Professional Documents
Culture Documents
Nabiac Borefield Stage 2B Pump Stations Pre Tender Meeting Minutes With Q&A
Nabiac Borefield Stage 2B Pump Stations Pre Tender Meeting Minutes With Q&A
Purpose:
To discuss the tendering process for the construction of the NA-WPS-00 100912.11 Nabiac
Borefield Stage 2B Pump Stations Contract Number: 100912.12 including:
Thursday 1st February 2024
Meeting No: 1
Time 12:00pm (Midday)
Location MidCoast Council, Nabiac WTP and Borefield
Project Number 100912.12
Attendees MidCoast Council
• Bill Baines
• Jesse Spencer
• Adam Gregory
Contractors:
As per attendance sheet:
NA-WPS-00 100912.12 Nabiac Borefield Stage 2B Pump Stations Pre
Tender Meeting Attendance Register - 01.02.2024
Agenda:
The mandatory pre-tender meeting for the NA-WPS-00 100912.12 Nabiac Borefield Stage 2B Pump
Stations Contract Number: 100912.12 was held at the MidCoast Water Treatment Plant on
Aerodrome Road, Nabiac. The meeting was followed by a site visit throughout the Borefield.
The specific points raised, questions asked and required actions to be taken are summarised in the
table below.
Acknowledgement of Country
We acknowledge the traditional custodians of the land on which we work and
live, the Gathang-speaking people and pay our respects to all Aboriginal and
Torres Strait Islander people who now reside in the MidCoast Council area.
We extend our respect to elders past and present, and to all future cultural-
knowledge holders.
2 Attendee Introductions
- Ensure all attendee’s sign attendee sheet including company they
represent and contact details.
3 Contract Information
- AS2124 will be the contract utilised for the works.
- It is important to review the contract documents, in particular Part
1B because there are some terms and conditions unique to MCC
Water Project Delivery.
4 Tendering
- Tender assessment procedure by MidCoast Council is outlined in
section 1 of Part 1A TENDER REQUIREMENTS & PRELIMINARIES.
- Tenderers are to accurately complete all of the Part 1C Tender
Schedules for consideration in the tender.
- Tenderers are required to prepare a Detailed Construction
Program/schedule for the work to be done under the engagement.
- Tenderers are to provide details in tender submissions that
demonstrate an understanding of the contract requirements e.g. tilt
panels to be cast onsite/offsite, proposed environmental controls for
working above an aquifer.
- Price will be assessed but MCC do not necessarily accept the lowest
bid.
- If the tenderer is unsure about the contract requirements please ask
questions using VendorPanel.
NA-WPS-00 100912.12 Nabiac Borefield Stage 2B Pump Stations Pre Tender Meeting Minutes with Q&A4
Contract 100912.12 2
Contract Number: 100912.12
6 Contract Preliminaries
- Preliminaries are required prior to start of works.
- Possession of site will not be granted until the preliminaries and any
other required documents are provided by the Contractor.
- Construction Insurance will be covered by the contractor.
- Long Service Levy payment is required to be paid by the winning
contractor and a receipt is required to be submitted as documented
evidence.
- Contract security is required under the contract for the amount of
5% in bank guarantees. This is done as two bank guarantees of 2.5%
each.
7 Site
- The Water Treatment Plant, Water reticulation network and
Borefield site will remain operational.
- Adam Gregory and Jesse Spencer will provide most of the
surveillance for this project and will be setup in a demountable at
the WTP.
- MCC operational staff will be required to conform to the successful
contractor’s site induction and general WH&S within the
construction site boundaries.
- The successful contractor shall not operate any existing services
without written approval from MCC.
- The site during wet conditions can have a high-water table which the
contractor is to allow for.
NA-WPS-00 100912.12 Nabiac Borefield Stage 2B Pump Stations Pre Tender Meeting Minutes with Q&A4
Contract 100912.12 3
Contract Number: 100912.12
8 Site utilities
- There is no sewerage reticulation onsite. The Contractor shall make
the necessary arrangements to provide for sewerage on site as
needed, and at the Contractors expense.
- Contractor shall allow for the required site amenities and is required
to provide all site amenities for their subcontractors.
- Power supply to be used during the construction of the works is the
Contractor’s responsibility. However, contractor can access
reasonable power for site sheds from site power. Connection to site
power made at contractor’s expense.
- The Contractor shall make the necessary arrangements to provide
potable water on site, and to the Contractors expense.
12 Site Inspection
- A site inspection for tenderers to visit the Borefield will follow the
meeting so that site conditions are understood.
13 Questions
- Questions after the meeting shall be raised through the tender
portal.
- MCC will provide these minutes and attendance sheets via Vendor
Panel as PDF documents that form part of the contract.
MCC Question – From the tender documents are the limits of contract
understood?
NA-WPS-00 100912.12 Nabiac Borefield Stage 2B Pump Stations Pre Tender Meeting Minutes with Q&A4
Contract 100912.12 4
Contract Number: 100912.12
Answer - If the tenderer has any queries on the expectations of the contract
could they please ask for clarification on VendorPanel. To ensure everyone is
pricing the same job we would like any ambiguity to be cleared up before the
end of the tendering period.
Question – Stowe are currently running cables and conduit. Are the borehut
slab conduits to be installed under this contract?
Answer – Conduits by the contractor as per the drawings. The pulling of the
cables through the conduits will be in a separate contract.
Question – What is the pump’s power cable fixing arrangement? And what is
the fixing method?
Answer – The cables for the pumps and hydrostatic level device are to be
attached within the well casing on to the pipework using stainless steel cable
ties at 450mm spacings.
Question – Have the bores been drilled? Have they run? Would we expect
blockages during commissioning?
Answer – The bores have been drilled and ran for flow testing and capped. It
is not expected that blockages should occur during commissioning.
Question – Pipe Schedule item 6 lists tapping band, pressure gauge ball
valves and associated fittings? What are the associated fittings?
Answer – Existing pipework can use the existing tapping band but for the
new pipework the associated fittings are to be:
Question – Do the lift points at the top of bore pipework need certification?
Answer – Required to be built to the requirements of drawings.
Question – Who have MCC used previously for stainless steel pipework?
Answer – Oliver Ivers Engineering have been used for all the stainless in the
borefield. The tenderer does not have to use Oliver but MCC have a great
working history with him.
NA-WPS-00 100912.12 Nabiac Borefield Stage 2B Pump Stations Pre Tender Meeting Minutes with Q&A4
Contract 100912.12 6
Contract Number: 100912.12
End.
Distribution: All MidCoast Council attendees and on the Vendor Panel Portal.
NA-WPS-00 100912.12 Nabiac Borefield Stage 2B Pump Stations Pre Tender Meeting Minutes with Q&A4
Contract 100912.12 7