PARTIAL OUTPUT FOR QUANTITY SURVEYING (CONSTRUCTION ESTIMATE)


MULTI-PURPOSE BUILDING / FACILITIES TO SUPPORT SOCIAL SERVICES –
CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY RADIWAN, IVANA,
BATANES
(9.0 X 12.0 M 2-STOREY BUILDING)

ABIERA, Jerlyn B.
Bachelor of Science in Civil Engineering 4A
Republic of the Philippines
CAMARINES NORTE STATE COLLEGE
F. Pimentel Avenue, Brgy. 2, Daet, Camarines Norte – 4600, Philippines

COLLEGE OF ENGINEERING
A. EARTHWORKS

 EXCAVATION
 BACKFILLING AND COMPACTION
 GRADING AND COMPACTION
 GRAVEL BEDDING
 SOIL POISONING

EXCAVATION

FOOTING

L = 1.9 + 0.25 + 0.25 = 2.4 m

W = 1.9 + 0.25 + 0.25 = 2.4 m

H = 1.5 + 0.1 (Gravel Bedding) = 1.6 m

V-F1 = 9.216 x 12 sets m3

TOTAL VOLUME OF FOOTING = 110.592 m3

WALL FOOTING

WF-1 DETAILS:

Width = 0.5 + 0.1 + 0.1 = 0.7 m


Republic of the Philippines
CAMARINES NORTE STATE COLLEGE
F. Pimentel Avenue, Brgy. 2, Daet, Camarines Norte – 4600, Philippines

COLLEGE OF ENGINEERING
Thickness = 0.15 m

Depth from NGL = 0.6 + 0.1 = 0.7 m

Total Length = 8.6 m

V-WF1 = 4.214 m3

WF-2 DETAILS:

Width = 0.5 + 0.1 + 0.1 = 0.7 m

Thickness = 0.15 m

Depth from NGL = 0.6 + 0.1 = 0.7 m

Length = 21.625 m

V-WF2 = 10.59625 m3

TOTAL VOLUME OF WALL FOOTING = 14.81025 m3

FOOTING TIE BEAM DETAILS:

Width = 0.2 + 0.25 + 0.26 = 0.7 m

Depth = 0.3 + 0.1 = 0.4 m

Length = 5.2 m + 5.2 m + 6.3 m = 16.7 M

TOTAL VOLUME OF FOOTING TIE BEAM = 4.676 m3

The total volume of excavated soil is 130.07825 m3.


Republic of the Philippines
CAMARINES NORTE STATE COLLEGE
F. Pimentel Avenue, Brgy. 2, Daet, Camarines Norte – 4600, Philippines

COLLEGE OF ENGINEERING
BACKFILLING AND COMPACTION

TOTAL EXCESS VOLUME = VOLUME OF CONCRETE FOOTING + VOL. OF WALL FOOTING +


VOLUME OF FOOTING TIE BEAM + VOLUME OF GRAVEL = 15.162 m3 + 2.266875 m3 + 2.226 m3 =
19.654875 + 14.7192 = 34.374075 m3

ELEVATIONS:

S.O.G = 100 mm

T&B (Level 0) = 400 mm (Fill with a height of 200 mm)

Porch = 400 mm (Fill with a height of 200 mm)

Rest of the Floor Area = 450 mm (Fill with a height of 250 mm)

Vfill = 1.7 x 2.15 x 0.2 = 0.731 m3

Vfill = 4.5 x 2 x 0.2 = 1.8 m3

Vfill = (108 - 3.655 - 9) x 0.25 = 23.83625 m3

TOTAL VOLUME OF FILL = 26.36725 m3

Since the total volume of excess soil (34.374075 m3) is greater than the total volume of fill
(26.36725 m3), there is no need to add more filling materials.

GRADING AND COMPACTION

1. FOOTING SUB GRADE

AREA F-1 = 2.4 x 2.4 x 12 sets = 69.12 m2

2. WALL FOOTING SUB-GRADE

AREA WF1 = 8.6 m x 0.6 = 5.16 m2


AREA WF2 = 21.625 x 0.6 = 12.975 m2

3. FOOTING TIE BEAM SUB GRADE

AREA FTB = 16.7 x 0.7 = 11.69 m2

4. SLAB ON GRADE

AREA OF SLAB = 108 m2

The total area to be compacted is 206.945 m2.


GRAVEL BEDDING
Republic of the Philippines
CAMARINES NORTE STATE COLLEGE
F. Pimentel Avenue, Brgy. 2, Daet, Camarines Norte – 4600, Philippines

COLLEGE OF ENGINEERING

Aggregates (gravel) used is approximately 1 inch in diameter.

FOOTING
F-1; V = 2.4 x 2.4 x 0.13 x 12 sets = 8.9856 m3

WALL FOOTING (MEASURE FACE TO FACE OF COLUMN)

WF-1; V = 8.6 x 0.6 x 0.13 = 0.6708 m3


WF-2; V = 21.625 x 0.6 x 0.13 = 1.68675 m3

FOOTING TIE BEAM


L = 37.1 m
FTB; V = 37.1 x 0.7 x 0.13 = 3.3761 m3

SLAB ON GRADE
S.O.G; V = 9 x 12 x 0.13 = 14.04 m3

TOTAL VOLUME OF GRAVEL G-1


V = VF-1 + VWF-1 + VWF-2 + VFTB + S.O.G = 28. 75925 m3
The total volume of gravel G-1 to be used is 28.7592 m3.

SOIL POISONING
AREA = 9 m x 12 m = 108 m2

SUMMARY:

EXCAVATION = 130.07825 m3

BACKFILLING AND COMPACTION = 122.071425 m3

GRADING AND COMPACTION = 206.945 m2

GRAVEL BEDDING = 28.7592 m3

SOIL POISONING = 108 m2


Republic of the Philippines
CAMARINES NORTE STATE COLLEGE
F. Pimentel Avenue, Brgy. 2, Daet, Camarines Norte – 4600, Philippines

COLLEGE OF ENGINEERING
B. STRUCTURAL WORKS

 CONCRETING
 FORMWORKS
 REBAR
 STEEL AND METAL TRUSSES

CONCRETING

F-1; V = 1.9 x 1.9 x 0.35 x 12 sets = 15.162 m3

TOTAL VOLUME = 15.162 m3

WF-1; V = 8.6 x 0.5 x 0.15 = 0.645 m3

WF-2; V = 21.625 x 0.5 x 0.15 = 1.621875 m3

TOTAL VOLUME = 2.266875 m3

FTB; V= 37.1 x 0.2 x 0.3 = 2.226 m3

TOTAL VOLUME = 2.226 m3

VOLUME OF CONCRETE

FOOTING
TOTAL # OF VOL. OF VOL. OF ¾”
LENGTH WIDTH THICKNESS NO. OF
VOLUME VOLUME CEMENT SAND GRAVEL
(m) (m) (m) SETS
(cu.m) (BAGS) (cu.m) (cu.m)
F1 1.9 1.9 0.35 1.26 12 15.16 137 7.6 15.2

WALL FOOTING
TOTAL # OF VOL. OF VOL. OF ¾”
LENGTH WIDTH THICKNESS NO. OF
VOLUME VOLUME CEMENT SAND GRAVEL
(m) (m) (m) SETS
(cu.m) (BAGS) (cu.m) (cu.m)
WF1 8.6 0.5 0.15 0.65 6 0.4 0.7
WF2 21.625 0.5 0.15 1.62 15 0.9 1.7

FOOTING TIE BEAM


TOTAL # OF VOL. OF VOL. OF ¾”
LENGTH WIDTH THICKNESS NO. OF
VOLUME VOLUME CEMENT SAND GRAVEL
(m) (m) (m) SETS
(cu.m) (BAGS) (cu.m) (cu.m)
FTB 37.1 0.2 0.3 2.23 21 1.2 2.3
Republic of the Philippines
CAMARINES NORTE STATE COLLEGE
F. Pimentel Avenue, Brgy. 2, Daet, Camarines Norte – 4600, Philippines

COLLEGE OF ENGINEERING
COLUMNS
TOTAL # OF VOL. OF VOL. OF ¾”
LENGTH WIDTH THICKNESS NO. OF
VOLUME VOLUME CEMENT SAND GRAVEL
(m) (m) (m) SETS
(cu.m) (BAGS) (cu.m) (cu.m)
L0 0.35 0.35 4.25 0.52 12 6.25 57 3.2 6.3
L1 0.35 0.35 3 0.37 12 4.41 40 2.3 4.5

BEAMS
TOTAL # OF VOL. OF VOL. OF ¾”
LENGTH WIDTH THICKNESS NO. OF
VOLUME VOLUME CEMENT SAND GRAVEL
(m) (m) (m) SETS
(cu.m) (BAGS) (cu.m) (cu.m)
2B 63.6 0.3 0.4 7.63 69 3.9 7.7
2B-2 4.05 0.2 0.3 0.24 3 0.2 0.3
STB 1.85 0.2 0.3 0.11 1 0.1 0.2
RB 63.6 0.25 0.3 4.77 43 2.4 4.8
LB-1 80 0.15 0.35 4.2 38 2.1 4.2

STIFFENER BEAM

LEVEL DESCRIPTION LT = L + L1 + L2 STIFFENER # OF SET VOLUME


BEAM (bxd)
Level 0 W1 0.5 + 0.20 +0.20 = 0.9 0.1 x 0.2 = 0.02 18 0.324
W2 0.5 + 0.20 +0.20 = 0.9 0.1 x 0.2 = 0.02 3 0.054
W3 0.5 + 0.20 +0.20 = 0.9 0.1 x 0.2 = 0.02 1 0.018
W4 0.5 + 0.20 +0.20 = 0.9 0.1 x 0.2 = 0.02 1 0.018
D1 0.9 + 0.20 +0.20 = 1.3 0.1 x 0.2 = 0.02 2 0.052
D2 0.8 + 0.20 +0.20 = 1.2 0.1 x 0.2 = 0.02 2 0.048
D3 0.7 + 0.20 +0.20 = 1.1 0.1 x 0.2 = 0.02 1 0.022
Level 1 W1 0.5 + 0.20 +0.20 = 0.9 0.1 x 0.2 = 0.02 19 0.342
W2 0.5 + 0.20 +0.20 = 0.9 0.1 x 0.2 = 0.02 1 0.018
W3 0.5 + 0.20 +0.20 = 0.9 0.1 x 0.2 = 0.02 1 0.018
D1 0.9 + 0.20 +0.20 = 1.3 0.1 x 0.2 = 0.02 1 0.026
D2 0.8 + 0.20 +0.20 = 1.2 0.1 x 0.2 = 0.02 4 0.096
D3 0.7 + 0.20 +0.20 = 1.1 0.1 x 0.2 = 0.02 1 0.022
Total Length = 13.5 m 1.058 m3

STIFFENER COLUMN
V = a x b x H x No. of Set

Level 0
a = 0.10 m
b = 0.20 m
H = 3.2 – 0.4 = 2.8 m

Level 1
a = 0.10 m
b = 0.20
H = 3 m – 0.3 m = 2.7 m
Republic of the Philippines
CAMARINES NORTE STATE COLLEGE
F. Pimentel Avenue, Brgy. 2, Daet, Camarines Norte – 4600, Philippines

COLLEGE OF ENGINEERING
STIFFENER BEAMS
L0 TOTAL # OF VOL. OF VOL. OF ¾”
LENGTH WIDTH THICKNESS NO. OF
VOLUME VOLUME CEMENT SAND GRAVEL
(m) (m) (m) SETS
(cu.m) (BAGS) (cu.m) (cu.m)
W1 0.9 0.1 0.2 0.018 7 0.126 1.134 0.063 0.126
W2 0.9 0.1 0.2 0.018 3 0.054 0.486 0.027 0.054
W3 0.9 0.1 0.2 0.018 1 0.018 0.162 0.009 0.018
W4 0.9 0.1 0.2 0.018 1 0.018 0.162 0.009 0.018
D1 1.3 0.1 0.2 0.026 2 0.052 0.468 0.026 0.052
D2 1.2 0.1 0.2 0.024 2 0.048 0.432 0.024 0.048
D3 1.1 0.1 0.2 0.022 1 0.022 0.198 0.011 0.022

