You are on page 1of 18

Approved/Proposed BOQ Rates profit

Pay Approved FWO Rates Amount Composit Amoun


Ser Description Unit Quantity Diff / Loss Remarks
item Rates incl incl Escl (Rs) (With t (Mn)
e
Bill. 1 EARTH WORKS
Jungle clearance and removing within 100 ft. (30
1 3/47 (a) SM 2,242,800.0 18.00 26.10 58.54 13.00 29.16 29.38 50%
m) (a) Light
Cutting and removing trees within a distance of
Eac
2 3/45 (a) 100 ft. (30 m) (a) upto 2½ ft. (760 2,500.00 1,491.00 2,161.95 5.40 1,890.41 4.73 0.68 13%
h
mm) girth.
Cutting and removing trees within a distance of
Eac
3 3/45 (b) 100 ft. (30 m) (b) above 2½ ft. to 6 ft. (760 to 1,600.00 5,467.00 7,927.15 12.68 3,170.86 5.07 7.61 60%
h
1800 mm) girth.
Compaction of earthwork with power road
roller, including ploughing, mixing, moistening
4 3/25 (i) earth to optimum moisture content in layers, CM 745,830.00 55.00 79.75 59.48 34.75 25.92 33.56 56%
etc. complete: 95% to 100% maximum modified
AASHO dry density.
5 NSI Natural Ground Compaction SM 1,308,000.00 41.99 54.46 71.23 21.43 28.03 43.20 61% New Item
6 NSI Granular Fill Material in Embankment CM 58,450.00 5,980.63 5,980.63 349.57 2,616.79 152.95 196.62 56% New Item
7 NSI Improved Subgrade CBR < 15% CM 599,400.00 4,850.00 4,850.00 2907.09 1,150 689.31 2217.78 76% New Item
8 NSI Subgrade Preparation in Earth Cut SM 512,300.00 168.45 186.89 95.74 126.00 64.55 31.19 33% New Item
Regular excavation dressed (Unsuitable Common
9 NSI CM 3,362,867.20 674.64 674.64 2268.72 380 1277.89 990.84 44% New Item
Material)
Dressing & Leveling of Earth work to Design
10 Ch 3/18 CM - - - - - - New Item
Section etc, Complete
11 a a. Ashes,sand,silt or soft soil CM 420,385 9.90 14.36 6.04 10.77 4.53 1.51 25% New Item
12 b b. Ordinary Soil or Hard Soil CM 252,231 19.45 28.20 7.11 21.15 5.33 1.78 25% New Item
13 c. Gravel Work or Soft Rock Not Req Blasting CM 168,154 46.60 67.57 11.36 50.68 8.52 2.84 25% New Item
14 3/6. Regular excavation dressed. CM 228,280.00 301.00 436.45 99.63 226.89 51.79 47.84 48%
Excavation in rock dressed to designed section,
grades and profiles, excavated
15 3/11 (a) material disposed off within 100 ft. (30 m) and CM 3,090.00 691.00 1,001.95 3.10 749.68 2.32 0.78 25%
lift upto 5'-0" (1.5 m).Soft rock, slate, shale,
schist laterite work, with pick and crow bar.
Excavation in hard rock requiring blasting and
disposal of excavated material (blasted material)
16 3/12 (a) upto 50 ft. (15 m) lead, (including dressing and CM 20,550.00 696.00 1,009.20 20.74 786.36 16.16 4.58 22%
leveling to
designed section,e tc. complete). i) Grade I
Supplying and filling sand under floor; or
17 7/30. CM 46,830.00 1,536.00 2,227.20 104.30 774.70 36.28 68.02 65%
plugging in wells
Transportation of earth all types when the total
3/17
18 distance, including the lead covered in the item CM 228,280.00 137.00 198.65 45.35 137.00 31.27 14.07 31%
(a,b,c)
of work,upto 1 Km lead
Transportation of earth all types when the total
3/17
19 distance, including the lead covered in the item CM 3,362,910.50 306.18 443.96 1493.00 - - 1493.00 100% New Item
(a,b,c,d)
of work upto 10 km lead.
Borrow Pit Excacvation Un dressed lead upto
20 ,3/5 100 ft. (30) CM 5,160,948.38 208.85 302.83 1562.89 - - 1562.89 100% New Item
a. Ordinary Soil
Earthowrk in ordinary soil for embankments lead
upto 100 ft. (30 m), including ploughing and
mixing with blade grade or disc harrow or other
suitable equipment, and compaction by
21 3/5 (i) CM 840,770.92 319.00 462.55 388.90 388.44 326.59 62.31 16%
mechanical means at optimum moisture content
and dressing to designed section, complete in all
respects:- 95% to 100% maximum modified
AASHO dry density.(ROADWAY EXC)
Earthowrk in ordinary soil for embankments lead
upto 100 ft. (30 m), including ploughing and
mixing with blade grade or disc harrow or other
3/5
suitable equipment, and compaction by
22 (i)+3/17 CM 5,160,948.38 475.00 688.75 3554.60 601.98 3106.79 447.82 13%
mechanical means at optimum moisture content
(a,b,c)
and dressing to designed section, complete in all
respects:- 95% to 100% maximum modified
AASHO dry density. (Including all lead & Lift)
23 - Construction of retaining Wall 20' High RM 2,000 9,443 13,692.35 27.38 79,022.00 158.04 -130.66 -477%
SUB TOTAL BILL- 13,153 6,025.23 7,127.63 54%
Bill. 2 BASE SUB BASE
Approved/Proposed BOQ Rates profit
Pay Approved FWO Rates Amount Composit Amoun
Ser Description Unit Quantity Diff / Loss Remarks
item Rates incl incl Escl (Rs) (With t (Mn)
e
Providing and laying sub-base course of stone
product of approved quality and grade, including
placing, mixing,spreading and compaction of sub-
18/3 (a-
1 base material to required depth, camber, grade CM 388,560 2,226.00 3,227.70 1254.16 4,500 1748.52 (494.36) -39%
ii) 1/1
to achieve 100% maximum modified AASHO dry
density, including carriage of all material to site
of work from taxila quarry.
