Professional Documents
Culture Documents
TABLE OF CONTENTS
1.0 SCOPE
3.1 General
3.2 Cell Design
3.3 Cell Selection Criteria
4.1 General
4.2 Number of Cells
4.3 Charging Rate
4.4 Other Considerations
4.5 Duty Cycle
4.6 Cell Sizing Calculations
5.0 BIBLIOGRAPHY
APPENDIX – I Lead Acid Battery and Nickel Cadmium Battery Sizing Calculation
for Typical Substation
1.0 SCOPE
1.1 This Engineering Standard establishes general guidelines, parameters and design
criteria for the selection and sizing of lead acid and nickel cadmium storage batteries
intended to be used in the system of National Grid SA.
1.2 The text includes methods for defining loads and factors relating to cell selection to
ensure adequate battery capacity for specific applications.
Generally, the following parameters as specified in TES-P-119.02 are adopted for the DC
control systems in National Grid SA substations:
Note: The maximum equalizing voltage is taken as 1.6 volt per cell for Nickel Cadmium
Ni-Cd battery, maximum load voltage to be limited to 135.14 V by dropper diodes in the
charger.
Float charging voltage per cell : Generally, 2.15 V - 2.25 V for Lead
Acid batteries and 1.38 V - 1.42 V for
Nickel Cadmium batteries, for accuracy
it shall be based on manufacturer's
recommendation of specific
battery to be used.
3.1 General
The cell selection of a storage battery is dependent upon the application and its
expected performance. The DC system design considers float battery operation with
battery charger serving to maintain the battery in a fully charged condition as well as
to supply the normal DC load. The batteries are put in equalizing mode without
disconnecting the batteries or the DC load from the bus. At the time of equalizing, all
the connected DC equipment is subjected to the maximum voltage of 135.14 V.
Several basic factors govern the size (number of cells and rated capacity) of the
battery. Included are the maximum system voltage, the minimum system voltage, the
duty cycle, correction factors, and design margin. Because a battery string is usually
composed of a number of identical cells connected in series, the voltage of the
battery is the voltage of a cell multiplied by the number of cells in series. The
ampere-hour capacity of a battery string is the same as the ampere-hour capacity of a
single cell.
In general, cell selection shall be made with the objective of meeting the load
requirements using the most economical battery which has long life and requires
minimum maintenance.
The Lead Acid batteries being economical, having high overcharge tolerance, less
self-discharge, low maintenance requirements (may be in the form of equalizing or
topping charge) and less toxic when compared with Nickel Cadmium batteries, shall
be used. Moreover, Nickel cadmium can also be a choice.
a. For Lead Acid cells, the positive plate configuration is either of the three
categories :
Tubular
Classification according to cell material falls into pure lead (plante), lead
antimony and lead calcium alloys. The lead alloys compositions are however,
mostly used in National Grid SA system.
Latest hybrid systems of alloys which offer longer l ife and less maintenance can also be
applied as per NG approval.
3.3.1 General
a. Load Requirements
b. Expected Life of the Cell and Planned life of the installation
c. Ambient Temperature
d. Maintenance Requirements
e. Physical Characteristics such as dimension and weight of the cells,
container material, inter cell connectors, and terminals
f. Economic Considerations
g. Charging characteristics
h. Frequency and depth of discharge
i. Ventilation requirements
j. Shock and vibration
3.3.2 Cell performance may largely affect its selection. A comparison of lead acid
cell performance characteristics based on material composition and plate
design is highlighted in Table 1 and Table 2, respectively.
Note: Lead calcium positive plates may grow in length and width because of grid oxidation
at the grain boundaries. This oxidation is usually caused by long term overcharging which is
common to batteries on constant float Grids may grow in size sufficiently to cause buckling
or rupture of their containers. Lead calcium plate batteries are not recommended for use in
National Grid SA system.
3.3.3 High ambient temperatures above 25 °C (77 °F) result in reduced life due to
accelerated chemical reaction. As a general rule of thumb, for every 9°C (15°F)
increase in electrolyte temperature above 25°C (77°F), the cell life is halved.