STIFFENER BEAMS
L1 TOTAL # OF VOL. OF VOL. OF ¾”
LENGTH WIDTH THICKNESS NO. OF
VOLUME VOLUME CEMENT SAND GRAVEL
(m) (m) (m) SETS
(cu.m) (BAGS) (cu.m) (cu.m)
W1 0.9 0.1 0.2 0.018 5 0.09 0.81 0.045 0.09
W2 0.9 0.1 0.2 0.018 1 0.018 0.162 0.009 0.018
W3 0.9 0.1 0.2 0.018 1 0.018 0.162 0.009 0.018
D1 1.3 0.1 0.2 0.026 1 0.026 0.234 0.013 0.026
D2 1.2 0.1 0.2 0.024 4 0.096 0.864 0.048 0.096
D3 1.1 0.1 0.2 0.022 1 0.022 0.198 0.011 0.022

SUMMARY (STIFFENER BEAMS)


# OF CEMENT VOL. OF SAND VOL. OF ¾”
(BAGS) (cu.m) GRAVEL (cu.m)
WINDOWS 4 0.2 0.4
DOORS 3 0.2 0.3

STIFFENER COLUMNS
TOTAL # OF VOL. OF VOL. OF ¾”
NO. OF
a (m) b (m) HEIGHT (m) VOLUME VOLUME CEMENT SAND GRAVEL
SETS
(cu.m) (BAGS) (cu.m) (cu.m)
L0 0.15 0.3 2.8 0.126 7 0.882 7.938 0.441 0.882
L1 0.15 0.3 2.7 0.1215 4 0.486 4.374 0.243 0.486

SLAB
TOTAL # OF VOL. OF VOL. OF ¾”
LENGTH WIDTH THICKNESS NO. OF
VOLUME VOLUME CEMENT SAND GRAVEL
(m) (m) (m) SETS
(cu.m) (BAGS) (cu.m) (cu.m)
SOG 9 12 0.1 10.8 10.8 97.2 5.4 10.8

SUSPENDED SLAB
TOTAL # OF VOL. OF VOL. OF ¾”
A-1 A-2 THICKNESS NO. OF
VOLUME VOLUME CEMENT SAND GRAVEL
(sq.m) (sq.m) (m) SETS
(cu.m) (BAGS) (cu.m) (cu.m)
S1 72 18 0.12 10.8 10.8 97.2 5.4 10.8
Republic of the Philippines
CAMARINES NORTE STATE COLLEGE
F. Pimentel Avenue, Brgy. 2, Daet, Camarines Norte – 4600, Philippines

COLLEGE OF ENGINEERING
S2 18 4.94875 0.12 1.56615 1.56615 14.09535 10.96305 1.56615
S3 9 12 0.1 10.8 10.8 97.2 5.4 10.8

CONCRETE CANOPY

Area of Concrete Sunbreaker Detail = (0.5 x 0.075) + (1/2 x 0.025 x 0.50 = 0.04375 m2

TOTAL # OF
VOL. OF VOL. OF ¾”
AREA (sq.m) L VOLUME CEMENT
SAND (cu.m) GRAVEL (cu.m)
(cu.m) (BAGS)
CC1 0.04375 12 1.05 9.45 0.525 1.05
CC2 0.04375 8 0.7 6.3 0.35 0.7
CC3 0.04375 6 0.525 4.725 0.2625 0.525
CC4 0.04375 4.5 0.196875 1.771875 0.0984375 0.196875
CC5 0.04375 9 0.39375 3.54375 0.196875 0.39375
CC1 0.04375 12 1.05 9.45 0.525 1.05

STAIR-1
STAIR TOTAL # OF VOL. OF VOL. OF ¾”
RISER TREAD NO. OF STRINGER
WIDTH VOLUME CEMENT SAND GRAVEL
(m) (m) STEPS THCK.
(m) (cu.m) (BAGS) (cu.m) (cu.m)
S-1 0.2 0.25 0.93 8 0.15 0.54 5 0.27 0.54
S-2 0.2 0.25 0.93 8 0.15 0.54 5 0.27 0.54

STIFFENER COLUMNS
TOTAL # OF VOL. OF VOL. OF ¾”
LENGTH WIDTH THICKNESS NO. OF
VOLUME VOLUME CEMENT SAND GRAVEL
(m) (m) (m) SETS
(cu.m) (BAGS) (cu.m) (cu.m)
LANDING 0.675 1.85 0.12 0.14985 0.14985 2 0.074925 0.14985

STAIR-2
STAIR TOTAL # OF VOL. OF VOL. OF ¾”
RISER TREAD NO. OF STRINGER
WIDTH VOLUME CEMENT SAND GRAVEL
(m) (m) STEPS THCK.
(m) (cu.m) (BAGS) (cu.m) (cu.m)
ST 2 0.15 0.25 3.975 3 0 0.22 3 0.2 0.3
Republic of the Philippines
CAMARINES NORTE STATE COLLEGE
F. Pimentel Avenue, Brgy. 2, Daet, Camarines Norte – 4600, Philippines

COLLEGE OF ENGINEERING
FORMWORKS

Dimension of Plywood Used: 1.2 m x 2.4 m


1. FOOTING

Total Area = P x h x Number of set


P = (a x 2) + (b x 2) + 4 (0.05) = 2(a +b) + 0.2

F-1 @ 12 sets = 7.8 m x 0.35 m x 12 sets = 32.76 m2

Number of Plywood Needed = Total Area/Area of Plywood


32.76
=
( 1.2 x 2.40 )
= 12.9375 pcs. x 50% = 6.46875 pcs or 7 pcs

2. COLUMN
C-1; 0.35 m x 0.35 m @ 12 sets

LEVEL 0
a = 0.35 m
b = 0.35 m
h = hn – hn/3 = 5.15 m – 1.71667 m = 3.4333 m
A = P x h x No. of Sets = 1.6 x 3.433 x 12 sets = 65.92 m2

Number of Plywood Needed = Total Area/Area of Plywood


65.92
=
( 1.2 x 2.40 )
= 22.8889 pcs. x 50%
= 11.4444 pcs. or 12 pcs.

3. BEAM

Area = P x L: P = 2d + b + 0.1: L = 1 m

PERIMETER LENGTH AREA


P; FTB = 2(0.3) + 0.2 + 0.1 = 0.9 m Length of FTB = 42 m Area; FTB = 42 x 0.9 = 37.8 m2

P; 2B = 2(0.4) + 0.3 + 0.1 =1.2 m Length of 2B = 72 m A; 2B = 72 x 1.2 = 86.4 m2

P; 2B-2 = 2(0.3) + 0.2 + 0.1 = 0.9 m Length of 2B-2 = 4.05 m A; 2B-2 = 4.05 x 0.9 = 3.645 m2

P; STB = 2(0.3) + 0.2 + 0.1 = 0.9 m Length of STB = 2 m A; STB = 2 x 0.9 = 1.8 m2

P; RB = 2(0.3) + 0.25 + 0.1 =0.95 m Length of RB = 72 m A; RB = 72 x 0.95 = 68.4 m2

P; LB-1 = 2(0.35) + 0.15 + 0.1 = 0.95 m Length of LB-1 = 80 m A; LB-1 = 80 x 0.95 = 76 m2

Total Area = 274.045 m2


Republic of the Philippines
CAMARINES NORTE STATE COLLEGE
F. Pimentel Avenue, Brgy. 2, Daet, Camarines Norte – 4600, Philippines

COLLEGE OF ENGINEERING
Number of Plywood Needed = Total Area/Area of Plywood
274.045
=
( 1.2 x 2.40 )
= 95.15451389 pcs. x 50%
= 47.67725694 pcs. or 48 pcs.

TOTAL = 67 pcs. x 4 ft x 8 ft x ½

4. FLOOR SLAB FORMS

Area = 9 m x 12 m = 108 m
108 m
= 37.5 pcs. or 38 pcs. 4’ x 8’ phenolic board
1.2m x 2.4 m

For Roof Beam Level:


Area = 9 m x 12 m = 108 m
108 m
= 37.5 pcs. or 38 pcs. 4’ x 8’ phenolic board
1.2m x 2.4 m

SCAFFOLDINGS

1. COLUMN

L = 8.15 m x 12 sets = 97.8 m


Vertical Support = 97.8 m x 7.00 = 684.6 Bd. ft. 2” x 3” lumber
Horizontal Support = 97.8 m x 21.00 = 2053.8 Bd. ft. 2” x 2”
Republic of the Philippines
CAMARINES NORTE STATE COLLEGE
F. Pimentel Avenue, Brgy. 2, Daet, Camarines Norte – 4600, Philippines

COLLEGE OF ENGINEERING
Diagonal Braces = 97.8 x 11.70 = 1144.26 Bd. ft. 2” x 2”

2. BEAM

Length of 2B = 72 m
Vertical Support = 72 m x 6.00 = 432 Bd. ft. 2” x 3” lumber
Horizontal Support = 72 m x 4.70 = 338.4 Bd. ft. 2” x 2”

Length of 2B-2 = 4.05 m


Vertical Support = 4.05 m x 6.00 = 24.3 Bd. ft. 2” x 3” lumber
Horizontal Support = 4.05 m x 4.70 = 19.035 Bd. ft. 2” x 2”

Length of STB = 2 m
Vertical Support = 2 m x 6.00 = 12 Bd. ft. 2” x 3” lumber
Horizontal Support = 2 m x 4.70 = 9.4 Bd. ft. 2” x 2”

Length of RB = 72 m
Vertical Support = 72 m x 6.00 = 432 Bd. ft. 2” x 3” lumber
Horizontal Support = 72 m x 4.70 = 338.4 Bd. ft. 2” x 2”

Length of LB-1 = 80 m
Vertical Support = 80 m x 6.00 = 480 Bd. ft. 2” x 3” lumber
Horizontal Support = 80 m x 4.70 = 376 Bd. ft. 2” x 2”

3. CONCRETE SLAB

Area = 9 m x 12 m = 108 m
Using 2” x 3” support = 108 x 9.10 = 982.8 Bd. ft. 2” x 3” lumber

For Roof Beam Level:


Area = 9 m x 12 m = 108 m
Using 2” x 3” support = 108 x 9.10 = 982.8 Bd. ft. 2” x 3” lumber

REBAR
Republic of the Philippines
CAMARINES NORTE STATE COLLEGE
F. Pimentel Avenue, Brgy. 2, Daet, Camarines Norte – 4600, Philippines

COLLEGE OF ENGINEERING

1. FOOTING

Grade 40 Steel
Yield Strength = fy = 414 MPa
Compressive Strength = 4000 psi
75 mm – Concrete Cover
0.02 Abfy
Idb = = 316.89 mm < 0.06dbfy = 397.44 mm
√f ' c
Thus, governing value is 397.44 mm.
2
Ab =
πD = 201.062 mm2
4

1900−2 ( 75 )−350
Ld; F-1 = = 700 mm > 397.44 mm
2

Main Bar End Hooks = 16 mm diameter @ 90° = 256 mm


F-1; L = 1.9 – 2(0.075) + 0.256(2) = 2.3 m
# of pcs = 12 sets x 8 pcs x 2 = 192 pcs of 2.3 m

(F-1) CUT LENGTH 2.3 m @ 192 pcs

Length of Cut Length # of pcs produced Wastage


Rebar (16 (m) pcs. pcs. Length
mm)
6 2.3 2.60869565 2 1.4
7.5 3.26086957 3 0.6
9 3.91304348 3 2.1
10.5 4.56521739 4 1.3
12 5.2173913 5 0.5

# of pcs. = 192/3 = 64 pcs. of 7.5 mm @16 mm diameter bar


WASTAGE = 64 pcs. with a cut length of 0.6 m

SIZE OF REBAR (DIAMETER) WEIGHT/METER


10 0.616 kg/m
12 0.888 kg/m
16 1.578 kg/m
20 2.466 kg/m
25 3.853 kg/m

64 pcs. @ 16 mm x 7.5 m = 64 x 1.578 x 3 = 757.44 kgs.


