
3 Top Slab Casting of 3rd Box 15-01-2024
4 Top Slab Casting of 4th Box 22-01-2024
Methodology submission of defects rectification and 08-01-2024
5 Tierod holes filling and its approval
6 Rectification/Grouting of Defects in 1st Box Wall 13-01-2024
7 Filling of Tie Rod Holes - 1st Box 14-01-2024
8 Filling of Tie Rod Holes - 2nd Box 15-01-2024
9 Filling of Tie Rod Holes - 3rd Box 19-01-2024
10 Filling of Tie Rod Holes - 4th Box
Revised TAD Submission incorporating Steel abutments 05-01-2024
11

12 TAD Approval from Railway 10-01-2024


13 RH Girder shifting to Site 10-01-2024
14 Approval for Box-Pushing Methodology 10-01-2024
Submission of all documents related to Crane (incl. 08-01-2024
15 standby) and Clearance from Safety team
16 Calibration certificate for Jack and power pack 06-01-2024
17 Pushing of 1st Box till Rly. Boundary 16-01-2024
18 Submission of DCN and Block requirement details 10-01-2024
19 PCE sanction submission for Pushing work 10-01-2024
20 Completion of RH Girder assembling for both Tracks 17-01-2024

Preperation of Level Ground for Crane and RH 18-01-2024


21 Girder/Track Positioning - Both Track
22 Availibility of Crane at Site (incl. Stand by) 18-01-2024
23 Insertion of RH Girder for UP-line (1st Block) 20-01-2024
24 Pushing of 2nd Box adjoining to the 1st Box and start of 21-01-2024
pushing into the Rly. Boundary
25 Insertion of RH Girder for DN-line (2nd Block) 22-01-2024
26 Pushing of 1st and 2nd Box upto 20m inside Rly. 30-01-2024
Boundary and pushing 3rd Box adjoining to the 2nd Box

Pushing of 1st 3-Boxes upto 30m inside Rly. Boundary 03-02-2024


27

28 Pushing of 4th Box uptill adjoining the 3rd Box 05-02-2024


Complete Pushing of all 4-Boxes for the length of 07-02-2024
29 41.155m
30 Lifting of Track (75mm to 100mm) 15-01-2024