3.3.4 Nickel cadmium, and other approved new technology batteries can sustain high
temperature more easily than the lead acid ones.
4.1 General
4.1.1 The number of cells and rated capacity, is primarily determined by the
following three (3) factors.
4.1.2 Conditions such as ambient temperature, discharge rate and final cell voltage
directly influence the available cell capacity. Hence, it is imperative that cell
capacity (expressed in ampere hours - Ah) shall always relate to the standard
conditions specified in 46-TMSS-01 for Lead Acid and 46-TMSS-06 for
Nickel Cadmium batteries and reproduced as under:
For Lead Acid cell sizing temperature correction factors, refer to Table 4
extracted from IEEE Std. 485 and for discharge current temperature
correction factors, reference shall be made to IEEE Std. 450.
For Nickel Cadmium cell, reference shall be made to IEEE 1115 and the
battery manufacturer’s data should be consulted for capacity derating factors
for various discharge time and electrolyte temperatures. If the expected
electrolyte temperature is above 25ºC, generally there is no noticeable
increase in the available capacity.
4.1.4 The Ampere-hour capacity of the entire battery bank shall be same as that of
a single cell which depends on the size and number of plates. Parallel
connections of low capacity cells to obtain the specified capacity is not
permissible.
4.2
4.3 Number of Cells
The number of cells is influenced by the maximum and minimum system voltages as
follows:
a. The number of cells governed by maximum system voltage as per IEEE 1818
Clause 5.2.5.4 Equation 14 is defined as:
(1)
Both the abovementioned formulas can be used for Lead Acid battery while for
Nickel Cadmium battery only formula (2) is applicable.
Based on the voltage window 101.5 V- 135.14 V as specified in clause 2.0 and lead
acid battery with equalizing voltage 2.33 V per cell, SEC has standardized 58 battery
cells for 125 V nominal DC system voltage.
For 125 V DC system voltage with Nickel Cadmium battery bank, considering the
minimum system voltage of 101.5 V and end of discharge voltage as 1.1 V, the
number of nickel cadmium cells shall be calculated on case to case basis as per
required nominal and permissible minimum and maximum DC system voltages and
in the light of self-discharge and charging time as limiting factor, which may result
in using larger cell that would otherwise have been necessary (Refer IEEE 1115).
Dropping diodes may be used in the circuit to avoid overvoltage beyond permissible
limits as indicated in 46-TMSS-02.
The specified recharge time influences the cell size. Hence, the number of cells and
size shall be selected so as to be recharged to 100% capacity within the
specified/available time shown in Table 3 for different applications.
The following factors also influence the final choice of the cell size; hence these
must be duly taken into account during the course of calculations.
High temperature accelerates the chemical reactions, thus increases the cell
capacity and decreases the expected life. The converse is true for low
temperatures. The standard temperature for stating cell capacity is 25°C
(77°F) as specified in clause 4.1.2. If the cell temperature is expected to be
less than 25°C (77°F) the cell size shall be adequately increased by
multiplying with the correction factor indicated in Table 4.
For SEC applications, generally the battery sizing calculations shall be done
at an assumed cell temperature of 10ºC (50ºF) which corresponds to
temperature correction factor of 1.19 for lead acid battery.
Capacity decreases gradually during battery life cycle. Aging factor allows
the battery to meet its duty cycle as it reaches the end of its expected life. A
factor of 1.25 for Lead Acid and Nickel Cadmium batteries shall be used.
The battery is thus sized to carry the load until the capacity has decreased to
80% of its rated capacity.
4.5.1 General
Duty cycle is defined as the load currents a battery is expected to supply for
specified time periods under specific modes of application. It, therefore,
requires that each load be correctly assessed and identified as to its inception
and duration. Sizing of a cell is based upon the duty cycle. Therefore, careful
development of duty cycle is the key to proper sizing.
a. Continuous Loads
These loads initiate at the very inception of the duty cycle and remain
energized throughout the duty cycle period. Typical loads include:
i. Indicating lights
ii. Lighting
iii. Continuously operating motors
iv. Converters (e.g., inverters, dc-dc converters)
v. Communication systems
vi. Microprocessors and computer devices
vii. Annunciation/alarm systems
viii. Continuously energized coils
ix. Other continuous loads
The battery shall be sized to feed these continuous loads for the full
durations of battery discharge as indicated in Table 5 below.