Republic of the Philippines
CAMARINES NORTE STATE COLLEGE
F. Pimentel Avenue, Brgy. 2, Daet, Camarines Norte – 4600, Philippines

COLLEGE OF ENGINEERING
Ties; No. of Intersection @F1 = 8 x 8 = 64 x 12 sets = 768 pcs.
Total Length of Tie/s = 768 x 0.3 = 230.4m/53m = 4.35kg of tie wire
#16 G.I Tie Wire, 1 kg of tie wire = 53m

2. COLUMN REINFORCEMENT

C1 (Foundation to Ground Floor Level) @ 12 sets H = 2.225 m


C-1 (Ground Floor Level to Second Floor Level) @ 12 sets H (CLEAR SPAN) =
2.8m
C-1 (Second Floor Level to Top of RB) @ 12 sets H (CLEAR SPAN) = 2.7 m

Main Bar 8 pcs @ 16 mm


Lateral Ties @ 10 mm

C-1 (Ground Floor Level to Second Floor Level) Splicing Zone = 2.8 – 2 (H/4) =2.8 –
2(0.7) = 1.4 m
C-1 (Second Floor Level to Top of RB) Splicing Zone = 2.7 – 2 (H/4) =2.8 – 2(0.675)
= 1.35 m

Total Length of Vertical Bar = 4.625 + 16db HOOK = 4.925 m (first set using 6 m
commercial length)
Total Length for Splicing (using 6 m commercial length) = 40db + 4.06m + 0.15m
(HOOK) = 4.85 m

Total Length of Vertical Bar = 7.2 + 16db HOOK = 7.5 m (first set using 7.5 m
commercial length)
Total Length for Splicing (using 6 m commercial length) = 40db + 1.485m + 0.15m
(HOOK) = 2.275 m

Splicing must be 50% or less (Staggered Position)


8 – 16 mm for C1 = 4 pcs. of 6 m @16mm bar for Set 1, 4 pcs. of 7.5 m @16 mm
bar for Set 2, and 4 pcs. of 7.5 mm @16 mm bar for splicing
Number of C1 = 12 sets

Total No. of 16mmx6m bar = 12 sets x 4 = 48 pcs. or 454.5 kgs. (VERTICAL BAR)
Total No. of 16mmx7.5m bar = 12 sets x 8 = 96 pcs. or 1136.16 kgs (VERTICAL
BAR)

Column Lateral Ties


L = 2A + 2B + HOOK(2) – 3(2db) – 2(3db) =
Hook = 9db or 3d + 75
2db for 90 deg. bend
3db for 135 deg. Bend
A = 350mm – 2(40mm) = 270 mm
B = 350mm – 2(40mm) = 270 mm
db = 10 mm dia.
Hook = 3(10) + 75 = 105 mm
Hook = 9db = 90 mm
L = 2(270) + 2(270) +105(2) – 3(2(10)) – 2(3(10)) = 1170 mm or 1.17 m
Republic of the Philippines
CAMARINES NORTE STATE COLLEGE
F. Pimentel Avenue, Brgy. 2, Daet, Camarines Norte – 4600, Philippines

COLLEGE OF ENGINEERING

Inner Ties
C = db + √ ¿ ¿
C = 200.92 mm or 201 mm
L = 4C + 2HOOK – 3(2db) – 2(3db) = 4(201) + 2(105) – 3(2(10)) – 2(3(10)) = 894 mm

C1 (Foundation to Ground Floor Level) @ 12 sets H = 2.225 m (less 75 mm


concrete cover)
H = 2.225 – 0.3 - 0.016(2) = 1.893 m
Ties spaced at 2 @50, 8 @75, REST @150mm O.C
Height @150 mm = 1.893 – (2x0.05x2) – (8x0.075x2) = 0.493 m
# of pcs @150 mm = (0.493/0.150)-1 = 3.3 pcs say 3 pcs.

C-1 (Ground Floor Level to Second Floor Level) @ 12 sets H (CLEAR SPAN) =
2.8m
Ties spaced at 2 @50, 8 @75, REST @150mm O.C
Height @150 mm = 2.8 – (2x0.05x2) – (8x0.075x2) = 1.4 m
# of pcs @150 mm = (1.4/0.150)-1 = 8.3 pcs say 8 pcs.

C-1 (Second Floor Level to Top of RB) @ 12 sets H (CLEAR SPAN) = 2.7 m
Ties spaced at 2 @50, 8 @75, REST @150mm O.C
Height @150 mm = 2.7 – (2x0.05x2) – (8x0.075x2) = 1.9 m
# of pcs @150 mm = (1.9/0.150)-1 = 11.6667 pcs say 12 pcs.

Total No. of Ties/Column = 2+8+3+8+2+2+8+8+8+2+2+8+12+8+2+2(starter ties) =


85 pcs.
Joint Confinement = 3 pcs. x 3 = 9 pcs.
Total # of pcs = Outer Ties with a cut length of 1.17m = 94 pcs; Inner Ties with a cut
length of 0.894 m = 94 pcs
TOTAL = Outer Ties with a cut length of 1.17m = 1128 pcs; Inner Ties with a cut
length of 0.894 m = 1128 pcs

LENGTH OF REBAR CUT LENGTH # of pcs produced WASTAGE LENGTH


(10 mm dia.) (m) (m)
6 1.17 5.12820513 5 0.15
7.5 1.17 6.41025641 6 0.48
SO # OF REBAR @10 mm x 6 m = 1128/5 = 225.6 say 226 pcs. @10 mm x 6m =
835.296 kgs

LENGTH OF REBAR CUT LENGTH # of pcs produced WASTAGE LENGTH


(10 mm dia.) (m) (m)
6 0.894 6.7114094 6 0.636
7.5 0.894 8.38926174 8 0.348
SO # OF REBAR @10 mm x 7.5 m = 1128/8 = 141 pcs. @10 mm x 7.5m = 651.42
kgs

#16 Tie Wire Used = 24 kgs


Republic of the Philippines
CAMARINES NORTE STATE COLLEGE
F. Pimentel Avenue, Brgy. 2, Daet, Camarines Norte – 4600, Philippines

COLLEGE OF ENGINEERING
STIFFENER COLUMNS (Ground Floor)
No. of 12mm x 6m bar = 6/2.8 = 2 pcs. of 2.8 m per 6 m bar (excess = 0.4m)
Total No. of 12mm x 6m bar = 2 pcs. x 7 = 14 pcs = 74.592 kgs. (VERTICAL BAR)

Column Lateral Ties


L = 2A + 2B + HOOK(2) – 3(2db) – 2(3db) =
Hook = 9db or 3d + 75
2db for 90 deg. bend
3db for 135 deg. Bend
A = 150mm – 2(40mm) = 70 mm
B = 300mm – 2(40mm) = 220 mm
db = 10 mm dia.
Hook = 3(8) + 75 = 99 mm
Hook = 9db = 72 mm
L = 2(70) + 2(220) +99(2) – 3(2(8)) – 2(3(8)) = 682 mm or 0.682 m

Inner Ties
C = db + √ ¿ ¿
C = 153 mm
L = 4C + 2HOOK – 3(2db) – 2(3db) = 4(153) + 2(99) – 3(2(8)) – 2(3(8)) = 714 mm

(Ground Floor Level to Second Floor Level) @ 12 sets H (CLEAR SPAN) = 2.8m
Ties spaced at 8 mm TIES AT SPACED 150 mm O.C
# of pcs @150 mm = (2.8/0.150)-1 = 17.6667 pcs say 18 pcs.

Total No. of Ties/Column = 18+2(starter ties) = 20 pcs.


Total # of pcs = Outer Ties with a cut length of 0.682m = 20 pcs; Inner Ties with a cut
length of 0.714 m = 20 pcs
TOTAL = Outer Ties with a cut length of 0.682m = 140 pcs; Inner Ties with a cut
length of 0.714 m = 140 pcs

LENGTH OF REBAR CUT LENGTH # of pcs produced WASTAGE LENGTH


(10 mm dia.) (m) (m)
6 0.682 8.79765396 8 0.544
7.5 0.682 10.9970674 10 0.68
SO # OF REBAR @8 mm x 6 m = 140/8 = 17.5 say 18 pcs. @8 mm x 6m = 42.7kgs

LENGTH OF REBAR CUT LENGTH # of pcs produced WASTAGE LENGTH


(10 mm dia.) (m) (m)
6 0.714 8.40336134 8 0.288
7.5 0.714 10.5042017 10 0.36
SO # OF REBAR @8 mm x 7.5 m = 140/8 = 17.5 say 18 pcs. @8 mm x 6m =
42.7kgs

STIFFENER COLUMNS (Second Floor)


No. of 12mm x 6m bar = 6/2.8 = 2 pcs. of 2.7 m per 6 m bar (excess = 0.6m)
Total No. of 12mm x 6m bar = 2 pcs. x 7 = 14 pcs = 74.592 kgs. (VERTICAL BAR)
Republic of the Philippines
CAMARINES NORTE STATE COLLEGE
F. Pimentel Avenue, Brgy. 2, Daet, Camarines Norte – 4600, Philippines

COLLEGE OF ENGINEERING
Column Lateral Ties
L = 2A + 2B + HOOK(2) – 3(2db) – 2(3db) =
Hook = 9db or 3d + 75
2db for 90 deg. bend
3db for 135 deg. Bend
A = 150mm – 2(40mm) = 70 mm
B = 300mm – 2(40mm) = 220 mm
db = 10 mm dia.
Hook = 3(8) + 75 = 99 mm
Hook = 9db = 72 mm
L = 2(70) + 2(220) +99(2) – 3(2(8)) – 2(3(8)) = 682 mm or 0.682 m

Inner Ties
C = db + √ ¿ ¿
C = 153 mm
L = 4C + 2HOOK – 3(2db) – 2(3db) = 4(153) + 2(99) – 3(2(8)) – 2(3(8)) = 714 mm

(Ground Floor Level to Second Floor Level) @ 12 sets H (CLEAR SPAN) = 2.7m
Ties spaced at 8 mm TIES AT SPACED 150 mm O.C
# of pcs @150 mm = (2.7/0.150)-1 = 17 pcs.

Total No. of Ties/Column = 17+2(starter ties) = 19 pcs.


Total # of pcs = Outer Ties with a cut length of 0.682m = 19 pcs; Inner Ties with a cut
length of 0.714 m = 19 pcs
TOTAL = Outer Ties with a cut length of 0.682m = 133 pcs; Inner Ties with a cut
length of 0.714 m = 133 pcs

LENGTH OF REBAR CUT LENGTH # of pcs produced WASTAGE LENGTH


(10 mm dia.) (m) (m)
6 0.682 8.79765396 8 0.544
7.5 0.682 10.9970674 10 0.68
SO # OF REBAR @8 mm x 6 m = 133/8 = 16.625 say 17 pcs. @8 mm x 6m = 40.29
kgs

LENGTH OF REBAR CUT LENGTH # of pcs produced WASTAGE LENGTH


(10 mm dia.) (m) (m)
6 0.714 8.40336134 8 0.288
7.5 0.714 10.5042017 10 0.36

SO # OF REBAR @8 mm x 7.5 m = 133/8 = 16.625 say 17 pcs. @8 mm x 6m =


40.29 kgs

#16 mm GI TIE WIRE USED (for L0,H = 2.8 m) = 2 kgs.


#16 mm GI TIE WIRE USED (for L0,H = 2.7 m) = 1 kg.

3. WALL FOOTING
Using Commercial Length 6m,
Republic of the Philippines
CAMARINES NORTE STATE COLLEGE
F. Pimentel Avenue, Brgy. 2, Daet, Camarines Norte – 4600, Philippines

COLLEGE OF ENGINEERING
Between Grid Line 3 & 4, L = 9m – 6m – 40db = 2.6 m
For a 6 m bar, we’ll get 2 pcs @2.6 m and a wastage of 0.8m
For WF1, we need 3 pcs of 10 mm temperature bars
# of rebar = 3/2 = 1.5 pcs say 2 pcs
Total = 5 pcs @10mm dia. x 6m (wastage = 1.6m and 3.8m)
Transverse Bar, L = 0.5 – 0.075 – 0.075 + 0.075 + 0.075 = 0.5m
# of 0.5m needed = 9/0.4(spacing) = 22.5 say 23 pcs 10 mm dia. x 0.5 m

LENGTH OF REBAR CUT LENGTH # of pcs produced WASTAGE LENGTH


(10 mm dia.) (m) (m)
6 0.5 12 12 pcs 0

Required Number of 10 mm dia. x 6m = 23/12 = 1.92 pcs say 2 pcs. @10mm dia. x
6m
Between Grid Line 3 & 4 (WF-1), L= 9m
TEMPERATURE (LONGITUDINAL) BAR = 5 pcs 10 mm dia. x 6 m
MAIN BAR (TRANSVERSE) = 2 pcs. 10mm dia. x 6m
# 16 tie wire used = (23(2)(0.4))/53 = 0.40 kgs.

