1 Top Slab Casting of 1st Box Completed 2 Top Slab Casting of 2nd Box 07-01-2024 3 Top Slab Casting of 3rd Box 15-01-2024 4 Top Slab Casting of 4th Box 22-01-2024 Methodology submission of defects rectification and 08-01-2024 5 Tierod holes filling and its approval 6 Rectification/Grouting of Defects in 1st Box Wall 13-01-2024 7 Filling of Tie Rod Holes - 1st Box 14-01-2024 8 Filling of Tie Rod Holes - 2nd Box 15-01-2024 9 Filling of Tie Rod Holes - 3rd Box 19-01-2024 10 Filling of Tie Rod Holes - 4th Box Revised TAD Submission incorporating Steel abutments 05-01-2024 11
12 TAD Approval from Railway 10-01-2024
13 RH Girder shifting to Site 10-01-2024 14 Approval for Box-Pushing Methodology 10-01-2024 Submission of all documents related to Crane (incl. 08-01-2024 15 standby) and Clearance from Safety team 16 Calibration certificate for Jack and power pack 06-01-2024 17 Pushing of 1st Box till Rly. Boundary 16-01-2024 18 Submission of DCN and Block requirement details 10-01-2024 19 PCE sanction submission for Pushing work 10-01-2024 20 Completion of RH Girder assembling for both Tracks 17-01-2024
Preperation of Level Ground for Crane and RH 18-01-2024
21 Girder/Track Positioning - Both Track 22 Availibility of Crane at Site (incl. Stand by) 18-01-2024 23 Insertion of RH Girder for UP-line (1st Block) 20-01-2024 24 Pushing of 2nd Box adjoining to the 1st Box and start of 21-01-2024 pushing into the Rly. Boundary 25 Insertion of RH Girder for DN-line (2nd Block) 22-01-2024 26 Pushing of 1st and 2nd Box upto 20m inside Rly. 30-01-2024 Boundary and pushing 3rd Box adjoining to the 2nd Box
Pushing of 1st 3-Boxes upto 30m inside Rly. Boundary 03-02-2024
27
28 Pushing of 4th Box uptill adjoining the 3rd Box 05-02-2024
Complete Pushing of all 4-Boxes for the length of 07-02-2024 29 41.155m 30 Lifting of Track (75mm to 100mm) 15-01-2024