Professional Documents
Culture Documents
Procedure For Change Order, Claim and Risk Management
Procedure For Change Order, Claim and Risk Management
no : 4G79371-Q0004-Y021-D
Status : Final
EM TS 5 AE Issue : 12/2014
Issued By EM TS 5 AE QM
PM QM Process Sales SO
Process Area
Tendering Procurement D&E DM Civil
Mandatory Clause M1 M2 NA R
Prepared by Haris Jafri Process & Resource Sgd Haris Jafri 22- Dec-2014
Manager
U:\B_QA-QC\C_ Procedures\C.19- Change, Claim & Risk Management\C.19.2-Procedures & Reference\Procedure for
Change claim and Risk Management.docx
INDEX PAGE
1. PURPOSE.............................................................................................................................4
2. SCOPE.................................................................................................................................4
3. RESPONSIBILITIES ................................................................................................................4
4. TERMS & ABBREVIATIONS:...................................................................................................4
5. PROCEDURE ........................................................................................................................4
5.1 DEFINITIONS: .......................................................................................................... 5
5.2 GENERAL:................................................................................................................ 6
5.3 ESCALATION ........................................................................................................... 7
5.4 CHANGE (ADDITIONAL) ORDERS PROCESS ............................................................... 7
5.5 CLAIMS ................................................................................................................... 8
5.6 PROJECT RISK MANAGEMENT ................................................................................ 10
5.7 NON CONFORMANCE COST(NCC) ......................................................................... 12
5.8 COST REDUCTION.................................................................................................. 12
5.9 COST TRANSFERS .................................................................................................. 12
5.10 PERFORMANCE EVALUATION AND ANALYSIS ..................................................... 13
6. REFERENCE DOCUMENT & RECORDS .................................................................................13
7. REVISION AND RETENTION PERIOD OF RECORDS ...............................................................13
8. ATTACHEMENT .................................................................................................................13
U:\B_QA-QC\C_ Procedures\C.19- Change, Claim & Risk Management\C.19.2-Procedures & Reference\Procedure for
Change claim and Risk Management.docx
DIRECTORY OF ABBREVIATIONS
M S
U:\B_QA-QC\C_ Procedures\C.19- Change, Claim & Risk Management\C.19.2-Procedures & Reference\Procedure for
Change claim and Risk Management.docx
1. PURPOSE
The purpose of this procedure is to systematically manage the change (additional) orders, claims with
client / suppliers, risks and opportunities internal cost transfers and Non conformance costs.
2. SCOPE
This procedure applies to all the contracts executed by Siemens LLC EM TS and the organisations
governed by EM TS business in UAE.
3. RESPONSIBILITIES
Responsibility of implementing this procedure lies with
Head of Projects
Head of Projects (Finance)
Project Managers
Contract Administrators (for Projects Category B and above)
Commercial Project Managers.
5. PROCEDURE
Change management process consists of the following topics:-
Change (Additional) orders,
Claims with client / suppliers,
Risks and Opportunities,
Non conformance costs.
Cost reduction
Cost transfers.
U:\B_QA-QC\C_ Procedures\C.19- Change, Claim & Risk Management\C.19.2-Procedures & Reference\Procedure for
Change claim and Risk Management.docx
5.1 DEFINITIONS:
5.1.2 Claims:
Claims (relating to financial, scheduling and/or supply/ services issues) are asserted by a
contracting party if
Other contracting party fails to fulfil its contractual obligations
Changes to the framework contract conditions has occurred or perceived misinterpretation of
contract conditions by the other party.
Claims asserted by us against customers, project partners or suppliers are referred to as outgoing
claims or own claims.
Claims asserted by customers, project partners or suppliers against us are referred to as incoming
claims or third party claims.
5.1.6 Opportunities
An opportunity refers to the possibility of taking action to improve the project result at any time
during the overall project lifecycle.
U:\B_QA-QC\C_ Procedures\C.19- Change, Claim & Risk Management\C.19.2-Procedures & Reference\Procedure for
Change claim and Risk Management.docx
5.2 GENERAL:
A synopsis of the customer contract shall be prepared consequent to contract award phase.
The entire project team shall be familiarized with the relevant contract conditions, e.g. by means
of the contract synopsis.
A Change management issues are to be documented, continuously updated and kept on the
project server. All projects shall use PMTC+ for Claims, Risk, Opportunity, NCC and Change orders.
The change management topics shall be reviewed during the monthly internal progress review
meetings.
U:\B_QA-QC\C_ Procedures\C.19- Change, Claim & Risk Management\C.19.2-Procedures & Reference\Procedure for
Change claim and Risk Management.docx
5.3 ESCALATION
Escalations related to change management shall be in line with the “Procedure for Project Specific
Escalation path – Doc No – 4G79371-Q0004-Y006”
Upon receipt of the additional order quote request on the existing contract from the customer, Project
Manager shall update the variation order form.
Quote shall be prepared considering the price, timeline and other contractual requirements. For the
quote value above AED 1,000,000 Power calc tool shall be used for calculation purpose, for valuation
of Change Orders of aggregate value up to MAED 1.00; Offer/Order Calculation Sheet [Doc. No.
4G79371-Q0010-Y137] shall be adopted.
U:\B_QA-QC\C_ Procedures\C.19- Change, Claim & Risk Management\C.19.2-Procedures & Reference\Procedure for
Change claim and Risk Management.docx
Cross verification of the prices shall be done with sales department to ensure all the elements are
considered with correct price.
Both the calculation and the quotation shall be signed in accordance with the signature mandate.
5.5 CLAIMS
A claim triangle consists of the three core elements of successful claims management: the facts, the
basis of the claim and enforcement.