Between Grid Line 1 & 2 (WF-2), L= 9m


TEMPERATURE BAR = 5 pcs @10 mm dia. x 6 m
MAIN BAR = 2 pcs. 10mm dia. x 6m
# 16 tie wire used = (23(2)(0.4))/53 = 0.40 kg

Between Grid Line A & B (WF-2), L= 1.65 m


TEMPERATURE BAR = 4 pcs 10 mm dia. x 6 m
MAIN BAR = 1 pc. 10mm dia. x 6m
# 16 tie wire used = (5(2)(0.4))/53 = 0.10 kg

At Grid Line B (WF-2), L= 1.5 m


TEMPERATURE BAR = 4 pcs 10 mm dia. x 6 m
MAIN BAR = 1 pc. 10mm dia. x 6m
# 16 tie wire used = (4(2)(0.4))/53 = 0.10 kg

Between Grid Line 2 & 3 (WF-2), L= 4.05 m


TEMPERATURE BAR = 6 pcs 10 mm dia. x 6 m
MAIN BAR = 1 pc. 10mm dia. x 6m
# 16 tie wire used = (11(2)(0.4))/53 = 0.20 kg

At Grid Line B, L = 3.65 m (WF-2)


TEMPERATURE BAR = 6 pcs 10 mm dia. x 6 m
MAIN BAR = 1 pc. 10mm dia. x 6m
# 16 tie wire used = (10(2)(0.4))/53 = 0.20 kg

At Grid Line B, L = 1.5m


TEMPERATURE BAR = 4 pcs 10 mm dia. x 6 m (with a wastage of 1.5m)
MAIN BAR = 1 pc. 10mm dia. x 6m
# 16 tie wire used = (4(2)(0.4))/53 = 0.10 kg
Republic of the Philippines
CAMARINES NORTE STATE COLLEGE
F. Pimentel Avenue, Brgy. 2, Daet, Camarines Norte – 4600, Philippines

COLLEGE OF ENGINEERING

4. BEAMS

FTB (horizontal); L(Clear Span) = 3.975m; V= 3.975(0.2)(0.3) = 0.2385 cu.m

FTB

Main Bar = 4 pcs. 16 mm dia. x 3.975m

Ties = 10mm dia. spaced 1 @ 50mm, 4 @100mm, and rest @200mm towards midspan

No. of Ties = 1(2) + 4(2) + 16 + 1(starter ties) = 27 pcs

Ln = 3.975 – (0.05x2) – (0.1x4x2) = 3.075m; n = 3.075/0.2 = 15.375 say 16 pcs

Stirrups, L = 2(200-25-25)+2(300-25-25)+((3x10)+75)(2)-2(3x10)-3(2x10) = 890 mm or 0.89 m

Main bar = 4 pcs. 16 mm dia. x 3.975m

Stirrups = 27 pcs. 10 mm dia. x 0.89 m

LENGTH OF REBAR CUT LENGTH # of pcs produced WASTAGE LENGTH


(10 mm dia.) (m) (m)
6 3.975 1.509433962 1 2.025
7.5 3.975 1.886792453 1 3.525
MAIN BAR = 4 pcs/1 pc. = 4pcs. 16 mm dia. x 3.975 m = 37.872 kgs.

LENGTH OF REBAR CUT LENGTH # of pcs produced WASTAGE LENGTH


(10 mm dia.) (m) (m)
6 0.89 6.741573034 6 0.66
7.5 0.89 8.426966292 8 0.38
STIRRUPS = 27/8 = 4 pcs. 10 mm dia. x 0.89 m = 18.48 kgs.

RATIO OF REBAR AND CONCRETE = Weight/Volume = 56.352 kgs./ 0.2385 cu.m = 236.28 kgs./cu.m

L = 3.975(4) = 15.9 m

Total Volume of FTB = 15.9 m(0.2)(0.3) = 0.954 cu.m


Republic of the Philippines
CAMARINES NORTE STATE COLLEGE
F. Pimentel Avenue, Brgy. 2, Daet, Camarines Norte – 4600, Philippines

COLLEGE OF ENGINEERING
Total Weight of FTB = ratio x total volume = 236.28 kgs./cu.m (0.954 cu.m) = 225.408 kgs.

Add 5% for splicing, hooks and additional ties (Maximum Length of Ties at Splicing Zone is 0.1 m or 100
mm)

Total Weight of FTB = 225.408 kgs. + 225.408 kgs.(5%) = 236.6784 kgs.

Total Cost = 236.6784 kgs. x 44 pesos = 10,413.85 pesos

MAIN STIRRUPS Ratio of rebar Tie Wire in


BAR & concrete Total Weight Total Cost kgs.
FTB (H) 4 4 236.2767296 236.6784 10413.85 3
FTB (V) 2 3 180 236.439 10403.316 4
2B (H) 9 7 232.8805031 933.1056 41056.646 12
2B(V) 5 6 195.0863309 768.76695 33825.746 12
2B-2 4 4 231.9012346 59.1696 2603.4624 1
STB 1 2 219.53125 22.12875 973.665 1
RB (H) 6 5 252.5383648 632.4192 27826.445 8
RB (V) 3 4 192.9553957 475.23105 20910.166 8
STF (W) 0.5 0.5 194.1666667 161.469 3067.911 3
STF (D1) 0.8 0.5833 197.2409091 13.668795 601.42698 1
STF (D2) 0.8 0.5833 180.8041667 27.33759 1202.854 1
STF (D3) 1 0.6667 202.9230769 11.0796 487.5024 use excess

MAIN STIRRUPS Ratio of rebar Tie Wire in


BAR & concrete Total Weight Total Cost kgs.
LB-1 (12) 8 8 178.8952381 473.3568 20827.6992 6
LB-1 (8) 8 5 235.3428571 207.5724 9133.1856 2
LB-1 (6) 4 4 178.8952381 118.3392 5206.9248 2
LB-1 (4) 4 3 246.3428571 54.3186 2390.0184 use excess

5. SLAB REBAR

SOG

100 mm thick concrete slab on fill with 12 mm diameter temperature bars spaced 300 mm both ways

# of rebar needed with a length of 9m = (12m/0.3m) +1 = 41 pcs. @12 mm x 12 m

Option 1: If using commercial length 6 m bar, L = 9m – 6m + 0.48m = 3.48m


Republic of the Philippines
CAMARINES NORTE STATE COLLEGE
F. Pimentel Avenue, Brgy. 2, Daet, Camarines Norte – 4600, Philippines

COLLEGE OF ENGINEERING
LENGTH OF REBAR CUT LENGTH # of pcs produced WASTAGE LENGTH
(10 mm dia.) (m) (m)
6 3.48 1.72413793 1 pc. 2.52
7.5 3.48 2.15517241 2 pcs. 0.54
= 41/2 = 20.5 say 21 pcs. @12mm x 7.5m

41 pcs. @12 mm x 6 m

21 pcs. @12mm x 7.5m

Option 2: If using commercial length 7.5 m bar, L = 9m – 7.5m + 0.48m = 1.02m

LENGTH OF REBAR CUT LENGTH # of pcs produced WASTAGE LENGTH


(10 mm dia.) (m) (m)
6 1.98 3.03030303 3 0.06
7.5 1.98 3.78787879 3 1.56
= 41/3 = 13.6667 pcs say 14 pcs. @12mm x 6m

41 pcs. @12 mm x 6 m

14 pcs. @12mm x 6m

Option1

W1 = 41 pcs. x 6 m x 0.888kg/m = 218.448 kgs.

W2 = 21 pcs. x 7.5m x 0.888kg/m = 139.86 kgs

Total Weight = 358.308 kgs

Option2

W1 = 41 pcs. x 6 m x 0.888kg/m = 218.448 kgs.

W2 = 14 pcs. x 6 m x 0.888 kg/m = 74.592 kgs.

Total Weight = 293.08 kgs.

*Use 41 pcs. @12 mm x 6 m and 14 pcs. @12mm x 6m

# of rebar needed with a length of 12m = (9m/0.3m) +1 = 31 pcs. @12 mm x 12 m

Option 1: If using commercial length 6 m bar, L = 12m – 6m + 0.48m = 6.48m

LENGTH OF REBAR CUT LENGTH # of pcs produced WASTAGE LENGTH


(10 mm dia.) (m) (m)
6 6.48 0.92592593 0 6
7.5 6.48 1.15740741 1 pc. 1.02
Republic of the Philippines
CAMARINES NORTE STATE COLLEGE
F. Pimentel Avenue, Brgy. 2, Daet, Camarines Norte – 4600, Philippines

COLLEGE OF ENGINEERING
= 31/1 = 31 pcs. @12mm x 7.5m

31 pcs. @12 mm x 6 m

31 pcs. @12mm x 7.5m

Option 2: If using commercial length 7.5 m bar, L = 12m – 7.5m + 0.48m = 4.98m

LENGTH OF REBAR CUT LENGTH # of pcs produced WASTAGE LENGTH


(10 mm dia.) (m) (m)
6 4.98 1.20481928 1 pc. 1.02
7.5 4.98 1.5060241 1 pc. 2.52
= 31/1 = 31 pcs. @12mm x 6m

31 pcs. @12 mm x 6 m

31 pcs. @12mm x 6m

Option1

W1 = 31 pcs. x 6 m x 0.888kg/m = 165.168 kgs.

W2 = 31 pcs. x 7.5m x 0.888kg/m = 206.46 kgs

Total Weight = 371.628 kgs

Option2

W1 = 31 pcs. x 6 m x 0.888kg/m = 165.168 kgs.

W2 = 31 pcs. x 6 m x 0.888kg/m = 165.168 kgs

Total Weight = 330.336 kgs

*Use 31 pcs. @12 mm x 6 m and 31 pcs. @12mm x 6m

S1

L = 4.325 m

W = 3.825 m

L/4 = 1.08125 m

W/4 = 0.95625 m

L/2 = 1.9125 m

W/2 = 2.1625 m

Bent Bars

L1 = 3.825 + (H x 2) + bend
Republic of the Philippines
CAMARINES NORTE STATE COLLEGE
F. Pimentel Avenue, Brgy. 2, Daet, Camarines Norte – 4600, Philippines

COLLEGE OF ENGINEERING
Hook = 195 mm or 0.195 m

Bend = 66 mm

L1 = 4.281 m

# of rebars needed = (2.1625/0.185) +1 = 12.7 say 13 pcs

L2 = 4.781 m

# of rebars needed = (1.9125/0.185) +1 = 11.34 say 12 pcs

Bottom Straight Bars

L3 = 3.825 + 0.195(2) = 4.215 m

# of rebars needed @ 4.215 = (4.325/0.185) +1 = 24.38 say 25 pcs

L4 = 4.325 + 0.195(2) = 4.715 m

# of rebars needed @ 4.715 = (3.825/0.185) +1 = 21.68 say 22 pcs

Top Straight Bars

L3 = 3.825 + 0.195(2) = 4.215 m

# of rebars needed @ 4.215 = (1.08125/0.185) +1 = 6.84 say 7 pcs x 2 = 14 pcs

L4 = 4.325 + 0.195(2) = 4.715 m

# of rebars needed @ 4.715 = (0.95625/0.185) +1 = 6.17 say 7 pcs x 2 = 14 pcs

Cut Bars

L5 = W/3 + 0.195 = 3.825/3 + 0.195 = 1.47 m

# of rebars needed @ 1.47m = 13 -1 = 12 pcs x 2 = 24 pcs

L6 = L/3 + 0.195 = 4.325/3 + 0.195 = 1.64 m

# of rebars needed @ 1.64m = 12 -1 = 11 pcs x 2 = 22 pcs

SLAB REINFORCEMENT
SOG @9m 41 pcs 12 mm x 6 m
14 pcs 12mm x 6m
@ 12 m 31 pcs 12 mm x 6 m
31 pcs 12mm x 6m
#16 GI TIE WIRE 8 KGS
S1 BENT BARS
13 pcs @ 4.281 m 13 pcs 12 mm x 6 m
12 pcs @ 4.781 m 12 pcs 12 mm x 6 m
Republic of the Philippines
CAMARINES NORTE STATE COLLEGE
F. Pimentel Avenue, Brgy. 2, Daet, Camarines Norte – 4600, Philippines

COLLEGE OF ENGINEERING
BOTTOM ST. BARS
25 pcs @ 4.215 m 25 pcs 12 mm x 6 m
22 pcs @ 4.715 m 22 pcs 12 mm x 6 m
TOP ST. BARS
14 pcs @ 4.215 m 14 pcs 12 mm x 6 m
14 pcs @ 4.715 m 14 pcs 12 mm x 6 m
CUT BARS
24 pcs @ 1.47m 6 pcs 12 mm x 6 m
22 pcs @ 1.64 m 6 pcs 12 mm x 7.5 m
#16 GI TIE WIRE 19 KGS.

