Professional Documents
Culture Documents
SUBMITTED TO
ENGR. DR. OLANIYAN O.S
FEBRUARY 2023
1
LIST OF GROUP 1 MEMBERS
2
CERTIFICATION
Signature/Date Supervisor-in-charge
Head of Department
3
DEDICATION
This technical report is dedicated to the Almighty God for His gracious support
and wisdom he has bestowed to us and the ability to pass through this learning
castle.
4
ACKNOWLEDGMENT
Special thanks to God Almighty for His sustaining grace and ever increasing
strength. Many thanks to the effort of the lecturer in charge of the course Dr. O.S.
Olaniyan.
5
TABLE OF CONTENT
1.0 INTRODUCTION
8.0 DISCUSSION
9.0 CONCLUSION
10.0 REFERENCE
6
THEODOLITE TRAVERSE
1.0 INTRODUCTION
A traverse consists a series of straight line of known length related one another by
known angles between the line. The points defining the ends of the traverse lines
are called traverse stations.
There are two(2) types of traverse, namely the open traverse and the
closed traverse [Figure 1.1]. An open traverse originates at a point of known
positions and terminates at a point of unknown position, where as a closed traverse
originates and terminates at the same points and wewere using an closed traverse in
this survey. For establishing control points, a closed traverse is preferred since it is
provides different checked for included angles, deflection angles and bearing for
adjusting the traverse. That why we use this method in this project. When an open
traverse is used the work should be checked by providing cut off lines and by
making observations on some prominent point visible forms as many stations as
possible.
Traversing surveys is very fundamental and has become one of the most
common methods in geomatic engineering work such as:- general purpose angle
measurement, provision of control surveys, contour and detail mapping and setting
out and construction work.
7
Figure 1.1 : Open travers & Closed traverse
8
2.0 THEODOLITE PRINCIPLES AND APPLICATIONS
A theodolite is an instrument which is capable of measuring angles to the nearest
whole second [Figure 2.1]. This can be done for both vertical and horizontal
angles. Vertical angles are required for the calculation of elevation of points for
example the reduction of slope distance to the horizontal.
The value of the angle observed however will be the same. Electronic
theodolites are more versatile than the optical type. Useful features in the form of
software can be added to an electronic theodolite. Thus modern instruments can be
used in a variety of surveying situations.
9
3.0 CONSTRUCTION OF A THEODOLITE
All theodolites have the same common lgfeatures [Figure 3.1] which can be
described as follows:
1. Tribrach
Allows the instrument to be connected to the top of a tripod and also allows the
instrument to be levelled with respect to a plate blubble.
The lower plate that carries the horizontal circle. In most instruments it is made of
glass with the graduations from 0ºto 360ºphotographicallyetched around the edge.
(ii) The upper plate that carries the horizontal circle indexing device and fits
concentric with the lower plate. Attached to the upper plate is the plate bubble.
When centered, the plate bubble ensures that the instrument axis is vertical. In
modern electronic theodolites, the spirit bubble has been replaced with an
electronic one. This electronic means of levelling has made initial levelling of
the instrument a less time consuming task.
The vertical circle is similar to the horizontal circle but is fixed to the telescope.
Thus it revolves with the rotation of the telescope. This compartment has the
vertical circle index. Most modern theodolites employ an automatic compensator
but some of the more elderly instruments use an altitude bubble.
This clamp ensures that when engaged the horizontal circle is fixed. The slow
motion screws allow for the movement of the instrument around the horizontal
axis. There is also a similar slow motion screw and plate clamp for the vertical
circle.
10
5. Optical Plummet
Built in the base of the instrument to allow the instrument to be precisely centered
over the station. The line of sight through the optical plummet is exactly the same
as the vertical axis of the theodolite.
11
4.0 TEMPORARY ADJUSTMENTS OF THEODOLITE
The temporary adjustments are steps that must be carried out every time at
theodolite is used. It is a procedure of setting up a theodolite that involves the
following process:
a) centering;
b) leveling; and
c) removing parallax.
1. Start with a plumbob to get it approximately right above the survey station
[Figure 4.1].