Note: For remote substations, more than 100 kM area from city if not
specified in the PTS the discharge duration shall be 14 hours.
b. Non-Continuous Loads
i. Emergency Loads
TESP10302R01/RBA Date of Approval: March 17, 2020 PAGE 9 OF 27
TRANSMISSION ENGINEERING STANDARD TES-P-103.02, Rev.01
These loads may be initiated any time during duty cycle and are supplied
for a particular period of time. These loads may be categorized as :
Emergency lighting
Emergency motors
Fire protection systems actuations
Motor-driven valve operations (stroke time >1 minute)
Critical ventilation system motors
Switchgear operations
Motor-driven valve operations (stroke time <1 minute)
Isolating switch operations
Field flashing of generators
Motor starting currents
Inrush currents
Other Loads
Loads that occur at any time in a duty are termed "Random" loads. These
may be either non-continuous or momentary. These loads are however
not considered for sizing battery in National Grid SA applications.
a. Once the duty cycle loads are correctly identified and tabulated, a duty
cycle profile based on these loads can be subsequently developed
showing the anticipated inception and shutdown times. Such a graphical
representation of all possible load combinations and variations helps in
better analysis of battery duty cycle.
iii. Loads with indefinite shut down times shall be assumed to continue
through the rest of the duty cycle.
4.6.1 The following cell sizing calculations methods for lead acid and nickel
cadmium battery are based on IEEE standard 485 and IEEE 1115
respectively. A specially developed Work Sheet with example of its use is
also included to facilitate the calculation process. Figure 1 illustrates a
generalized duty cycle profile for foregoing discussions. The method is a
simple iterative technique wherein each section of duty cycle profile is
individually analyzed. If the current in succeeding section say N+1 is greater
than the current in preceding section N, no sizing calculations is required for
section N since section N+1 will always require a larger battery than section
N.
4.6.2 The formulas for sizing both lead acid and nickel cadmium batteries are
given below:
S 1
S=1 P=1 (4)
A A( P 1) K t Tt
S= N S N P =S
max FS max P (5)
S=1 S1 P =1
Where,
Where,
4.6.3 Any fractional cells computed as a result of calculations, shall be rounded off
to nearest whole number.
The cell size thus finally calculated shall be the optimum size for specific
application and shall have enough capacity to carry the combined loads
during the duty cycle.
The cell size thus selected usually does not match with the commercially
available sizes. Under this situation, the next higher capacity cell shall be
selected which further introduces additional degree of conservatism in cell
sizing calculations.
5.0 BIBLIOGRAPHY
5. IEEE 485 Recommended Practice for Sizing Lead Acid Batteries for Stationary
Applications.
6. IEEE 1115 Recommended Practice for Sizing Nickel Cadmium Batteries for
Stationary Applications
8. IEEE 1184 IEEE Guide for the Selection and Sizing of Batteries for
Uninterruptible Power Systems
9. IEEE 1818 IEEE Guide for the Design of Low-Voltage Auxiliary Systems for
Electric Power Substations
10. IEEE 1189 IEEE Guide for Selection of Valve-Regulated Lead-Acid (VRLA)
Batteries for Stationary Applications
APPENDIX - I
1.0 GENERAL
The provided sample calculations basically are for battery size of 132kV, 115 kV, and 110
kV Unified substations based on recommendations by National Grid SA study comprising of
12 bays details highlighted in the appendix. This is only a sample that will serve as a
calculation guide in determining the requirements, however to calculate the exact project
requirements actual project data shall be applied.
An assumed summary of the equipment-wise load is indicated in section 4, below. The load
profile thus developed (refer to section 6) based from the Unified Substation arrangement
fairly depicts the load requirements for sizing the most economical battery.
The condition applied is that battery and charger are continuously connected to the
loads.