S2-A BENT BARS


6 pcs @ 2.206 m 2 pcs 12 mm x 7.5 m
6 pcs @ 2.306 m 2 pcs 12 mm x 7.5 m
BOTTOM ST. BARS
6 pcs @ 2.14 m 2 pcs 12 mm x 7.5 m
6 pcs @ 2.24 m 2 pcs 12 mm x 7.5 m
TOP ST. BARS
8 pcs @ 2.14 m 3 pcs 12 mm x 7.5 m
8 pcs @ 2.24 m 3 pcs 12 mm x 7.5 m
CUT BARS
10 pcs @ 0.77833 2 pcs 12 mm x 7.5 m
10 pcs @ 0.81 m Use excess bars
#16 GI TIE WIRE 1 KG.

S2-B BENT BARS


26 pcs @ 2.456 m 9 pcs 12 mm x 7.5 m

BOTTOM ST. BARS


14 pcs @ 2.39 m 5 pcs 12 mm x 7.5 m
7 pcs @ 4.89 m 7 pcs 12 mm x 6 m
TOP ST. BARS
8 pcs @ 4.89 m 8 pcs 12 mm x 6 m
CUT BARS
50 pcs @ 0.86167 m 7 pcs 12 mm x 7.5 m

#16 GI TIE WIRE 2 KGS

S3 BENT BARS
10 pcs @ 4.265 m 10 pcs 12 mm x 6 m
9 pcs @ 4.765 m 9 pcs 12 mm x 6 m
BOTTOM ST. BARS
19 pcs @ 4.215 m 19 pcs 12 mm x 6 m
17 pcs @ 4.715 m 17 pcs 12 mm x 6 m
TOP ST. BARS
12 pcs @ 4.215 m 12 pcs 12 mm x 6 m
10 pcs @ 4.215 m 10 pcs 12 mm x 6 m
CUT BARS
18 pcs @ 1.47m 5 pcs 12 mm x 6 m
16 pcs @ 1.64 m 4 pcs 12 mm x 7.5 m
#16 GI TIE WIRE 15 KGS
Republic of the Philippines
CAMARINES NORTE STATE COLLEGE
F. Pimentel Avenue, Brgy. 2, Daet, Camarines Norte – 4600, Philippines

COLLEGE OF ENGINEERING

TOTAL (BARS) 320 pcs / 1704.96 kgs 12 mm x 6 m


47 pcs / 313.02 kgs 12 mm x 7.5 m
TOTAL (TIE WIRE) 45 kgs. #16 GI (0.3 m cut @ 6m)
TOTAL COST 88,791.12 pesos

6. STAIR REINFORCEMENT

STAIR 1A # of 10 mm lateral bars required at steps pcs @ 6m 6


# of 10 mm horizontal bars required at steps pcs @ 6m 5
# of 12 mm lateral bars required at stringer pcs @ 6m 4
# 0f 12 mm horizontal bars required at pcs @ 6m 2
stringer
# of 16 mm tie wire used kgs 1
STAIR 1B # of 10 mm lateral bars required at steps pcs @ 6m 6
# of 10 mm horizontal bars required at steps pcs @ 6m 5
# of 12 mm lateral bars required at stringer pcs @ 6m 4
# 0f 12 mm horizontal bars required at pcs @ 6m 2
stringer
# of 16 mm tie wire used kgs 1

SLAB at
stairs BENT BARS
8 pcs @ 1.531 m 2 pcs 12 mm x 7.5 m
5 pcs @ 2.306 m 2 pcs 12 mm x 7.5 m
BOTTOM ST. BARS
8 pcs @ 1.465 m 2 pcs 12 mm x 6 m
5 pcs @ 2.24 m 2 pcs 12 mm x 7.5 m
TOP ST. BARS
10 pcs @ 1.465 m 3 pcs 12 mm x 6 m
6 pcs @ 2.24 m 2 pcs 12 mm x 7.5 m
CUT BARS
14 pcs @ 0.55333m 2 pcs 12 mm x 7.5 m
8 pcs @ 0.81166667 m Use excess bars
# 16 GI TIE WIRE 1 KG

STAIR 2 # of 10 mm lateral bars required at steps pcs @ 6m 6


# of 10 mm horizontal bars required at steps pcs @ 6m 6
# of 12 mm lateral bars required at stringer pcs @ 6m -
# 0f 12 mm horizontal bars required at pcs @ 6m 3
stringer
# of 16 mm tie wire used kgs Use excess
TOTAL (BARS) 34 pcs. / 125.664 kgs 10 mm x 6 m
20 pcs. / 106.56 kgs. 12 mm x 6 m
10 pcs. / 66.6 kgs 12 mm x 7.5 m
3 kgs. #16 GI (0.3 m cut @
TOTAL (TIE WIRE) 6m)
TOTAL COST 13,148.26 pesos
Republic of the Philippines
CAMARINES NORTE STATE COLLEGE
F. Pimentel Avenue, Brgy. 2, Daet, Camarines Norte – 4600, Philippines

COLLEGE OF ENGINEERING
7. WALL REINFORCEMENT

Area of Exterior Wall = 193.7525 m2


Vertical Reinforcement (Running Bond) = 60 cm (spacing) = 2.13 m per sq.m
Horizontal Reinforcement = every 3 layers = 2.15 m per sq.m
Vertical Bar = 2.13 m per sq.m x 193.7525 sq.m = 412.7 m
# of Vertical Bars Used = (193.7525 x 2.13)/6 = 69 pcs @ 6m
Horizontal Bar = 2.15 m per sq.m x 193.7525 sq.m = 416.57 m
# of Horizontal Bars Used = 70 pcs @ 6 m
Total Length = 829.27 m
Pcs. of 6 m bars = 829.27/6 = 138.21 say 139 pcs of 6 mm comm. length
Total Weight = 513.744 kgs
# 16 tie wire used = 9.20 kgs say 9 kgs

Area of Interior Wall = 118.71 m2


Vertical Reinforcement (Running Bond) = 60 cm (spacing) = 2.13 m per sq.m
Horizontal Reinforcement = every 3 layers = 2.15 m per sq.m
Vertical Bar = 2.13 m per sq.m x 118.71 sq.m = 252.8523 m
# of Vertical Bars Used = (118.71 x 2.13)/6 = 43 pcs @ 6m
Horizontal Bar = 2.15 m per sq.m x 118.71 sq.m = 255.2265 m
# of Horizontal Bars Used = 43 pcs @ 6m
Total Length = 508.0788 m
Pcs. of 6 m bars = 508.0788/6 = 84.6798 say 86 pcs of 6 mm comm. length
Total Weight = 317.856 kgs
# 16 tie wire used = 5.60 kgs say 6 kgs

8. CONCRETE CANOPY REINFORCEMENT

# of transverse # of pcs total no. of Weight Total Total Tie Wire


kgs
@0.535 per 7.5 m longitudinal (Longitudinal) Weight Cost in kgs.
@ 12m 96 7 32.34 10 36.96 277.2 12196.8 9
@ 8m 64 5 23.1 6 23.1 92.4 4065.6 3
@ 6m 48 4 18.48 5 18.48 73.92 3252.48 3
@ 4m 32 3 13.86 5 18.48 32.34 1422.96 1

MASONRY WORKS
 CHB LAYING
Interior Wall 4” (400mm x 100mm x 200 mm)
Exterior Wall 6” (400mm x 150 mm x 200 mm)

First Floor (Exterior)

FRONT ELEVATION
Area = LH = 3.975m x 2.8m = 11.13 m2

Area = LH = 8.7m x 2.8m = 24.36 m2


Area (D1) = 2.1m x 0.9m = 1.89 m2
Area (W1) = 1.8m x 0.5m = 0.9 m2
Total Area = 17.97 m2
Republic of the Philippines
CAMARINES NORTE STATE COLLEGE
F. Pimentel Avenue, Brgy. 2, Daet, Camarines Norte – 4600, Philippines

COLLEGE OF ENGINEERING
REAR ELEVATION
Area = LH = 3.975m x 2.8m = 11.13 m2
Area (W2) = 1.2m x 0.5m = 0.6 m2
Total Area = 11.13 – 3(0.6) = 9.33 m2

Area = LH = 3.975m x 2.8m = 11.13 m2


Area (W1) = 1.8m x 0.5m = 0.9 m2
Area (W3) = 0.6m x 0.5m = 0.3 m2
Total Area = 11.13 – 2(0.9) – 0.3 = 9.03 m2

LEFT SIDE ELEVATION


Area = LH = 3.475m x 2.8m = 9.73 m2
Area (W1) = 1.8m x 0.5m = 0.9 m2
Total Area = 9.73 – 2(0.9) = 7.93 m2

Area = LH = 3.65m x 2.8m = 10.22 m2


Area (W1) = 1.8m x 0.5m = 0.9 m2
Total Area = 10.22 – 3(0.9) = 7.52 m2

Area = LH = 3.475m x 2.8m = 9.73 m2


Area (W1) = 1.8m x 0.5m = 0.9 m2
Total Area = 9.73 – 0.9 = 8.83 m2

RIGHT SIDE ELEVATION


Area = LH = 3.475m x 2.8m = 9.73 m2
Area (W1) = 1.8m x 0.5m = 0.9 m2
Total Area = 9.73 – 2(0.9) = 7.93 m2

Area = LH = 3.65m x 2.8m = 10.22 m2


Area (W1) = 1.8m x 0.5m = 0.9 m2
Total Area = 10.22 – 2(0.9) = 8.42 m2

Area = LH = 3.475m x 2.8m = 9.73 m2


Area (W1) = 1.8m x 0.5m = 0.9 m2
Total Area = 9.73 – 0.9 = 8.83 m2

Second Floor (Exterior)

FRONT ELEVATION
Area = LH = 3.975m x 2.7m = 10.7325 m2

REAR ELEVATION
Area = LH = 3.975m x 2.7m = 10.7325 m2
Area (W1) = 1.8m x 0.5m = 0.9 m2
Area (W3) = 0.6m x 0.5m = 0.3 m2
Total Area = 10.7325 – 2(0.90) – 0.3 = 8.6325 m2

Area = LH = 3.975m x 2.7m = 10.7325 m2


Area (W1) = 1.8m x 0.5m = 0.9 m2
Republic of the Philippines
CAMARINES NORTE STATE COLLEGE
F. Pimentel Avenue, Brgy. 2, Daet, Camarines Norte – 4600, Philippines

COLLEGE OF ENGINEERING
Area (W2) = 1.2m x 0.5m = 0.6 m2
Total Area = 10.7325 – 0.9 – 0.6 = 9.2325 m2

LEFT SIDE ELEVATION


Area = LH = 3.475m x 2.7m = 9.3825 m2
Area (W1) = 1.8m x 0.5m = 0.9 m2
Total Area = 9.3825 – 2(0.9) = 7.5825 m2

Area = LH = 3.65m x 2.7m = 9.855 m2


Area (W1) = 1.8m x 0.5m = 0.9 m2
Total Area = 9.855 – 3(0.9) = 7.155 m2

Area = LH = 3.475m x 2.7m = 9.3825 m2


Area (W1) = 1.8m x 0.5m = 0.9 m2
Total Area = 9.3825 – 2(0.9) = 7.5825 m2

RIGHT SIDE ELEVATION


Area = LH = 3.475m x 2.7m = 9.3825 m2
Area (W1) = 1.8m x 0.5m = 0.9 m2
Total Area = 9.3825 – 3(0.9) = 6.6825 m2

Area = LH = 3.65m x 2.7m = 9.855 m2


Area (W1) = 1.8m x 0.5m = 0.9 m2
Total Area = 9.855 – 3(0.9) = 7.155 m2

Area = LH = 1.825m x 2.7m = 4.9275m2


Area (W1) = 1.8m x 0.5m = 0.9 m2
Total Area = 4.9275 – 0.8 = 4.0275 m2

TOP OF RB (FRONT & REAR ELEVATIONS)


Area = LH = 4.325m x 0.7m = 3.0275 m2

Area = LH = 4.325m x 0.7m = 3.0275 m2


Area = 1/2bh = ½(1.9875)(0.8) = 2(0.795) = 1.59 m2
Total Area = 4.6175 m2

Area = LH = 7.950m x 0.7m = 5.565 m2

TOP OF RB (LEFT & RIGHT SIDE ELEVATIONS)


Area = LH = 10.6m x 0.7m = 7.42m2

Area = LH = 10.6m x 0.7m = 7.42m2

TOTAL AREA OF EXTERIOR WALL AND NO. OF CHB NEEDED:


Area of Exterior Wall = 193.7525 m2
CHB 6” = 193.7525 m2 x 12.5 = 2421.90625 pcs. or 2422 pcs.