2. Using the foot screws, move the optical plummet cross hairs on to the survey
station.
3. Roughly level the instrument using the legs of the tripod – the theodolite should
stay almost on target.
4. Level with foot screws. Move instrument above target; repeat level and move
until done.
5. If not, move it back one-half of the movement from the centre and re-adjust for a
further 90º turn.
12
6. Repeat the whole procedure; assuming this is the correct, the bubble will stay in
a stationary position.
7. The bubble must remain in the same place in the tube during a 360ºrotation of the
instrument.
8. If the stationary position of the bubble is still off the centre, then a permanent
adjustment should be made.
Figure 4.1 : Centering the theodolite Figure 4.2 : Levelling the theodolite
13
5.0 PERMANENT ADJUSTMENTS OF THEODOLITE
These adjustments are carried out once and will not alter unless it is being roughly
handled or tampered with. There are certain basic requirements for a theodolite that
must be established particularly when using it. The basic requirements are as
follows:
The leader of the team, setting up and reads the instrument, while the 2nd
person has the important job of recording the readings on the booking sheet. The
3rd person has the task of moving and setting up the wooden stands with plumbob
as the traverse progresses. There are several steps which should be followed that
will lead to a smooth traverse [Figure 6.1].
1. Three picket(station) were established at the proposed site.(peg 1, peg 2 & peg
3).
2. The theodolite was plumbed over peg 2 and accurately leveled. Wooden stands
were plumbed over peg 1&3.
3. Level and center the instrument.
14
4. Set the theodolite to read zero.
13. The theodolite was moved to peg 3. Wooden stands were plumbed over peg 1
and 2. Peg2 was sighted on face left with theodolite set to the reading taken from
step 10.
14. Peg 1 was sighted and the horizontal angle was taken. The instrument was set to
face right and peg 1 was sighted again. Then peg 2 was sighted and the reading
was taken.
15. Step 13-14 was repeated on peg 1.All readings were observed and recorded.
15
7.0 TRAVERSING ERRORS
Traversing errors normally falls into three categories, i.e. centering, angular and
distance. By taking precautions during the field work, it is possible to reduce their
effect.
1. Centering
It is important to ensure that the theodolite instrument and targets are centered
correctly over each survey station. Remember that angles and distances may be
required from or to a known station. This will not be the case if the theodolite or
targets are not centered correctly.
2. Angles
When clamping the instrument, apply light clamp to the vertical and horizontal
locks. Hard clamping can affect the pointing of the instrument and is not necessary.
Failure to eliminate parallax and poor focusing can affect accurate pointing.
Always keep the target in the center of the field of view. All movement of the
theodolite should be kept as smooth as possible and all movement around the
instrument should be kept to a minimum.
3. Distances
When recording these, all distances should be obtained to 3 decimal places and
three readings should be taken and the mean calculated.
There is a possibility that that some of the errors outlined below will occur
from time to time, so be aware of them. Don’ t rush and hopefully you will not
forget to record any information which is required.
a) Turning the wrong screw.
16
8.0 DISCUSSION
Before doing the survey, there are a few things that must be considered. There are:
All screw must be parallel to the centre line
When survey was taking on, there are several things that must be clearly taking
place which are:
The cross hair must be clearly seen by observer.
The parallax error might be occur when reading was taken.Therefore the observer
must be the same person and very sure that the reading taken was correctly.
During the changing of left face and right face, be sure tahat the position of tripod
did not change.
Distance between one point to another was taken correctly.
After field wprk was complete, proceed with analyzing data. The correction
between latitude and departure must be placed with correct sign and value.
A closed traverse enables a check by plotting or computation with a gap called the
linear misclosure.
17
9.0 CONCLUSION
Basically there are two types of modern theodolite i.e. the optical
theodolite and electronic digital theodolite. But both have the same common
features in terms of their construction.
18
10.0 REFERENCE
http://www.southgeosystems.com/index.html
http://www.geomaticsurveys.systems.com
http://www.scribd.com/doc/38971159/Traverse-Survey
http://www.ce.memphis.edu/1112/notes/traverse/Surveying_traverse
19