18/3 (a- Re- Use of salvaged Granullar Material from
2 CM 10,833 497.00 720.65 7.81 720.65 7.81 0.00 0%
ii) existing road as subbase
Asphalt
Providing and laying plant premixed bituminous
Rarte
carpet,including compaction and finishing to
18/10 without
3 required camber, grade and density.4% Bitumen CM 178,590 21,769.00 31,565.05 5637.20 19,526.28 3487.20 2150.00 38%
(iii), 1-1 Crush &
(including Carriage of crush stone aggregate
Stone
from taxila quarry.
Dust
Providing and laying base course (WBM) of
crushed stone aggregate of approved quality and
grade, and supply and spreading of stone
18/4 (a), screening, including placing, mixing,spreading
4 CM 394,480 3,532.99 5,122.84 2020.86 6,000 2366.88 (346.02) -17%
1-1 and compaction of base course material to
required depth, camber and grade to achieve
100% maximum modified AASHO dry density,
including carriage of all materials to site of work
5 4/45. Dismantling and removing road metalling. CM 4,020 623.00 903.35 3.63 722.68 2.91 0.73 20%
Dismantling and removing road pavement, etc.,
6 4/46. including screening and stacking of byproducts CM 12,037 646.00 936.70 11.28 749.36 9.02 2.26 20%
upto one chain lead (30 metre).
Disposal of Existing Unusable Road Pavement
7 1/1. CM 5,230 94.05 136.37 0.71 109.10 0.57 0.14 20%
Structure (Lead 1KM)
SUB TOTAL BILL- 8,936 7,622.90 1,312.74 15%
Bill. 3 SURFACE COURSE & PAVEMENT
Providing and laying bituminous priming coat,
1 18/6. using 10 lbs. kerosene oil and 10 lbs. binder per SM 1,172,320 136.00 197.20 231.18 130.00 152.40 78.78 34%
100 Sft. or 0.5 Kg kerosene and 0.5 Kg binder per
Providing and laying bituminous Tack coat, using
2 18/7. 10 lbs. of bitumen per 100 Sft (0.49 Kg of SM 2,315,650 70.00 101.50 235.04 70.00 162.10 72.94 31%
bitumen per sq.m.)
Asphalt
Providing and laying plant premixed bituminous
Rarte
carpet, wearing course including compaction
18/10 without
3 and finishing to required camber, grade and CM 59,780 23,284.00 33,761.80 2018.28 22,646.28 1353.79 664.49 33%
(iv),1-1 Crush &
density.4.5% Bitumen (including Carriage of
Stone
crush stone aggregate from taxila quarry.
Dust
Providing surface treatment to roads, including
supply of bitumen and bajri/crushed stone
aggregate of approved quality, including
cleaning of road surface,heating and spraying
4 18/8 (a) bitumen, spreading bajri and rolling with road SM 305,630 680.00 986.00 301.35 1,091.00 333.44 -32.09 -11%
roller (including its operation cost, fuel and hire
charges, etc.) etc. complete including carriage of
all materials to site of work except bajjri/crushed
stone aggregate. (TST)
SUB TOTAL BILL- 2,786 2,001.73 784.12 28%
Bill. 4-1 STRUCTURE (RIGID PAVEMENT/NJB)
Providing, laying, compacting and curing pre-
mixed Cement Concrete of specified strength by
using OP Cement of specified ratio including
screening washing of aggregate ;mixing of
constituents by using batching plant, transported
by transit mixer and pouring with pumps, with
6/54 b(i) specified consistency I/c the cost of shuttering,
1 CM 16,950 14,505 21,032.03 356.49 21,709.97 367.98 -11.49 -3%
+ 1/1 compaction with Viberator but excluding, the
cost of Admixture, as approved and directed by
the Engineer Incharge. NS ( MRS Based ) ( c )
Substructure without shuttering (Foundations,
Raft, Strip and Footing Beams and other
structural members not mentioned above in 8( a
) &( b ). Ratio 1:1.5:3 Cylindrical Strength 4000
Approved/Proposed BOQ Rates profit
Pay Approved FWO Rates Amount Composit Amoun
Ser Description Unit Quantity Diff / Loss Remarks
item Rates incl incl Escl (Rs) (With t (Mn)
e
Providing and laying Kerb Block / RCC Barrier
of Concrete having compressive strength of
4000 PSI ratio (1:1.5:3) of required size, over
Lean Concrete of (1:4:8), with Slip form Paver /
6/54 b(i)
2 power kerber machine, batching plant, CM - 15,500 22,475.00 0.00 22,846.89 0.00 0.00 0%
+ 1/1
excluding the cost of additive / super
plasticizer, steel reinforcement and its labour
for bending and laying in position as specified
etc complete in all respect. b)
Providing and laying Kerb Block / RCC Barrier
of Concrete having compressive strength of