First Floor (Interior)


Area = LH = 1.9m x 2.8m = 5.32 m2
Republic of the Philippines
CAMARINES NORTE STATE COLLEGE
F. Pimentel Avenue, Brgy. 2, Daet, Camarines Norte – 4600, Philippines

COLLEGE OF ENGINEERING

Area = LH = 2.6m x 2.8m = 7.28 m2


Area (D2) = LH = 2.1m x 0.8m = 1.68 m2
Total Area = 5.6 m2

Area = LH = 1.6m x 2.8m = 4.48 m2


Area (D3) = LH = 2.1m x 0.7m = 1.47 m2
Total Area = 3.01 m2

Area = 4.3m x 2.8m = 12.04 m2


Area (D2) = LH = 2.1m x 0.8m = 1.68 m2
Total Area = 10.36 m2

Area = 3.65m x 2.8m = 10.22 m2


Area (D1) = 2.1m x 0.9m = 1.89 m2
Total Area = 8.33 m2

Area = 1.75m x 2.8m = 4.9 m2

Area = 4.3m x 2.8m =12.04 m2


Area (W4) = 1.8m x 0.5m = 0.9 m2
Total Area = 5.74m2

Second Floor (Interior)


Area = 3.975m x 2.7m = 10.7325 m2
Area (D2) = LH = 2.1m x 0.8m = 1.68 m2
Total Area = 9.0525 m2

Area = 3.975m x 2.7m = 10.7325 m2


Area = 1.325m x 2.7m =3.5775 m2
Total Area = 7.155 m2

Area = 3.8m x 2.7m = 10.26 m2

Area = 3.475m x 2.7m = 9.3825 m2


Area (D2) = LH = 2.1m x 0.8m = 1.68 m2
Total Area = 7.7025 m2

Area = 3.8m x 2.7m = 10.26 m2


Area (D2) = LH = 2.1m x 0.8m = 1.68 m2
Total Area = 8.58 m2

Area = 3.65m x 2.7m = 9.855 m2

Area = 1.75m x 2.7m =4.725 m2


Area (D2) = LH = 2.1m x 0.8m = 1.68 m2
Total Area = 3.045 m2

Area = 8.7m x 2.7m = 23.49 m2


Republic of the Philippines
CAMARINES NORTE STATE COLLEGE
F. Pimentel Avenue, Brgy. 2, Daet, Camarines Norte – 4600, Philippines

COLLEGE OF ENGINEERING
Area (D1) = 2.1m x 0.9m = 1.89 m2
Area (W1) = 1.8m x 0.5m = 0.9 m2
Total Area = 19.8 m2

TOTAL AREA OF INTERIOR WALL AND NO. OF CHB NEEDED:


Area of Interior Wall = 118.71 m2
CHB 4” = 1483.875 pcs. or 1484 pcs.

 CEMENT MORTAR

Class C (1:4) – General Use (Exterior and Interior)

CHB 6” = 193.7525 m2 x 12.5 = 2421.90625 pcs. or 2422 pcs.

Cement = 2422 x 0.0667 = 161.5474 say 162 bags

Sand = 161.5474 x 4 = 646.1896 cu.ft. or 18.298 cu.m

CHB 4” = 1483.875 pcs. or 1484 pcs.

Cement = 1484 x 0.04 = 59.36 say 60 bags

Sand = 59.36 x 4 = 237.44 cu.ft. or 6.724 cu.m

TOTAL:

Cement = 222 bags

Sand = 25.022 cu.m

For residential houses (two-storey) and bungalows, add 2% - 5% Factor of Safety to


the total area of the wall.

 PLASTERING

First Floor (Exterior Wall)


Republic of the Philippines
CAMARINES NORTE STATE COLLEGE
F. Pimentel Avenue, Brgy. 2, Daet, Camarines Norte – 4600, Philippines

COLLEGE OF ENGINEERING
Area (1) = P x H = 44.5m x 3.65m = 162.425 m2

Perimeter = 9+12+4.5+2.15+3.9+3.95+9=44.5 m

Height = 3.65m

Area (Porch) = (4.5+2) x 0.45 = 2.925 m2

Area (Signage) = (4.5+1.209+1.209) x 1m = 6.918 m2

Area (Design at Front Elev) = (1.209+0.3+1.209) x 6.55 =3(17.8029) = 53.4087


m2

Second Floor (Exterior Wall)

Perimeter (2) = 4.5+4+4+4+4.5+4.5+4+4+2+9=44.5 m

Area (2) = 44.5m x 3m = 133.5 m2

TOP OF RB (FRONT & REAR ELEVATIONS)

Area = LH = 4.325m x 0.7m = 3.0275 m2

Area = LH = 4.325m x 0.7m = 3.0275 m2

Area = 1/2bh = ½(1.9875)(0.8) = 2(0.795) = 1.59 m2

Total Area = 4.6175 m2

Area = LH = 7.950m x 0.7m = 5.565 m2

TOP OF RB (LEFT & RIGHT SIDE ELEVATIONS)

Area = LH = 10.6m x 0.7m = 7.42m2

Area = LH = 10.6m x 0.7m = 7.42m2

TOTAL AREA = 387.2267 m2

DOORS AND WINDOWS

LEVEL DESCRIPTION SETS DIMENSION AREA


Republic of the Philippines
CAMARINES NORTE STATE COLLEGE
F. Pimentel Avenue, Brgy. 2, Daet, Camarines Norte – 4600, Philippines

COLLEGE OF ENGINEERING
H W
Level 0 (Exterior) W1 18 1.8 0.5 16.2
W2 3 1.2 0.5 1.8
W3 1 0.6 0.5 0.3
D1 1 2.1 0.9 1.89
Level 0 (Interior) W4 7 1.8 0.5 6.3
D1 1 2.1 0.9 1.89
D2 2 2.1 0.8 3.36
D3 1 2.1 0.7 1.47
Level 1 (Exterior) W1 19 1.8 0.5 17.1
W2 1 1.2 0.5 0.6
W3 1 0.6 0.5 0.3
D1 1 2.1 0.9 1.89
Level 1 (Interior) D2 4 2.1 0.8 6.72
D3 1 2.1 0.7 1.47
TOTAL 61.29
Exterior 40.08
Interior 21.21

TOTAL AREA TO BE PLASTERED = 387.2267 m2 – 40.08 m2 = 347.1467m2

First Floor (Columns)

Perimeter =
0.175+0.175+0.175+0.35+0.175+0.175+0.175+0.175+0.35+0.175+0.35+0.35+0.35+0.2+0.175+0.35+0.1
75+0.175+0.35+0.175+0.35+0.2+0.35+0.2+0.35+0.175+0.175+0.35+0.25+0.35+0.35+0.35+0.175+0.175
+0.175 = 8.725 m

Height = 3.2m

Area = 27.92 m2

First Floor (Interior)


Area = LH = 4.25 x 2.8 = 11.9 m2
Area (D2) = LH = 2.1m x 0.8m = 1.68 m2
Area (D3) = LH = 2.1m x 0.7m = 1.47 m2
Total Area = 2(8.75) = 17.5 m2

Area = LH = 4.25 x 2.8 = 11.9 m2


Area (D2) = LH = 2.1m x 0.8m = 1.68 m2
Total Area = 2(10.22) = 20.44 m2

Area = LH = 1.85m x 2.8m = 2(5.18) = 10.36 m2

Area = LH = 4.25 x 2.8 = 11.9 m2


Area (W4) = 1.8m x 0.5m = 0.9 m2
Total Area = 2(5.6) = 11.2 m2

Area = 3.65m x 2.8m = 10.22 m2


Area (D1) = 2.1m x 0.9m = 1.89 m2
Republic of the Philippines
CAMARINES NORTE STATE COLLEGE
F. Pimentel Avenue, Brgy. 2, Daet, Camarines Norte – 4600, Philippines

COLLEGE OF ENGINEERING
Total Area = 2(8.33) = 16.66 m2

Area = 1.65m x 2.8m = 2(4.62) = 9.24 m2

Area (around the perimeter) = Perimeter = 9+12+4.5+2.15+3.9+3.95+9=44.5 m

Columns = 12(0.35) = 4.2m

Total Area = 40.3 x 2.8 = 112.84 m2 – 20.19 m2 = 92.65 m2

Second Floor (Columns)

Columns (Perimeter) =
0.175+0.175+0.175+0.2+0.175+0.175+0.175+0.175+0.2+0.175+0.2+0.2+0.2+0.35+0.175+0.2+0.175+0.1
75+0.35+0.175+0.2+0.35+0.35+0.2+0.175+0.2+0.175+0.35+0.35+0.35+0.35+0.35+0.175+0.35+0.175+0.
175= 8.275

Height = 3.0m

Area = 24.825 m2

Second Floor (Interior)


Area = 3.975m x 2.7m = 10.7325 m2
Area (D2) = LH = 2.1m x 0.8m = 1.68 m2
Total Area = 2(9.0525) = 18.105 m2

Area = 3.975m x 2.7m = 10.7325 m2


Area = 1.325m x 2.7m =3.5775 m2
Total Area = 2(7.155) = 14.31 m2

Area = 3.75m x 2.7m = 2(10.125) = 20.25 m2

Area = 3.475m x 2.7m = 9.3825 m2


Area (D2) = LH = 2.1m x 0.8m = 1.68 m2
Total Area = 2(7.7025) = 15.405 m2

Area = 3.75m x 2.7m = 10.125 m2


Area (D2) = LH = 2.1m x 0.8m = 1.68 m2
Total Area = 2(8.445) = 16.89 m2

Area = 3.65m x 2.7m = 9.855 m2

Area = 1.65m x 2.7m =4.455 m2


Area (D2) = LH = 2.1m x 0.8m = 1.68 m2
Total Area = 2(2.775) = 5.55 m2

Area = 8.7m x 2.7m = 23.49 m2


Area (D1) = 2.1m x 0.9m = 1.89 m2
Area (W1) = 1.8m x 0.5m = 0.9 m2
Total Area = 2(19.8) = 39.6 m2
Republic of the Philippines
CAMARINES NORTE STATE COLLEGE
F. Pimentel Avenue, Brgy. 2, Daet, Camarines Norte – 4600, Philippines

COLLEGE OF ENGINEERING
Area (around the perimeter) = Perimeter = 4.5+4+4+4+4.5+4.5+4+4+2+9=44.5 m

Columns = 12(0.35) = 4.2m

Total Area = 40.3 x 2.7 = 108.81 m2 – 19.89 m2 = 88.892 m2

TOTAL AREA TO BE PLASTERED (INCLUDING COLUMNS) = 205.97 + 253.682 = 459.652 m2

CORNER AREA

LEVEL DESCRIPTION SETS DIMENSION AREA PERIMETER t CORNER AREA


H W
Level 0 (Exterior) W1 18 1.8 0.5 16.2 4.6 0.25 20.7
W2 3 1.2 0.5 1.8 3.4 0.25 2.55
W3 1 0.6 0.5 0.3 2.2 0.25 0.55
D1 1 2.1 0.9 1.89 5.1 0.25 1.275
Level 0 (Interior) W4 7 1.8 0.5 6.3 4.6 0.25 8.05
D1 1 2.1 0.9 1.89 5.1 0.25 1.275
D2 2 2.1 0.8 3.36 5 0.25 2.5
D3 1 2.1 0.7 1.47 4.9 0.25 1.225
Level 1 (Exterior) W1 19 1.8 0.5 17.1 4.6 0.25 21.85
W2 1 1.2 0.5 0.6 3.4 0.25 0.85
W3 1 0.6 0.5 0.3 2.2 0.25 0.55
D1 1 2.1 0.9 1.89 5.1 0.25 1.275
Level 1 (Interior) D2 4 2.1 0.8 6.72 5 0.25 5
D3 1 2.1 0.7 1.47 4.9 0.25 1.225
TOTAL 61.29 68.875
Exterior 40.08
Interior 21.21

SUMMARY

Interior Wall = 459.652 m2

Exterior Wall = 347.1467m2

Corner Area = 68.875m2

TOTAL = 875.6737 m2

For the possibility of wastage, add 15%-20% to the


total area to be plastered.