Wherein:
101.5
End of discharge voltage = 1.75 V/cell
58
2.2 The duration of continuous loads is taken as 10 hours in general. The duration of
other loads is based on National Grid SA practice/design criteria. However, for
remote substations the working committee/engineer who finalizes the PTS for the
concerned project, will decide the duration of continuous load.
2.3 Normally the battery room temperature is maintained at 25°C. Standardization takes
into account the following factors :
2.4 Worst contingency case for assessing the momentary loads takes into consideration
the following assumptions:
a. Simultaneous tripping of one (1) Line and one (1) Transformer which involves
tripping of four (4) HV breakers.
b. The simultaneous bus fault on both 13.8 kV buses, which calls for tripping of 30
Nos. 13.8 kV breakers; via the simultaneous operation of bus differential
protection. It is also assumed that either one of the outer bus sections acts as a
standby.
• Closing of one breaker (Even if it is assumed that the mechanism of one breaker
fails, the second breaker will be closed after the failure of the first. The total
momentary load will be one after another and will not be for more than one
minute).
• Simultaneous closing of one incomer, and one outgoing feeder (controlling the
station service transformer) and tripping of one breaker if fault persists. It also
considers that one spring charging motor is in the process of starting and one
motor is running.
2.5 Starting current of spring charging motor is taken as 5 times the normal current.
2.6 DC load assessment does not include emergency exit lights and other lights which are
equipped with self-contained rechargeable battery packs.
2.8 Actual cell sizing is shall be based on Performance curves/data of one of the Listed
manufacturers.
3.0 SCOPE
Six (6) lines and three (3) 50/67 MVA Power Transformers, details are below;
6.0 DUTY CYCLE (D.C. LOAD PROFILE) & CELL SIZING CALCULATIONS:
6.1 Based upon above loads the duty cycle is drawn. It is to be noted that the duty cycle
does not include any spare capacity as this is accounted for by the design margin
factor (Kd).
6.2 The Duty cycle includes loads at the end of the cycle which are required for restart,
ensuring that there should be enough energy in the battery at the end of the duty
cycle to close the breakers upon restoration of AC supply.
a) Load Summary:
KT factors used for calculation are tabulated as below. The actual KT factors shall be
obtained on the basis of the suppliers’ curve for the respective battery:
Note: Interpolation method was used to get the mid values for Kt factor (Y Company).
However, for more accurate results battery manufacturer shall be consulted for Kt and
Temperature factor values. It various from manufacturer to manufacturer.
Time to
Capacity
Change in Duration End Positive Negative
Period Load (A) Rating
Load of Period Section Values Values
Factor, Kt
(Min)
Section 1-First Period Only – if A2 is greater than A1, go
NO
to Section 2 - NO
A1=789. A1-
1 M1=1 T1=1 1.4686 1159.1366 0.00
28 0=789.28
Total 1159.1366
Time to Capacity
Change in Duration of Positive Negative
Period Load (A) End Rating
Load Period Values Values
Section Factor, Kt
Section 2-First 2 Periods Only – if A3 is greater than A2, go to
YES
Section 3 - YES
A1-
1 A1=789.28 M1=1 T1+T2=180 3.4647 2734.6184 0.00
0=789.28
A2-A1=
2 A2=201.28 M2=179.00 T2=179.00 3.4535 0.00 -2030.66
-588.00
Sub Total 2735.1035 -2030.66
Total 703.9584
Time to Capacity
Change in Duration of Positive Negative
Period Load (A) End Rating
Load Period Values Values
Section Factor, Kt
Section 3-First 3 Periods Only – if A4 is greater than A3, go to
NO
Section 4 - NO
A1- T1+T2+T3
1 A1=789.28 M1=1 5.3546 4226.2787 0.00
0=789.28 =360.00