4000 PSI ratio (1:1.5:3) of required size, over
Lean Concrete of (1:4:8), with Slip form Paver /
6/54 b(ii)
3 power kerber machine, batching plant, CM 9,280 15,500 22,475.00 208.57 22,846.89 212.02 -3.45 -2%
+ 1/1
excluding the cost of additive / super
plasticizer, steel reinforcement and its labour
for bending and laying in position as specified
etc complete in all respect. b
NS (MRS
4 Admixture Ltrs 19,144 162 162.00 3.10 140.00 2.68 0.42 14% New Item
Base)
Cement concrete plain including placing,
compacting, finishing and curing complete
6/5(i) +
5 (including screening and washing of stone CM 10,400 9,135 13,245.75 137.76 13,948.80 145.07 -7.31 -5%
1/1
aggregate): (i) Ratio 1: 4: 8 Lean Conceret for
RCC Barrier & Rigid Pavement
Fabrication of mild steel reinforcement for
cement concrete, including cutting, bending,
laying in position, making joints and fastenings,
6 6/11 (c) Ton 1,320 245,518 356,001.10 469.92 300,000 396.00 73.92 16%
including cost of binding wire and labour charges
for binding of steel reinforcement (also includes
removal of
NS (MRS Single Componement polyurethane Based Joint
7 RM 80,160 1,189 1,724.05 138.20 1,515.00 121.44 16.76 12%
Base) Sealant (25mm x 25mm)
-
SUB TOTAL BILL- 1,314 1,245 69
Bill. 4-2 STRUCTURE (FLYOVER/OVERPASS)
Providing ,laying,compacting and curing pre-
mixed Cement Concrete of specified strength
by using OP Cement of specified ratio
including screening washing of aggregate ;mixing
of constituents by using batching
plant,transported by transit mixer and pouring
1 6/8 c(iv) with pumps,with specified consistency i/c the CM 169 14,015.00 20,321.75 3.43 22,846.89 3.86 -0.43 -12%
cost of shuttering, compaction with Viberator
but excluding, the cost of Admixture, as
approved and directed by the Engineer
Incharge. (c) Substructure without shuttering
(Foundations,Raft,Strip and Footing Beams and
other structural members not mentioned above
NS (MRS
2 Admixture Ltrs 19,144 162.00 162.00 3.10 140.00 2.68 0.42 14% New Item
Base)
Providing ,laying,compacting and curing pre-
mixed Cement Concrete of specified strength
by using OP Cement of specified ratio
including screening washing of aggregate ;mixing
of constituents by using batching plant,
transported by transit mixer and pouring with
pumps, with specified consistency i/c the cost
6/54 b(i) of shuttering, compaction with Viberator but
3 CM 2,734 16,357.40 23,718.23 64.85 24,021.37 65.67 -0.83 -1%
+ 1/1 excluding, the cost of Admixture, as approved
and directed by the Engineer Incharge.
(a) Superstructure (Slabs,beams,Columns,
lintels, girders and prestressed members others
cast in situ requiring formwork)
(nominal mix1:1.5:3) Cylindrical Strength 4000
PSI Transom, deck Slab, diaphragm, Wing Walls,
Curtain wall, Abutment Cap.
Approved/Proposed BOQ Rates profit
Pay Approved FWO Rates Amount Composit Amoun
Ser Description Unit Quantity Diff / Loss Remarks
item Rates incl incl Escl (Rs) (With t (Mn)
e
Providing and laying Kerb Block / RCC Barrier
of Concrete having compressive strength of
4000 PSI ratio (1:1.5:3) of required size, over
Lean Concrete of (1:4:8), with Slip form Paver /
4 6/54 b(i) power kerber machine, batching plant, CM 356 15,500.00 22,475.00 8.00 22,846.89 8.13 -0.13 -2%
excluding the cost of additive / super
plasticizer, steel reinforcement and its labour
for bending and laying in position as specified
etc complete in all respect. b)
Providing ,laying,compacting and curing pre-
mixed Cement Concrete of specified strength
by using OP Cement of specified ratio
including screening washing of aggregate ;mixing
of constituents by using batching plant,
transported by transit mixer and pouring with
pumps, with specified consistency i/c the cost
6/54 b(i)
5 of shuttering, compaction with Viberator but CM 520 16,357.40 23,718.23 12.33 24,021.37 12.49 -0.16 -1%
+ 1/1
excluding, the cost of Admixture, as approved
and directed by the Engineer Incharge.
(a) Superstructure (Slabs,beams,Columns,
lintels, girders and prestressed members others
cast in situ requiring formwork)
(nominal mix 1:1.5:3) Cylindrical Strength 4000
PSI Piers.