AREA = 1007.024755 m2
Republic of the Philippines
CAMARINES NORTE STATE COLLEGE
F. Pimentel Avenue, Brgy. 2, Daet, Camarines Norte – 4600, Philippines

COLLEGE OF ENGINEERING

Cement = 1007.024755 m 2 x 0.24 = 241.6859412


say 242 bags

Sand = 1007.024755 m2 x 0.02 = 20.1404951 m3

STONE CLADDING

Stone Cladding at Front Elevation = 2.8 x 6.05 = 16.94 m2

Stone Cladding at Left and Right Elevation = 2(5.95 x 3.7) = 44.03 m2

TOTAL = 60.97 m2

First Floor (Exterior Wall)

Area (1) = P x H = 44.5m x 3.65m = 162.425 m2

Perimeter = 9+12+4.5+2.15+3.9+3.95+9=44.5 m

Height = 3.65m

Area (Porch) = (4.5+2) x 0.45 = 2.925 m2

Second Floor (Exterior Wall)

Perimeter (2) = 4.5+4+4+4+4.5+4.5+4+4+2+9=44.5 m

Area (2) = 44.5m x 3m = 133.5 m2

Area of Exterior Wall (excluding areas that doesn’t require plain cement wall finish) = 298.85 – 60.97 =
237.88 m2
Republic of the Philippines
CAMARINES NORTE STATE COLLEGE
F. Pimentel Avenue, Brgy. 2, Daet, Camarines Norte – 4600, Philippines

COLLEGE OF ENGINEERING
Interior Wall

WF2

A1 = 1.7 x 2.8 = 4.76 m2 – W3 = 4.46 m2

A2 & A3 = 2(2.15 x 2.8) = 12.04 m2

A4 = 1.7 x 2.8 = 4.76 m2 – D3 = 3.29 m2

A5 = (1.5 x 2.7) – W3 = 3.75 m2

A6 = 2(2.15 x 2.7) = 11.61 m2

A7 = (1.5 x 2.7) – D3 = 2.58 m2

TOTAL = 77.73 m2

Area of Interior Wall (excluding areas that doesn’t require plain cement wall finish) = 459.652 – 77.73 =
381.922 m2

Cement Coverage Area = 25 sq.m/bag

237.88
Cement (Exterior Wall) = = 9.5152 bags say 10 bags
25
381.922
Cement (Exterior Wall) = = 15.27688 bags say 16 bags
25
SUMMARY

Sand = 20.1404951 m3

Cement = 242 + 10 + 16 = 268 bags

PAINTING WORKS

Area of WF3

A1 = (2.8 x 2.8) – 2(W1) = 6.04 m2

A2 = (2.15 x 2.8) – W1 = 5.12 m2

A3 = (2.8 x 2.8) – D2 = 6.16 m2

A4 = (2.35 X 2.7) – W1 = 5.445 m2

A5 = (4.0 x 2.7) – 2(W1) = 9 m2

A6 = (2.35 x 2.7) – D2 = 4.665 m2

TOTAL = 36.43 m2
Republic of the Philippines
CAMARINES NORTE STATE COLLEGE
F. Pimentel Avenue, Brgy. 2, Daet, Camarines Norte – 4600, Philippines

COLLEGE OF ENGINEERING
Area of Exterior Wall + Corner Area (excluding areas that doesn’t require painted finish) = 237.88 m2 +
68.875 m2 = 306.755 m2

Area of Interior Wall (excluding areas that doesn’t require painted finish) = 381.922 m2 - 36.43 m2 =
345.492 m2

EXTERIOR WALL
MATERIALS NEEDED COVERAGE AREA QUANTITY PACKAGING
AREA
1 MASONRY NEUTRALIZER B- 20 sq.m / 306.755 1.013061427 1 gal or 3.875 L
3.8344375
44 4.25 L = 2 gals
2 ACRYTEX PRIMER B-1705 4 L and 16 L
a. First Coat 25 sq.m / 306.755 49.0808 5.623841667 = 5 pails
b. Second Coat 30 sq.m / 306.755
40.90066667 2.495366667 = 3 gals
4.0 L
3 ACRYTEX CAST B-1711 25 sq.m / 306.755 4 L and 16 L
49.0808 12.2702 = 13 gals
4.0 L
4 ACRYTEX TOP COAT 4 L and 16 L
a. First Coat 25 sq.m / 306.755
49.0808 5.623841667 = 5 pails
4.0 L
b. Second Coat 30 sq.m / 306.755
40.90066667 2.495366667 = 3 gals
4.0 L
5 THINNING SOLVENT 4 L and 16 L
(ACRYTEX REDUCER B-1750)
a. ACRYTEX CAST B- 1:4
12.2702
1711
14.31523333 = 15 gals
b. ACRYTEX PRIMER B- 1:4
22.49536667
1705
c. ACRYTEX TOP COAT 1:4 22.49536667

INTERIOR WALL
MATERIALS NEEDED COVERAGE AREA QUANTITY PACKAGING
AREA
1 MASONRY NEUTRALIZER B-44 20 sq.m / 4.25 345.492 1 gal or 3.875 L
4.31865 1.140990753 = 2 gals
L
2 FLAT LATEX B-701 (PRIMER) 4 L and 16 L
c. First Coat 25 sq.m / 345.492 55.27872 25.33608 = 25 pails
d. Second Coat 30 sq.m / 4.0 L 345.492 46.0656 1.34432 = 2 gals
3 MASONRY PUTTY B-7311 25 sq.m / 4.0 L 345.492 55.27872 13.81968 = 14 gals 1L, 4 L and 16 L
4 FLAT LATEX 4 L and 16 L
c. First Coat 25 sq.m / 4.0 L 345.492 55.27872 25.33608 = 25 pails
d. Second Coat 30 sq.m / 4.0 L 345.492 46.0656 1.34432 – 2 gals

TILING WORKS
Republic of the Philippines
CAMARINES NORTE STATE COLLEGE
F. Pimentel Avenue, Brgy. 2, Daet, Camarines Norte – 4600, Philippines

COLLEGE OF ENGINEERING
CHB (Exterior Wall) = 150 mm

CHB (Interior Wall) = 100 mm

First Floor

STORAGE

400 x 400 mm Non Slip Ceramic Floor Tile (Brown)

Plastering = 0.025 m

L = 2800 – 150 – 25 – 25 – 50 – 25 = 2525 mm

W = 2150 – 150 -25 -25 = 1950 mm

Quantity of Tiles at L = 2525/400 = 6.3125

Quantity of Tiles at W = 1950/400 = 4.875

L@2525 = 0.3125 x 0.4 = 0.125

L@1950 = 0.875 x 0.4 = 0.35

Quantity of Tiles = 6 x 4 = 24 + 9 (seruho) = 33 pcs. 400 x 400 mm Non Slip Ceramic Floor Tile (Brown)

TOILET (Ground Floor)

300 x 300 mm Ceramic Floor Tiles (Non Slip)

Plastering = 0.025 m

L = 1700-50-25-50-25 = 1550

W = 2150 – 150 -25 -25 = 1950 mm

Quantity of Tiles at L = 1550/300 = 5.16667

Quantity of Tiles at W = 1950/300 = 6.5

L@1550 = 0.16667 x 0.3 = 0.05

L@1950 = 0.5 x 0.3 = 0.15

Quantity of Tiles = 5 x 6 = 30 + 4 = 34 pcs.

PANTRY

400 x 400 mm Non Slip Ceramic Floor Tile (Brown)

Plastering = 0.025 m

L = 4500-150-25-25-50-25= 4225 mm
Republic of the Philippines
CAMARINES NORTE STATE COLLEGE
F. Pimentel Avenue, Brgy. 2, Daet, Camarines Norte – 4600, Philippines

COLLEGE OF ENGINEERING
W = 2150 – 150 -25 -25 = 1950 mm

Quantity of Tiles at L = 4225/400 = 10.5625

Quantity of Tiles at W = 1950/400 = 4.875

L@4225 = 0.5625 x 0.4 = 0.225

L@1950 = 0.875 x 0.4 = 0.35

Quantity of Tiles = 10 x 4 = 40 + 15 = 55 pcs

DAYCARE

600 x 600 mm Ceramic Tile (White)

Plastering = 0.025 mm

L = 4500 – 150 – 25 – 25 – 50 - 25 = 4225 mm

W = 7850 – 150 – 25 – 25 = 7650 = 7650 mm

Quantity of Tiles at L = 4255/600 = 7.0416667

Quantity of Tiles at W = 7650/600 = 12.75

L@4225 = 0.0416667 x 0.6 = 0.025

L@7650 = 0.75 x 0.6 = 0.45

Quantity of Tiles = 7 x 12 = 84 + 8 = 92 pcs.

PLAY AREA

600 x 600 mm Ceramic Tile (White)

Plastering = 0.025 m

L = 4500 – 150 -25 – 25 = 4300 mm

W = 3900 – 100 – 25 – 25 = 3750 mm

Quantity of Tiles at L = 4300/600 = 7.16667

Quantity of Tiles at W = 3750/600 = 6.25

L@4300 = 0.16667 x 0.6 = 0.100002

L@3750 = 0.25 x 0.6 = 0.15

Quantity of Tiles = 7 x 6 = 42 + 5 = 47 pcs.

RECEIVING AREA
Republic of the Philippines
CAMARINES NORTE STATE COLLEGE
F. Pimentel Avenue, Brgy. 2, Daet, Camarines Norte – 4600, Philippines

COLLEGE OF ENGINEERING
600 x 600 mm CERAMIC TILE (OFF WHITE)

Plastering = 0.025 m

L = 4500 – 150 -25 -25 = 4300 mm

W = 3950 mm

Quantity of Tiles at L = 4300/600 = 7.16667

Quantity of Tiles at W = 3950/600 = 6.58333

L@4300 = 0.16667 x 0.6 = 0.100002

L@3950 = 0.58333 x 0.6 = 0.35

Quantity of Tiles = 7 x 6 = 42 + 8 = 50 pcs.

PORCH

400 x 400 mm Non-Slip Ceramic Floor Tiles (Brown)

Plastering = 0.025 m

L = 4500 mm

W = 900 mm

Quantity of Tiles at L = 4500/400 = 11.25

Quantity of Tiles at W = 900/400 = 2.25

L@4500 = 0.25 x 0.4 = 0.1

L@900 = 0.25 x 0.4 = 0.1

Quantity of Tiles = 11 x 2 = 22 + 4 = 26 pcs.

STAIR PART

L = 1675 mm

W = 2000 – 150 – 25 – 25 = 1800 mm

Quantity of Tiles at L = 1675/400 = 4.1875

Quantity of Tiles at W = 1800/400 = 4.5

L@1675 = 0.1875 x 0.4 = 0.075

L@1800 = 0.5 x 0.4 = 0.2

Quantity of Tiles = 4 x 4 = 16 + 4 = 20 pcs.


Republic of the Philippines
CAMARINES NORTE STATE COLLEGE
F. Pimentel Avenue, Brgy. 2, Daet, Camarines Norte – 4600, Philippines

COLLEGE OF ENGINEERING
Second Floor

STORAGE

400 x 400 mm Non-Slip Ceramic Floor Tiles (Brown)

L = 2350 – 150 – 25 -25 – 50 -25 = 2075 mm

W = 4000 - 150 – 25 – 25 = 3800 mm

Quantity of Tiles at L = 2075/400 = 5.1875

Quantity of Tiles at W = 3800/400 = 9.5

L@2075 = 0.1875 x 0.4 = 0.075

L@3800 = 0.5 x 0.4 = 0.2

Quantity of Tiles = 5 x 9 = 45 + 5 = 50 pcs

PANTRY

400 x 400 mm Non-Slip Ceramic Floor Tiles (Brown)

L = 2150-50-25-50-25 = 2000 mm

W = 4000-150-25-25-50-25 = 3725 mm

Quantity of Tiles at L = 2000/400 = 5

Quantity of Tiles at W = 3725/400 = 9.3125

L@3725 = 0.3125 x 0.4 = 0.125

Quantity of Tiles = 5 x 9 = 45 + 3 = 48 pcs

TOILET

200 x 200 mm Ceramic Tile (Toilet)

L = 1500-50-25-50-25 = 1350 mm

W = 2150-150-25-25 = 1950 mm

Quantity of Tiles at L = 1350/200 = 6.75

Quantity of Tiles at W = 1950/200 = 9.75

L@1350 = 0.75 x 0.2 = 0.15

L@1950 = 0.75 x 0.2 = 0.15

Quantity of Tiles = 6 x 9 = 54 + 16 = 70 pcs.


