This document outlines standard operating procedures for steam boilers, including:
1. The objectives are to gain practical knowledge of steam boilers, identify components and explain their purpose, and learn safety guides.
2. The start-up procedure involves 15 steps like opening valves slowly to fill pipelines and allow steam flow, and monitoring turbine inlet pressure, RPM, steam and fuel flow rates, and output voltage and current.
3. The assessment section describes a self-check test by closing the steam turbine inlet valve to confirm the turbine will not operate.
This document outlines standard operating procedures for steam boilers, including:
1. The objectives are to gain practical knowledge of steam boilers, identify components and explain their purpose, and learn safety guides.
2. The start-up procedure involves 15 steps like opening valves slowly to fill pipelines and allow steam flow, and monitoring turbine inlet pressure, RPM, steam and fuel flow rates, and output voltage and current.
3. The assessment section describes a self-check test by closing the steam turbine inlet valve to confirm the turbine will not operate.
This document outlines standard operating procedures for steam boilers, including:
1. The objectives are to gain practical knowledge of steam boilers, identify components and explain their purpose, and learn safety guides.
2. The start-up procedure involves 15 steps like opening valves slowly to fill pipelines and allow steam flow, and monitoring turbine inlet pressure, RPM, steam and fuel flow rates, and output voltage and current.
3. The assessment section describes a self-check test by closing the steam turbine inlet valve to confirm the turbine will not operate.
STANDARD OPERATING PROCEDURES OBJECTIVES: 1.TO GATHER PRACTICAL KNOWLEDGE, EXPERIENCE AND UNDERSTAND THE PROS AND CONS OF STEAM BOILER
2.TO IDENTIFY THE COMPONENTS OF
BOILERS AND EXPLAIN THE PURPOSE OF EACH
3.LEARN THE SAFETY GUIDES WHEN
HANDLING WITH INDUSTRIAL AND LABORATORY STEAM BOILERS. OPERATION: TO START: START- UP PROCEDURE STEAM TURBINE, CONDENSER IN COOLING TOWER
1. FULLY “OPEN” COOLING WATER SUPPLY VALVE TO
CONDENSER 2. SWITCH “ON” COOLING WATER CIRCULATING PUMP 3. FULLY “CLOSE” THE INLET VALVE OF THE STEAM TURBINE 4. FULLY “OPEN” THE INLET VALVE OF THE STEAM TURBINE GOING TO CONDENSER 5. SLOWLY “OPEN” THE STEAM OUTLET VALVE OF THE BOILER, AND ALLOW THE STEAM FLOW UNTIL PIPELINE IS ALREADY FILLED 6. SLOWLY “OPEN” THE STEAM INLET VALVE OF THE TURBINE AND ITS DRAIN VALVE ALSO TO REMOVE THE CONDENSATE WATER ACCUMULATED DURING ITS IDLE TIME 7. FULLY “CLOSE” THE DRAIN VALVE OF THE TURBINE AS SOON AS STEAM IS ALREADY COMING OUT OF IT. 8. LET THE TURBINE OPERATES UNTIL THE REQUIRED OUTLET VOLTAGE (220VAC) IS REACHED, SEE VOLT METER 9. LET THE TURBINE OPERATES FOR SOMETIME AT NO-LOAD FOR A FEW MINUTES 10. FULLY “OPEN” DRAIN VALVE OF THE CONDENSER UNTIL CONDENSATE WATER COMING OUT IS ALREADY CLEAN, THEN CLOSE THE DRAIN VALVE 11. OPEN SET OF BOARD BULBS TO LOAD THE TURBINE 12. AFTER NOTICED THE VOLTAGE IS DROPPING AND START TO DECREASE, OPEN FURTHER THE STEAM INLET VALVE OF THE TURBINE JUST TO INCREASE ITS VOLTAGE AGAIN TO 220 VAC, SEE VOLT METER 13. OPERATE THE LOAD FOR ANY LENGTH TIME 14. FOR RECORD PURPOSES, GET THE FOLLOWING DATA:
14.1 TURBINE INLET STEAM PRESSURE, PSI
14.2 RPM OF STEAM TURBINE
14.3 STEAM FLOW RATE, KG/R
14.4 FUEL FLOW RATE , M^3/HR
14.5 TURBINE OUTPUT VOLTAGE
14.6 TURBINE OUTPUT CURRENT
15. SWITCH “ON” CONDENSATE PUMP, WHEN THERE IS ENOUGH ACCUMULATED CONDENSATE WATER IN THE CONDENSER, BY JUST LETTING THE AIRVENT VALVE OPEN UNTIL THERE IS STEADY FLOW OF STEAM OUT OF IT ASSESMENT (SELF-CHECK) BO-01-4 IN MONITORING “ MONITORING STEAM TURBINE FUNCTIONALITY FOR PARTICULAR” STUDENT SHOULD SEE TO IT THAT RELATED VALVES ARE “OPEN” TEST 1. CLOSE THE STEAM TURBINE INLET VALVE @ILLUSTRATION I-H.5 ASSESMENT (SELF-CHECK) BO-01-4 IN MONITORING “ MONITORING STEAM TURBINE FUNCTIONALITY FOR PARTICULAR” STUDENT SHOULD SEE TO IT THAT RELATED VALVES ARE “OPEN”
TEST 1. CLOSE THE STEAM TURBINE INLET VALVE @ILLUSTRATION
I-H.5 (NOTE : STEAM TURBINE WILL NOT OPERATE, THEREFORE VOLTAGE WILL NOT GENERATE )
( YOU MAY THINK OF OTHER WAYS IN ORDER TO SELF-CHECK THE