Providing ,laying,compacting and curing pre-
mixed Cement Concrete of specified strength
by using OP Cement of specified ratio
including screening washing of aggregate ;mixing
of constituents by using batching
plant,transported by transit mixer and pouring
6/8 a(i),1-
6 with pumps,with specified consistency i/c the CM 1,303 18,389.00 26,664.05 34.74 29,033.17 37.83 -3.09 -9%
1
cost of shuttering, compaction with Viberator
but excluding, the cost of Admixture, as
approved and directed by the Engineer
Incharge.(a) Superstructure
(Slabs,beams,Columns, lintels, girders and
prestressed members others cast in situ
Cement concrete plain including placing,
compacting, finishing and curing complete
7 6/5 (i) CM 60 9,135.00 13,245.75 0.79 13,948.80 0.84 -0.04 -5%
(including screening and washing of stone
aggregate): (i) Ratio 1: 4: 8 (Lean Concrete)
Fabrication of mild steel reinforcement for
cement concrete, including cutting, bending,
laying in position, making joints and fastenings,
8 6/11 (c) Ton 1,014 245,518.00 356,001.10 360.99 300,000.00 304.20 56.79 16%
including cost of binding wire and labour charges
for binding of steel reinforcement (also includes
removal of rust from bars):- ('c) Deformed bars
Fabrication of mild steel reinforcement
deformed bar cage of specified yield strength
for R.C.C bored piles including cutting bending,
lowering of cage with crane in position, welding
9 6/10 (ii) Ton 511 245,518.00 356,001.10 181.92 300,000.00 153.30 28.62 16%
and fastening, including the cost of binding wire,
Crane machine (also includes removal of rust
from the bars) as approved and directed by the
Engineer Incharge. (ii) Deformed Bars Grade-60
10 6/22. Fabrication of high tensile steel prestressing Ton 65 509,857.00 739,292.65 48.05 735,000.00 47.78 0.28 1%
11 6/24 (iii) cables for prestressed (post tensioned) concrete, CM 1,303 3,340.00 4,843.00 6.31 4,358.70 5.68 0.63 10%
Providing and laying Elastomeric Neoprene
Bearing Pads of specified grade,Specific gravity,
hardness, elongation, min tensile strength of
18/22 II 2250 psi, and compressive strength of 2000 psi cu.c
12 1,195,425 3.81 5.52 6.60 4.00 4.78 1.82 28%
b(i) conforming to ASTM D2240 standard test m
method for rubber as approved and directed by
the Engineer
Incharge. (II) Grade 60 (b) Laminated (i) Without
NS (MRS Confirmatory Boring in Rock Strata (nx size)
13 LM 350.00 17,769.39 17,769.39 6.22 10,500.00 3.68 2.54 41% New Item
Base) including Testing and reporting
Approved/Proposed BOQ Rates profit
Pay Approved FWO Rates Amount Composit Amoun
Ser Description Unit Quantity Diff / Loss Remarks
item Rates incl incl Escl (Rs) (With t (Mn)
e
Providing and casting in situ bored premixed
reinforced concrete pile with specified type of
premixed conctete using core sand including all
labor and materials boring rig maching crane
excavator welding plant batching plant transit
NS (MRS mixture land etc (Except the cost of steel
14 LM 2,150 31,782.00 46,083.90 99.08 41,500.00 89.23 9.86 10%
Base) reinforcement its labor for bending and laying in
position in boat plate form etc) which will be
paid separately including screeing and washing
of shengal and curin as approved by engineer
incharge:- in ordinary soil dia 48" Pile (4000Psi
cylleder strength
Extra for Kentledge and loading arangements
for test pile to ensure structural and
Geotechnical soundness of pile upto a
maximum test load applying in stages i/c the
hiring of machinary required for complete job M.T
15 6/49. 6,000 491.00 711.95 4.27 529.70 3.18 1.09 26%
and furnishing a report in this regard by a on
qualified/authorized Geo Technical Engineer by
studying the data of at least seven days as
approved and directed by the Engineer Incharge.
Proof load test (Upto 3.0 times design load)
Extra for Kentledge and loading arangements
for test pile to ensure structural and
Geotechnical soundness of pile upto a
maximum test load applying in stages i/c the
hiring of machinary required for complete job M.T
16 6/49. 5,000 491.00 711.95 3.56 529.70 2.65 0.91 26%
and furnishing a report in this regard by a on
qualified/authorized Geo Technical Engineer by
studying the data of at least seven days as
approved and directed by the Engineer Incharge.
Proof load test (Upto 1.5 times design load)
Providing and fixing metalic expansion Joints of
3/4" thick Aluminium Alloy strip of specified
width duly bolted with check nuts @ 9" c/c with
18/21 (B) the MS lugs for specified movements as
17 LM 258 114,310.00 165,749.50 42.76 110,000.00 28.38 14.38 34%
iii mentioned by the designer i/c the cost of
polystrene joint fill but excluding the cost of Lugs
complete in all respect as approved and directed
by the Engineer Incharge. (B) Saw-tooth Type
Providing and laying stone pitching, hand
packed, with surface levelled off to the correct
18 16/31 (i) section and voids filled in 1:8 cement, sand CM 859 3,450.00 5,002.50 4.30 6,389.00 5.49 -1.19 -28%
mortar, in floors of bridges along banks and in
appons etc. (i) top layer on slope
Cast iron rain water downpipe fixed in position,
excluding heads and shoes, but including
19 9/21 (a) LM 264 936.00 1,357.20 0.36 1,240.00 0.33 0.03 9%
painting and clamps, etc:- (a) 4" dia (100 mm)
cast iron down pipe.
Providing and laying stone pitching, hand
packed, with surface levelled off to the correct
NS (MRS Eac
20 section and voids filled in 1:8 cement, sand 80 10,934.00 15,854.30 1.27 6,149.00 0.49 0.78 61%
Base) h
mortar, in floors of bridges along banks and in
appons etc.