Republic of the Philippines
CAMARINES NORTE STATE COLLEGE
F. Pimentel Avenue, Brgy. 2, Daet, Camarines Norte – 4600, Philippines

COLLEGE OF ENGINEERING
BARANGAY CAPTAIN’S OFFICE

600 x 600 mm Ceramic Tile (White)

L = 3000-150-25-25-50-25 = 2725 mm

W = 4000-150-25-25-50-25 = 3725 mm

Quantity of Tiles at L = 2725/600 = 4.5416667

Quantity of Tiles at W = 3725/600 = 6.208333

L@2725 = 0.5416667 x 0.6 = 0.325

L@3725 = 0.208333 x 0.6 = 0.125

Quantity of Tiles = 4 x 6 = 24 + 8 =32 pcs

REPUBLIC’S HALL

600 x 600 mm Ceramic Tile (White)

L = 4500-150-25-25 = 4300 mm

W = 6000-50-25-150-25-25 = 5725 mm

Quantity of Tiles at L = 4300/600 = 7.16667

Quantity of Tiles at W = 5725/600 = 9.5416667

L@4300 = 0.16667 x 0.6 = 0.100

L@5725 = 0.5416667 x 0.6 = 0.325

Quantity of Tiles = 7 x 9 = 63 + 10 = 73 pcs

OFFICE

600 x 600 mm Ceramic Tile (White)

L = 4500-150-25-25 = 4300 mm

W = 6000-50-25-150-25-25 = 5725 mm

Quantity of Tiles at L = 4300/600 = 7.16667

Quantity of Tiles at W = 5725/600 = 9.5416667

L@4300 = 0.16667 x 0.6 = 0.100

L@5725 = 0.5416667 x 0.6 = 0.325

Quantity of Tiles = 7 x 9 = 63 + 10 = 73 pcs


Republic of the Philippines
CAMARINES NORTE STATE COLLEGE
F. Pimentel Avenue, Brgy. 2, Daet, Camarines Norte – 4600, Philippines

COLLEGE OF ENGINEERING
BALCONY

400 x 400 mm Non-Slip Ceramic Floor Tiles (Brown)

L = 4500 mm

W = 2000 mm

Quantity of Tiles at L = 4500/400 = 11.25

Quantity of Tiles at W = 2000/400 = 5

L@4500 = 0.25 x 0.4 = 0.1

Quantity of Tiles = 11 x 5 = 55 + 2 = 57 pcs.

STAIR PART

L = 1675 mm

W = 2000 – 150 – 25 – 25 = 1800 mm

Quantity of Tiles at L = 1675/400 = 4.1875

Quantity of Tiles at W = 1800/400 = 4.5

L@1675 = 0.1875 x 0.4 = 0.075

L@1800 = 0.5 x 0.4 = 0.2

Quantity of Tiles = 4 x 4 = 16 + 4 = 20 pcs.

STAIRS

300 x 300 Non-Skid Stair Tile

L = 250 mm

W = 925 mm

Quantity = 0.25 x 0.925 = 0.23125/0.09 = 2.56944 say 3(14) = 42 pcs

H = 200 mm

W = 925 mm

Quantity = 2.05556 say 3(16) = 48 pcs.

L = 925 mm

W = 925 mm

Quantity at L = 925/300 = 3.08333

Quantity at W = 925/300 = 3.08333


Republic of the Philippines
CAMARINES NORTE STATE COLLEGE
F. Pimentel Avenue, Brgy. 2, Daet, Camarines Norte – 4600, Philippines

COLLEGE OF ENGINEERING
L@925 = 0.025 or 25 x 300 mm

Quantity of Tiles = 3 x 3 = 9 + 1 = 10 pcs

Area = 7.053125 sq.m

WALL TILES AT TOILETS (GROUND FLOOR)

300 x 600 mm Ceramic Wall Tiles

A1 = 1.7 x 2.8 = 4.76 m2 – W3 = 4.46 m2

Quantity = 4.46/(0.3x0.6) = 24.7778 say 28 pcs

A2 & A3 = 2(2.15 x 2.8) = 12.04 m2

Quantity = 12.04/0.18 = 66.8889 say 67 pcs

A4 = 1.7 x 2.8 = 4.76 m2 – D3 = 3.29 m2

Quantity = 3.29/0.18 = 18.27778 say 19 pcs

A5 = (1.5 x 2.7) – W3 = 3.75 m2

Quantity = 3.75/0.18 = 20.8333 say 21 pcs

A6 = 2(2.15 x 2.7) = 11.61 m2

Quantity = 11.61/0.18 = 64.5 say 65 pcs

A7 = (1.5 x 2.7) – D3 = 2.58 m2

Quantity = 2.58/0.18 = 14.333 say 15 pcs.

SUMMARY

400 x 400 Non Slip Ceramic Tile (Brown) = 309 pcs.

300 x 300 Ceramic Floor Tile (Non Slip) = 34 pcs.

600 x 600 Ceramic Tile (White) = 317 pcs.

600 x 600 Ceramic Tile (Off White) = 50 pcs.

200 x 200 Ceramic Tile = 70 pcs.


Republic of the Philippines
CAMARINES NORTE STATE COLLEGE
F. Pimentel Avenue, Brgy. 2, Daet, Camarines Norte – 4600, Philippines

COLLEGE OF ENGINEERING
300 x 300 Non Skid Stair Tile = 100 pcs.

300 x 600 Ceramic Wall Tiles = 215 pcs.

Tile Adhesive

400 x 400 Non Slip Ceramic Tile (Brown)

Area = 47.5775 sq.m

Tile Adhesive = 47.5775 sq.m/2.6 sq.m = 18.3 say 19 bags

Tile Grout = 11.894375 say 12 bags

300 x 300 Ceramic Floor Tile (Non Slip)

Area = 3.0225 sq.m

Tile Adhesive = 3.0225/2.6 = 1.1625 say 2 bags

Tile Grout = 0.756 say 1 bag

600 x 600 Ceramic Tile (White)

Area = 107.831875 sq.m

Tile Adhesive = 107.831875/2.6 = 41.5 say 42 bags

Tile Grout = 27 bags

600 x 600 Ceramic Tile (Off White)

Area = 16.985 sq.m

Tile Adhesive = 16.985/2.6 = 6.53 say 7 bags

Tile Grout = 3 bags


Republic of the Philippines
CAMARINES NORTE STATE COLLEGE
F. Pimentel Avenue, Brgy. 2, Daet, Camarines Norte – 4600, Philippines

COLLEGE OF ENGINEERING

200 x 200 Ceramic Tile

Area = 2.6325 sq.m

Tile Adhesive = 2.6325/5 = 0.53 say 1 bag

Tile Grout = 1 bag

300 x 300 Non Skid Stair Tile

Area = 7.053125 sq.m

Tile Adhesive = 2.7 bags say 3 bags

Tile Grout = 1.76 bags say 2 bags

300 x 600 Ceramic Wall Tiles

Area = 37.73 sq.m

Tile Adhesive = 37.73/2.6 = 14.5 say 15 bags

Tile Grout = 9.4 bags say 9 bags

Topping/Dry Pack

400 x 400 Non Slip Ceramic Tile (Brown)

Area = 47.5775 sq.m

Cement = 21 bags

Sand = 1.8 cu.m

300 x 300 Ceramic Floor Tile (Non Slip)

Area = 3.0225 sq.m

Cement = 2 bags

Sand = 0.2 cu.m

600 x 600 Ceramic Tile (White)

Area = 107.831875 sq.m

Cement = 48 bags
Republic of the Philippines
CAMARINES NORTE STATE COLLEGE
F. Pimentel Avenue, Brgy. 2, Daet, Camarines Norte – 4600, Philippines

COLLEGE OF ENGINEERING
Sand = 4 cu.m

600 x 600 Ceramic Tile (Off White)

Area = 16.985 sq.m

Cement = 8 bags

Sand = 0.7 cu.m

200 x 200 Ceramic Tile

Area = 2.6325 sq.m

Cement = 1 bag

Sand = 0.085 cu.m

300 x 600 Ceramic Wall Tiles

Area = 37.73 sq.m

Cement = 17 bags

Sand = 1.5 cu.m

PLUMBING WORKS

SEWER LINE
1. PVC PIPES
6" / 152mm PVC pipe 3 pcs
4" / 100mm PVC pipe 6 pcs
3" / 100mm PVC pipe 1 pc
2. Clean Out
4" Clean out 2 pcs
3. P-trap
4" P-trap 2 pcs
4. PVC Wye
4" x 4" Wye 4 pcs
5. PVC Cross Wye
4" x 4" Cross Wye 1 pc
6. PVC Elbow 90
SANITARY LINE
1. PVC PIPES
50 mm PVC pipe 1 pc
Republic of the Philippines
2" LAV PVCCAMARINES
pipe 1 pc
NORTE STATE COLLEGE
2. Clean Out
F. Pimentel Avenue, Brgy. 2, Daet, Camarines Norte – 4600, Philippines
2" Clean Out 2 pcs
COLLEGE OF ENGINEERING
3. P-trap
4" x 4" PVC Elbow 90 2 pcs 2" P-trap (FD) 2 pcs
2" P-trap (LAV) 4 pcs
4. PVC Wye
WATER LINE
4" x 2" Wye 4 pcs
1. PVC PIPES
5. PVC Elbow 90
25 mm 7 pcs
2" x 2" PVC Elbow 90 5 pcs
20 mm SH 1 pc
6. Tee
20 mm WC 1 pc
4" x 4" Tee 1 pc
20 mm LAV 1 pc
2" x 2" Tee 2 pcs
2. Angle Valve
4" x 3" Tee 1 pc
25 mm 6 pcs
7. Catch Basin
3. Tee
8 pcs
25 x 25 mm 6 pcs
8. Bushing Reducer
4. Tee with Thread
4" x 2" Bushing Reducer 2 pcs
Tee with Thread 3 pcs
5. Elbow 90
25 x 25 mm 12 pcs
6. Elbow 90 with Thread
25 x 20 mm 9 pcs
7. Faucet
Lav/Sink 4 pcs
Shower Faucet 1 pc
8. Water Closet
2 pcs
9. Gate Valve
1 pc
10. Check Valve
1 pc
11. Water Meter
1 pc

ELECTRICAL WORKS

Lighting
18W LED Surface Mounted Square Light 37 pcs
12W LED Light Bulb 8 pcs
Ceiling Receptacle 8 pcs
Duplex Receptacle Outlet 27 pcs
3-Gang Switch Flush Type with Switch
Plate 4 pcs
2-Gang Switch Flush Type with Switch
Plate 8 pcs
1-Gang Switch Flush Type with Switch
Plate 4 pcs
Switch Fan 6 pcs
6x6 junction box 11 pcs
Republic of the Philippines
CAMARINES NORTE STATE COLLEGE
F. Pimentel Avenue, Brgy. 2, Daet, Camarines Norte – 4600, Philippines

COLLEGE OF ENGINEERING
2x4 utility box 39 pcs

Wires and Fixtures


3.5mm THHN CU. Wire, Stranded, 15
AT (20 mm Ø PVC Electrical Pipe for LO) 66.25 m
3.5mm THHN CU. Wire, Stranded, 20
AT (20 mm Ø PVC Electrical Pipe for LO) 21.23 m
3.5mm THHN CU. Wire, Stranded (20
mm Ø PVC Electrical Pipe for CF) 34.75 m
3.5mm THHN CU. Wire, Stranded (20
mm Ø PVC Electrical Pipe for CO) 55.3 m
3.5mm THHN CU. Wire, Stranded (20
mm Ø PVC Electrical Pipe for 1-gang) 10 m
3.5mm THHN CU. Wire, Stranded (20
mm Ø PVC Electrical Pipe for 2-gang) 21 m
3.5mm THHN CU. Wire, Stranded (20
mm Ø PVC Electrical Pipe for 3-gang) 11.5 m
Flexible Hose 3/4"Ø 1 roll
3-gang Convenience outlet with cover 23 pcs
2-gang Convenience outlet with cover 10 pcs
1-gang Convenience outlet with cover 1 pcs

Panel Board and Breakers


Koten Premium Panel Board Box, 14
pc 4749.00
branches 1