A2-A1= T2+T3=
2 A2=201.28 M2=179.00 5.3443 0.00 3142.4484
-588.00 359.00
3 A3=210.88 A3-A2=9.6 M3=180.00 T3=180.00 3.4647 33.2611 0.00
Sub Total 4259.5398 -3142.45
Total 1117.0898
Capacity
Change in Duration of Time to End Positive Negative
Period Load (A) Rating
Load Period Section Values Values
Factor, Kt
Section 4-First 4 Periods Only – if A5 is greater than A4, go to
YES
Section 5 - YES
A1- T1+T2+T3+T4
1 A1=789.28 M1=1 8.5600 6756.2368 0.00
0=789.28 =600.00
A2-A1= T2+T3+T4=
2 A2=201.28 M2=179.00 8.5500 0.00 -5027.4
-588.00 599.00
A3-
3 A3=210.88 M3=180.00 T3+T4=419.00 5.9810 57.4176 0.00
A2=9.6
A4-A3=
4 A4=201.28 M4=239.00 T4=239.00 4.0830 00 -39.1968
-9.6
Sub Total 6813.6544 -5066.5968
Total 1747.0576
Capacity
Change in Duration of Time to End Positive Negative
Period Load (A) Rating
Load Period Section Values Values
Factor, Kt
Section 5-First 5 Periods Only – if A6 is greater than A5, go to
YES
Section 6 - YES
A1- T1+T2+T3+T4
1 A1=789.28 M1=1 8.5610 6757.0261 0.00
0=789.28 =600.00
A2-A1= T1+T2+T3+T4
2 A2=201.28 M2=179.00 8.5610 0.00 -5033.868
-588.00 = 600.00
A3-
3 A3=210.88 M3=180.00 T3+T4=419.00 5.9900 57.504 0.00
A2=9.6
A4-A3=
4 A4=201.28 M4=239.00 T4+T5=240.00 4.0940 0.00 -39.3024
-9.6
A5-
5 A5=242.08 M5=1.00 T5=1.00 1.4686 59.9189 0.00
A4=40.8
Sub Total 6874.45 -5074.22
Total 1800.23
Lead Acid Battery shall be selected as per the available Battery Manufacturers catalog’s
nearest highest capacity rating.
The condition applied is that battery and charger are continuously connected to
the loads.
7.2 Similar assumptions applied with Lead Acid Battery for Scope, Conditions, DC
Load details and estimation, will be considered for Nickel Cadmium battery
calculations.
7.3 Duty Cycle (DC Load Profile) & Cell Sizing Calculations:
7.3.1 Based upon above loads the duty cycle is drawn. It is to be noted that the
duty cycle does not include any spare capacity as this is accounted for by the
design margin factor (Kd).
7.3.2 The Duty cycle includes loads at the end of the cycle which is required for
restart, ensuring that there should be enough energy in the battery at the end
of the duty cycle to close the breakers upon restoration of A.C.
a) Load Summary:
Kt factors used for calculation are tabulated as below for typical Nickel-
Cadmium cell referred in Table -10. The actual Kt factors shall be obtained on
the basis of the suppliers curve for the respective battery. Designer should make
sure that capacity rating factors (Kt) obtained from the manufacturer is based on
constant potential operation.
Table – 8
Discharge Time t1 Time t2 (1) (2) Factor Factor Factor
time t from from Amperes Amperes Kt1for Kt2for Kt for
(min) data data for time t1 for time t2 time t1 time t2 time t
(min) (min) (A) (A) 369 ÷ 369 ÷
(1) (2)
1 1 -- 627 -- 0.589 -- 0.589
179 120 180 138 107 2.67 3.45 3.44
180 180 -- 107 -- 2.05 -- 3.45
359 300 480 72.0 45.4 5.13 8.13 6.11
360 300 480 72.0 45.4 5.13 8.13 6.13
539 480 720 45.4 29.83 8.13 12.37 9.17
540 480 720 45.4 29.83 8.13 12.37 9.19
718 480 720 45.4 29.83 8.13 12.37 12.33
719 480 720 45.4 29.83 8.13 12.37 12.35
720 720 -- 29.83 12.37 12.37
Table -9
Discharge Temperature derating Discharge time (t) Temperature
time (t min) factor (Tt) at 10 °C correction factor (Tt) at
10 °C
1 1.1 539 1.04
179 1.05 540 1.04
180 1.05 718 1.04
359 1.04 719 1.04
360 1.04 720 1.04
Table - 10
Hypothetical discharge currents for KM cell range manufactured by ABC Company (Discharge
amperes to 1.1 V/cell after prolonged float charging)
The Kt factor for time t is calculated in the following table by interpolation using the
formula
K t K t2
K t 2 K t1 t 2 t
t 2 t1
Note that interpolation must be performed only on the Kt factors. Interpolation of current
will yield incorrect results.