-
SUB TOTAL BILL- 893 781 112
Bill. 4-3 STRUCTURE (RIVER/CANAL/RAILWAY BRIDGE)
Excavation in foundation of building, bridges and
other structures, including dagbelling, dressing,
refilling around structure with excavated earth,
1 3/21 b(ii) CM 11,124 313 453.85 5.05 320.00 3.56 1.49 29%
watering and ramming lead upto one chain (30
m) and lift upto 5 ft. (1.5 m) (b) By Excavator (ii)
Ordinary soil
Approved/Proposed BOQ Rates profit
Pay Approved FWO Rates Amount Composit Amoun
Ser Description Unit Quantity Diff / Loss Remarks
item Rates incl incl Escl (Rs) (With t (Mn)
e
Providing ,laying,compacting and curing pre-
mixed Cement Concrete of specified strength
by using OP Cement of specified ratio
including screening washing of aggregate ;mixing
of constituents by using batching
plant,transported by transit mixer and pouring
2 6/8 c(iv) with pumps,with specified consistency i/c the CM 1,020 14,015 20,321.75 20.73 22,846.89 23.30 -2.58 -12%
cost of shuttering, compaction with Viberator
but excluding, the cost of Admixture, as
approved and directed by the Engineer
Incharge. (c) Substructure without shuttering
(Foundations,Raft,Strip and Footing Beams and
other structural members not mentioned above
NS (MRS
3 Admixture Ltrs 150,692 162.00 162.00 24.41 140.00 21.10 3.32 14% New Item
Base)
Confrimatory Boring in Rock Strata (nx
4 LM 540 17,769.39 17,769.39 9.60 10,500.00 5.67 3.93 41% New Item
size) including Testing and reporting
NS (MRS
5 Permanent Pile casing (Steel Linear) Ton 260 446,246.70 446,246.70 116.02 338,655.00 88.05 27.97 24% New Item
Base)
Providing, laying ,compacting and curing pre-
mixed Cement Concrete of specified strength
by using OP Cement of specified ratio
including screening washing of aggregate ;mixing
of constituents by using batching
plant,transported by transit mixer and pouring
with pumps,with specified consistency i/c the
6/54 b(i) cost of shuttering, compaction with Viberator
6 CM 17,413 16,357 23,718.23 413.01 24,021.37 418.28 -5.28 -1%
+ 1/1 but excluding, the cost of Admixture, as
approved and directed by the Engineer
Incharge.
(a) Superstructure (Slabs, beams, Columns,
lintels, girders and prestressed members others
cast in situ requiring formwork)
(nominal mix (1:1.5:3) Cylindrical Strength 4000
PSI Transom, Deck Slab, Diaphragm, Wing
Providing and laying Kerb Block / RCC Barrier
of Concrete having compressive strength of
4000 PSI ratio (1:1.25:2.25) of required size, over
Lean Concrete of (1:4:8), with Slip form Paver /
7 6/54 b(i) power kerber machine, batching plant, CM 1,259 15,500 22,475.00 28.30 22,846.89 28.76 -0.47 -2%
excluding the cost of additive / super
plasticizer, steel reinforcement and its labour
for bending and laying in position as specified
etc complete in all respect. b RCC Barrier (i)
Providing, laying, compacting and curing pre-
mixed Cement Concrete of specified strength
by using OP Cement of specified ratio
including screening washing of aggregate ;mixing
of constituents by using batching
plant,transported by transit mixer and pouring
with pumps,with specified consistency i/c the
6/54 b(i)
8 cost of shuttering, compaction with Viberator CM 3,798 16,357 23,718.23 90.08 24,021.37 91.23 -1.15 -1%
+ 1/1
but excluding, the cost of Admixture, as
approved and directed by the Engineer
Incharge.
(a) Superstructure (Slabs, beams, Columns,
lintels, girders and prestressed members others
cast in situ requiring formwork)
(nominal mix 1:1.5:3) Cylindrical Strength 4000
Approved/Proposed BOQ Rates profit
Pay Approved FWO Rates Amount Composit Amoun
Ser Description Unit Quantity Diff / Loss Remarks
item Rates incl incl Escl (Rs) (With t (Mn)
e
Providing, laying, compacting and curing pre-
mixed Cement Concrete of specified strength
by using OP Cement of specified ratio
including screening washing of aggregate ;mixing
of constituents by using batching
plant,transported by transit mixer and pouring
with pumps,with specified consistency i/c the
6/54 b(i)
9 cost of shuttering, compaction with Viberator CM 8,470 16,357 23,718.23 200.89 24,021.37 203.46 -2.57 -1%
+ 1/1
but excluding, the cost of Admixture, as
approved and directed by the Engineer
Incharge.
