Professional Documents
Culture Documents
1 Provisional Sum
Procument Item Details
SL.
Item Description Unit Quantity Unit Rate(NPR) Amount(NPR)
No
1 Third party Insurance, Insurance of the work and PS 1.0 2052664.42 2,052,664.42
Insurance against accident of the workmen for
Contractors all Risk as per conditions of the contract.
Payment will made as per submitted receipt but limited
to maximum amount in this item.
2 Execution of tests of construction materials as per PS 1.0 91229.53 91,229.53
specification and when required as per instruction and
submission of the test Reports.
3 As built drawing preparation and submission after the PS 1.0 228073.82 228,073.82
completion of project as per contract SCC.
4 Commission for performance bond for all complete PS 1.0 228073.82 228,073.82
works with submission of bank receipt.
5 Other miscellaneous works (Environment related, PS 1.0 3432107.38 3,432,107.38
electric pole related, access road related, Local
footbridge, dismantle of old structures, existing
tubewells etc. with tree and shrubs cuttings, social
concern related and any other)
6 Combine Construction Survey before the execution of PS 1.0 1000000.0 1,000,000.00
work and submission of Report & Construction
Drawings as per instruction including Supplying of
Surveying equipments
2 Construction work
2.1 Works for complete or part construction and civil engineering work