Time to Temperat
Capacity
Perio Change in Duration End ure Positive Negative
Load (A) Rating
d Load of Period Section Derating Values Values
Factor, Kt
(Min) Factor
Section 1-First Period Only – if A2 is greater than A1, go to
NO
Section 2 - NO
1 A1=789. A1- M1=1 T1=1 1.090 1.100 946.3467 0.00
28 0=789.28 Total 946.3467
Temperat
Time to Capacity
Perio Change in Duration ure Positive Negative
Load (A) End Rating
d Load of Period Derating Values Values
Section Factor, Kt
Factor
Time Temperat
Capacity
Perio Change in Duration of to End ure Positive Negative
Load (A) Rating
d Load Period Sectio Derating Values Values
Factor, Kt
n Factor
Section 3-First 3 Periods Only – if A4 is greater than A3, go
NO
to Section 4 - NO
T1+T2
5138.528
1 789.28 A1-0=789.28 M1=1 +T3=3 6.260 1.040 0.00
5
60.00
T2+T3 -
A2-A1= -
2 201.28 M2=179.00 =359.0 6.240 1.040 0.00 3815.884
588.00
0 8
T3=18
3 210.88 A3-A2=9.6 M3=180.00 3.830 1.040 38.2387 0.00
0.00
Sub Total 5176.77 -3815.88
Total 1360.89
Time Temperat
Capacity
Load Change in Duration of to End ure Positive Negative
Period Rating
(A) Load Period Sectio Derating Values Values
Factor, Kt
n Factor
Section 4-First 4 Periods Only – if A5 is greater than A4, go
YES
to Section 5 - YES
A1=78 7863.754
1 A1-0=789.28 1 599.00 9.580 1.04 0.00
9.28 5
A2=20 A2-A1= -
2 179.00 598.00 9.560 1.04 0.00 -5846.13
1.28 588.00
A3=21
3 A3-A2=9.6 180.00 419.00 7.180 1.04 71.685 0.00
0.88
A4=20
4 A4-A3=-9.6 239.00 239.00 4.620 1.04 00 -46.1261
1.28
Sub Total 7935.44 -5892.26
Total N/A 2043.18
Time Temperat
Capacity
Load Change in Duration of to End ure Positive Negative
Period Rating
(A) Load Period Sectio Derating Values Values
Factor, Kt
n Factor
Section 5-First 5 Periods Only – if A6 is greater than A5, go
YES
to Section 6 - YES
A1=78
1 A1-0=789.28 1 600.00 10.050 1.040 8249.555 0.00
9.28
A2=20 A2-A1= -
2 179.00 599.00 10.030 1.040 0.00 -6133.55
1.28 588.00
A3=21
3 A3-A2=9.6 180.00 420.00 7.190 1.040 71.785 0.00
0.88
A4=20
4 A4-A3=-9.6 239.00 240.00 4.630 1.040 0.00 -46.23
1.28
A5=24
5 A5-A4=40.08 1.00 1.00 1.090 1.100 48.156 0.00
2.08
Sub Total 8369.5 -6202.7
Total 2166.8
Nickel Cadmium Battery shall be selected as per the available Battery Manufacturers
catalog’s nearest highest capacity rating.
8.0 CONCLUSION
88.1 As per above calculation the minimum battery size for 132kV, 115 kV or 110 kV
substation with scope as described in section 3 for Lead Acid Battery is 2950 Ah and
for Nickel Cadmium 3000 Ah 10 hours duration basis.
88.2 The presented calculations shall be used as a guideline only. The contractor/designer
shall however, compute the required battery size for each project based on above
respective guidelines. The appropriate size of the battery to be supplied shall be
verified as per actual load requirements.