(a) Substructure without shuttering
(Foundations, raft, Strip and Footing Beams and
other structural members not mentioned above
in 8(a) & (b). (nominal mix (1:1.5:3) Cylindrical
Providing ,laying,compacting and curing pre-
mixed Cement Concrete of specified strength
by using OP Cement of specified ratio
including screening washing of aggregate ;mixing
of constituents by using batching
plant,transported by transit mixer and pouring
6/8 a(i),1-
10 with pumps,with specified consistency i/c the CM 6,155 18,389 26,664.05 164.12 30,044.00 184.92 -20.80 -13%
1
cost of shuttering, compaction with Viberator
but excluding, the cost of Admixture, as
approved and directed by the Engineer
Incharge.(a) Superstructure
(Slabs,beams,Columns, lintels, girders and
prestressed members others cast in situ
Cement concrete plain including placing,
compacting, finishing and curing complete
11 6/5 (i) CM 817 9,135 13,245.75 10.82 13,948.80 11.40 -0.57 -5%
(including screening and washing of stone
aggregate): (i) Ratio 1: 4: 8 (Lean Concerte)
Fabrication of mild steel reinforcement for
cement concrete, including cutting, bending,
laying in position, making joints and fastenings,
12 6/11 (c) Ton 7,822 245,518 356,001.10 2784.64 300,000.00 2346.60 438.04 16%
including cost of binding wire and labour charges
for binding of steel reinforcement (also includes
removal of rust from bars):- ('c) Deformed bars
Fabrication of mild steel reinforcement
deformed bar cage of specified yield strength
for R.C.C bored piles including cutting bending,
lowering of cage with crane in position, welding
13 6/10 (ii) Ton 4,687 245,518 356,001.10 1668.58 300,000.00 1406.10 262.48 16%
and fastening, including the cost of binding wire,
Crane machine (also includes removal of rust
from the bars) as approved and directed by the
Engineer Incharge. (ii) Deformed Bars Grade-60
Fabrication of high tensile steel prestressing
cables for prestressed (post tensioned) concrete,
including assembling by drawing the H.T. wire
through metal spacer plate, inserting in helix
core and taping or tying, sheathing in
longitudinally welded metal corrugated sheath,
positioning , anchorage with male and female
14 6/22. set of anchorage cone, forming ducts for Ton 296 509,857 739,292.65 218.83 735,000.00 217.56 1.27 1%
transverse cable,stressing cables with jack at
both ends as per stressing schedule, maintaining
stressing record and supply the same in the
approved proforma to the Engineer-in-charge,
making loop at blind end, including all materials
required for it, grouting the cable ducts with
cement, cutting projected ends and making
Approved/Proposed BOQ Rates profit
Pay Approved FWO Rates Amount Composit Amoun
Ser Description Unit Quantity Diff / Loss Remarks
item Rates incl incl Escl (Rs) (With t (Mn)
e
Add
@20%
Lifting, transporting and placing precast extra in
prestressed concrete B eam, Girder and other Sublet
members (excluding battens) etc. in Position on Rates for
15 6/24 (iii) CM 6,155 3,340 4,843.00 29.81 4,358.70 26.83 2.98 10%
the bridge to correct alignment and level, Soan /
etc.complete Beam above 75ft. (22.5m) upto Silt River
100ft. (30m) length (I & Box Girder Both due to
high flow
of water
Providing and laying Elastomeric Neoprene
Bearing Pads of specified grade,Specific gravity,
hardness, elongation, min tensile strength of
18/22 II 2250 psi, and compressive strength of 2000 psi Cu.c
16 5,630,475 3.81 5.52 31.08 4.00 22.52 8.56 28%
b(i) conforming to ASTM D2240 standard test m
method for rubber as approved and directed by
the Engineer Incharge. (II) Grade 60
(b) Laminated (i) Without Anchrage
Providing and casting of situ bored premixed
reinforced concrete piles with specified type of
premixed concrete using course sand including
all labour and materials, boring, rig machine,
crane, excavator, welding plant, baching plant
NS (MRS transit mixer, I- Land etc (except the cost of steel @10%
17 LM 6,900 31,782 46,083.90 317.98 41,500.00 286.35 31.63 10%
Base) reinforcement, its labor for bending and laying in For River
position and boat plateform etc) which will be
paid separately, including, screening & washing
of shingle and cruing as approved by Engineer
incharge:- In Ordinary Soil Dia 48" pile. (4000
psi Cylinder Strength)
Providing and casting of situ bored premixed
reinforced concrete piles with specified type of
premixed concrete using course sand including
all labour and materials, boring, rig machine,
crane, excavator, welding plant, baching plant
NS (MRS transit mixer, I- Land etc (except the cost of steel @10%
18 LM 18,480 24,137 34,998.65 646.78 39,500.00 729.96 -83.18 -13%
Base) reinforcement, its labor for bending and laying in For River
position and boat plateform etc) which will be
paid separately, including, screening & washing
of shingle and cruing as approved by Engineer
incharge:- In Ordinary Soil Dia 42" pile. (4000
psi Cylinder Strength)
Extra for Kentledge and loading arangements
for test pile to ensure structural and
Geotechnical soundness of pile upto a
maximum test load applying in stages i/c the
hiring of machinary required for complete job M.T
19 6/49. 16,800 491 711.95 11.96 1,059.00 17.79 -5.83 -49%
and furnishing a report in this regard by a on
qualified/authorized Geo Technical Engineer by
studying the data of at least seven days as
approved and directed by the Engineer Incharge.
Proof load test (Upto 3.0 times design load)
Extra for Kentledge and loading arangements
for test pile to ensure structural and
Geotechnical soundness of pile upto a
maximum test load applying in stages i/c the
hiring of machinary required for complete job M.T
20 6/49. 14,000 491 711.95 9.97 523.00 7.32 2.65 27%
and furnishing a report in this regard by a on
qualified/authorized Geo Technical Engineer by
studying the data of at least seven days as
approved and directed by the Engineer Incharge.
