Daily Report Tuesday 02/06/2024 by Julio Quintero

Working hours 8:00 am to 04:07 pm. 5-minute break at 10 o'clock and 15 minutes at 1:00 pm.

SUBCONTRACTOR: Builder Choice Co.:


1 Project Manager

10 Carpenters

INSPECTIONS: inspection today about concrete quality.

ACTIVITIES: Concrete pouring in wall forms, beam forms, taking off plumbing pipes

The weather: Windy Cloudy day, and cold.

I arrived at 7:27 am

7:20 am Ten carpenters came in, ready to work.

10:39 The first concrete truck arrived. Four concrete trucks, 40 cubic yards in total.
The plumbers took out the pipes through the walls. This is a change, the pipes will be outside of the concrete
walls.

12:21 am Michael Ritvo was visiting us at the site


12:41 pm Officer Carrasco arrived to give us a ticket warming because the trucks were stopped on one of the
street lanes.
Concrete pouring test by Nutting Engineering.
Eng. Roberto arrived with some engineer friends.

Completing the rebars and wall forms.


3:57 pm The workers finished

4:02 pm Everybody left

4:07 I left the site