Claims can only be successfully enforced if the facts have been adequately clarified and the verifiably
documented.
Claims are more likely to be successful if the basis of the claim has been agreed by contract or is
defined in law.
Even well prepared and well founded claims – for which an appropriate basis exists – must be
successfully enforced.
A distinction must be drawn between
Preventive claims management
Influence the terms and conditions of the contract and observation of the project environment
during the fulfilment of the contract with the aim of securing an advantageous position in the
event of possible future claims
Subsequently the actual claim has to be prepared by using the summary Sheet. To maintain a
consistent approach towards the client throughout the projects and unless rates are mentioned in
the contract, the standard rates given in the Claim List shall be used. If applicable, a register has to
be drawn up under which citied or supporting documents such as reports, comment sheets, time
schedules and such like shall be attached.
In general, the claim amount shall be as much as possible/reasonably justifiable and may include
indirect costs. The official claim has to be signed as per the signatory mandate policy. In complex
cases Power Calc shall be used.
U:\B_QA-QC\C_ Procedures\C.19- Change, Claim & Risk Management\C.19.2-Procedures & Reference\Procedure for
Change claim and Risk Management.docx
Customer / Project specific claim strategy shall be defined in the Siemens Project Management
Plan (PMP).
As and when deemed appropriate, assistance of Legal Services shall be availed for appraisal of
specific / settlement Agreement(s) with Customer.
U:\B_QA-QC\C_ Procedures\C.19- Change, Claim & Risk Management\C.19.2-Procedures & Reference\Procedure for
Change claim and Risk Management.docx
Penalties shall be a deterrent and shall be used skillfully as a tool to promote supplier
performance. This is intended to avoid Supplier provisioning the claims as costs / risks in the future
projects.
In accordance to stipulated contract conditions, sufficient / reasonable notice shall be given to the
suppliers for improvement in performance- viz delivery of the equipment or services.
As and when deemed appropriate, assistance of Legal Services shall be availed for appraisal of
specific/settlement Agreement(s) with Supplier.
The penalty levels shall be increased for repeated offenders if the price offered for the project is
attractive. This claim strategy stands common for all the suppliers.
U:\B_QA-QC\C_ Procedures\C.19- Change, Claim & Risk Management\C.19.2-Procedures & Reference\Procedure for
Change claim and Risk Management.docx
Risk management is an ongoing process which consists of the elements: risk identification, risk
evaluation, risk influencing and risk controlling.
Outcome of the risk management process must be regularly updated during the project
implementation phase as follows:
Evaluation of continuing risks and opportunities of the effectiveness of planned measures.
Addition and treatment of newly identified risks.
Minimising the costs of new risks by means of suitable measures.
Updated risk contingencies have to be included in the OEC in the WBS elements provided for risk
contingencies.
Updating risk and opportunities shall be done in PMTC+ tool for all projects.
The result of “Risk evaluation before measure” is calculated through Risk Backup Calculation (Format.
No. 4G79371-Q0010-Y251).
At the project closure there are no more general project risks. The corresponding risk contingencies
must therefore be zero. The updated risk contingencies for warranty and contractual / default
penalties have to be transferred into planned cost items for corresponding provisions via risk change
notifications.
Non conformance cost (NCC) as a result of risk management shall be reported in PMTC tool. Refer the
“Procedure for Non Conformance Management – Doc No. 4G79731-Q0004-Y022” for the details NCC
from risk management.
U:\B_QA-QC\C_ Procedures\C.19- Change, Claim & Risk Management\C.19.2-Procedures & Reference\Procedure for
Change claim and Risk Management.docx
Planned cost reductions can only be integrated in project planning using a cost reduction change
notification if a specific and demonstrable implementation concept exists or, in the case of purchasing
success.
Cost reductions arising from procurements and occurring after the contract has been concluded with
the supplier (due contractual penalties, reductions owing to a failure to fulfil the contract in its
entirety) must be treated as claims even if they can be directly clarified. There may also be included
any cost increases incurred by us.
The planned project costs of the relevant WBS elements must be increased, reduced or reallocate
using individual notifications. The change in the planned costs in the collective notification must be
zero.
All changes shall be recorded in the format (4G79371-Q0010-Y189) and duly signed mandatory by
PM, CPM, Head of BA and General Manager on monthly basis and becomes a part of monthly project
review meeting. Signature of Head of Projects and Head of Projects Finance is optional.
U:\B_QA-QC\C_ Procedures\C.19- Change, Claim & Risk Management\C.19.2-Procedures & Reference\Procedure for
Change claim and Risk Management.docx
At the end of project, claims list, variation order and Risk & opportunity list shall be evaluated to find
the success rate. Means the percentage of claims accepted / rejected, Percentage of variation orders
w.r.t. the initial sales order, percentage of risks mitigated / materialised.
Summary shall be prepared by Commercial Project Manager with the details of measures taken for
success and reasons failure of claims, variations, risk and opportunity. This summary shall be part of
lessons learned and communicated to other projects in the organisation.
All the documents of the projects including the drawings and correspondence stored in the project
folder shall be retained for 10 years from the date of PAC. System / Process related records stored in the
relevant folders shall be retained for 5 years from the date of filing.
8. ATTACHEMENT
Change Management record (4G79371-Q0010-Y189)
Offer/Order Calculation Sheet (4G79371-Q0010-Y137)
Risk Backup calculation sheet (4G79371-Q0010-Y251)
U:\B_QA-QC\C_ Procedures\C.19- Change, Claim & Risk Management\C.19.2-Procedures & Reference\Procedure for
Change claim and Risk Management.docx