Proof load test (Upto 1.5 times design load)
Providing and fixing metalic expansion Joints of
3/4" thick Aluminium Alloy strip of specified
width duly bolted with check nuts @ 9" c/c with
18/21 (B) the MS lugs for specified movements as
21 LM 2,063 114,310 165,749.50 341.94 110,000.00 226.93 115.01 34%
iii mentioned by the designer i/c the cost of
polystrene joint fill but excluding the cost of Lugs
complete in all respect as approved and directed
by the Engineer Incharge. (B) Saw-tooth Type
Approved/Proposed BOQ Rates profit
Pay Approved FWO Rates Amount Composit Amoun
Ser Description Unit Quantity Diff / Loss Remarks
item Rates incl incl Escl (Rs) (With t (Mn)
e
Providing and laying stone pitching, hand
packed, with surface levelled off to the correct
22 16/31 (i) section and voids filled in 1:8 cement, sand CM 5,039 3,450 5,002.50 25.21 6,389.00 32.19 -6.99 -28%
mortar, in floors of bridges along banks and in
appons etc. (i) top layer on slope
Cast iron rain water downpipe fixed in position,
excluding heads and shoes, but including
23 9/21 (a) LM 952 936 1,357.20 1.29 1,240.00 1.18 0.11 9%
painting and clamps, etc:- (a) 4" dia (100 mm)
cast iron down pipe.
NS (MRS Eac
24 Sonic Integrity Tests (SIT) on all piles 892 10,934 15,854.30 14.14 8,500.00 7.58 6.56 46%
Base) h
-
SUB TOTAL BILL- 7,185 6,409 777
Bill. 4-4 STRUCTURE (SUBWAY)
Excavation in foundation of building, bridges and
other structures, including dagbelling, dressing,
refilling around structure with excavated earth,
1 3/21 b(ii) CM 21,382 313 453.85 9.70 320.00 6.84 2.86 29%
watering and ramming lead upto one chain (30
m) and lift upto 5 ft. (1.5 m) (b) By Excavator (ii)
Ordinary soil
2 Admixture 113,736 162 162.00 18.43 140.00 15.92 2.50 14% New Item
Providing, laying, compacting and curing pre-
mixed Cement Concrete of specified strength
by using OP Cement of specified ratio
including screening washing of aggregate ;mixing
of constituents by using batching
plant,transported by transit mixer and pouring
with pumps,with specified consistency i/c the
6/54 b(i) cost of shuttering, compaction with Viberator
3 CM 9,661 16,357 23,718.23 229.14 24,021.37 232.07 -2.93 -1%
+ 1/1 but excluding, the cost of Admixture, as
approved and directed by the Engineer
Incharge.
(a) Substructure without shuttering
(Foundations, raft, Strip and Footing Beams and
other structural members not mentioned above
in 8(a) & (b). (nominal mix (1:1.5:3) Cylindrical
Strength 4000 PSI Base Slab, Toe Wall, drain
Providing ,laying,compacting and curing pre-
mixed Cement Concrete of specified strength
by using OP Cement of specified ratio
including screening washing of aggregate ;mixing
of constituents by using batching
plant,transported by transit mixer and pouring
4 6/8 c(iv) with pumps,with specified consistency i/c the CM 1,367 14,015 20,321.75 27.78 22,846.89 31.23 -3.45 -12%
cost of shuttering, compaction with Viberator
but excluding, the cost of Admixture, as
approved and directed by the Engineer
Incharge. (c) Substructure without shuttering
(Foundations,Raft,Strip and Footing Beams and
other structural members not mentioned above
Providing, laying, compacting and curing pre-
mixed Cement Concrete of specified strength
by using OP Cement of specified ratio
including screening washing of aggregate ;mixing
of constituents by using batching
plant,transported by transit mixer and pouring
with pumps,with specified consistency i/c the
6/54 b(i)
5 cost of shuttering, compaction with Viberator CM 17,406 16,357 23,718.23 412.84 24,021.37 418.12 -5.28 -1%
+ 1/1
but excluding, the cost of Admixture, as
approved and directed by the Engineer
Incharge.
(a) Superstructure (Slabs, beams, Columns,
lintels, girders and prestressed members others
cast in situ requiring formwork)
(nominal mix (1:1.5:3) Cylindrical Strength 4000
Cement concrete plain including placing,
compacting, finishing and curing complete
6 6/5 (i) CM 1,383 9,135 13,245.75 18.32 13,948.80 19.29 -0.97 -5%
(including screening and washing of stone
aggregate): (i) Ratio 1: 4: 8 (Lean Concerte)
Approved/Proposed BOQ Rates profit
Pay Approved FWO Rates Amount Composit Amoun
Ser Description Unit Quantity Diff / Loss Remarks
item Rates incl incl Escl (Rs) (With t (Mn)
e
Fabrication of mild steel reinforcement for
cement concrete, including cutting, bending,
laying in position, making joints and fastenings,
7 6/11 (c) Ton 4,265 245,518 356,001.10 1518.34 300,000.00 1279.50 238.84 16%
including cost of binding wire and labour charges
for binding of steel reinforcement (also includes
removal of
Providing embeding 10" (250 mm) wide ¼" (6
mm) thick rubber water stopper in
8 6/30. LM 3,957 1,229 1,782.05 7.05 1,225.00 4.85 2.20 31%
expansion joints of R.C.C. roof slab complete in
all respects.
Bitumen coating to plastered or cement
9 13/9 (i) concrete surface:- (i) 20 lbs. per 100 Sft. SM 34,742 149 216.05 7.51 200.00 6.95 0.56 7%
(9.07 Kg per Sq.m)
-
SUB TOTAL BILL- 2,249 2,015 234
Bill. 4-5 STRUCTURE (BOX CULVERT)
Excavation in foundation of building, bridges and
other structures, including dagbelling, dressing,
refilling around structure with excavated earth,
1 3/21 b(ii) CM 6,870 313 453.85 3.12 320.00 2.20 0.92 29%
watering and ramming lead upto one chain (30
m) and lift upto 5 ft. (1.5 m) (b) By Excavator (ii)
Ordinary soil
Providing ,laying,compacting and curing pre-
mixed Cement Concrete of specified strength
by using OP Cement of specified ratio
including screening washing of aggregate ;mixing
of constituents by using batching
plant,transported by transit mixer and pouring
2 6/8 c(iv) with pumps,with specified consistency i/c the CM 1,845 14,015 20,321.75 37.49 22,846.89 42.15 -4.66 -12%
cost of shuttering, compaction with Viberator
but excluding, the cost of Admixture, as
approved and directed by the Engineer
Incharge. (c) Substructure without shuttering
(Foundations,Raft,Strip and Footing Beams and
other structural members not mentioned above
3 Admixture Lits 59,424 162 162.00 9.63 140.00 8.32 1.31 14% New Item
Providing, laying, compacting and curing pre-
mixed Cement Concrete of specified strength
by using OP Cement of specified ratio
including screening washing of aggregate ;mixing
of constituents by using batching
plant,transported by transit mixer and pouring
with pumps,with specified consistency i/c the
6/54 b(i)
4 cost of shuttering, compaction with Viberator CM 3,112 16,357 23,718.23 73.81 24,021.37 74.75 -0.94 -1%
+ 1/1
but excluding, the cost of Admixture, as
approved and directed by the Engineer
Incharge.
(a) Superstructure (Slabs, beams, Columns,
lintels, girders and prestressed members others
cast in situ requiring formwork)
(nominal mix (1:1.5:3) Cylindrical Strength 4000
Providing, laying, compacting and curing pre-
mixed Cement Concrete of specified strength
by using OP Cement of specified ratio
including screening washing of aggregate ;mixing
of constituents by using batching
plant,transported by transit mixer and pouring
with pumps,with specified consistency i/c the
6/54 b(i)
5 cost of shuttering, compaction with Viberator CM 6,139 16,357 23,718.23 145.61 24,021.37 147.47 -1.86 -1%
+ 1/1
but excluding, the cost of Admixture, as
approved and directed by the Engineer
Incharge.
(a) Superstructure (Slabs, beams, Columns,
lintels, girders and prestressed members others
cast in situ requiring formwork)
(nominal mix (1:1.5:3) Cylindrical Strength 4000
Approved/Proposed BOQ Rates profit
Pay Approved FWO Rates Amount Composit Amoun
Ser Description Unit Quantity Diff / Loss Remarks
item Rates incl incl Escl (Rs) (With t (Mn)
e
Providing, laying, compacting and curing pre-
mixed Cement Concrete of specified strength
by using OP Cement of specified ratio
including screening washing of aggregate ;mixing
of constituents by using batching
plant,transported by transit mixer and pouring
with pumps,with specified consistency i/c the
6/54 b(i)
6 cost of shuttering, compaction with Viberator CM 3,760 16,481 23,897.45 89.85 24,021.37 90.32 -0.47 -1%
+ 1/1
but excluding, the cost of Admixture, as
approved and directed by the Engineer
Incharge.
(a) Superstructure (Slabs, beams, Columns,
lintels, girders and prestressed members others
cast in situ requiring formwork)
(nominal mix (1:1.5:3) Cylindrical Strength 4000
Cement concrete plain including placing,
compacting, finishing and curing complete
7 6/5 (i) CM 1,427 9,135 13,245.75 18.90 13,948.80 19.90 -1.00 -5%
(including screening and washing of stone
aggregate): (i) Ratio 1: 4: 8 (Lean Concerte)
Fabrication of mild steel reinforcement for
cement concrete, including cutting, bending,
laying in position, making joints and fastenings,
8 6/11 (c) Ton 2,228 245,518 356,001.10 793.17 300,000.00 668.40 124.77 16%
including cost of binding wire and labour charges
for binding of steel reinforcement (also includes
removal of
Providing embeding 10" (250 mm) wide ¼" (6
9 6/30. mm) thick rubber water stopper in expansion LM 7,037 1,229 1,782.05 12.54 1,225.00 8.62 3.92 31%
joints of R.C.C. roof slab complete in all respects.
Providing and laying stone pitching, hand
packed, with surface levelled off to the correct
10 16/31 (i) section and voids filled in 1:8 cement, sand CM 480 3,450 5,002.50 2.40 6,389.00 3.07 -0.67 -28%
mortar, in floors of bridges along
banks and in appons etc. (i) top layer on slope
Bitumen coating to plastered or cement
11 13/9 (i) concrete surface:- (i) 20 lbs. per 100 Sft. SM 23,934 149 216.05 5.17 200.00 4.79 0.38 7%
(9.07 Kg per Sq.m)
-
SUB TOTAL BILL- 1,192 1,070 122
Bill. 5 DRAINAGE & EROSION WORKS
Excavation in foundation of building, bridges and
other structures, including dagbelling, dressing,
refilling around structure with excavated earth,
1 3/21 b(ii) CM 23,900 313 453.85 10.85 320.00 7.65 3.20 29%
watering and ramming lead upto one chain (30
m) and lift upto 5 ft. (1.5 m) (b) By Excavator (ii)
Ordinary soil
2 ,4/13 Dismantling Brick Work in Lime or cement Conc CM 8,900 1,268 1,838.82 16.37 1,497.75 13.33 3.04 19% New Item
Earthwork excavation in irrigation channels,
drains, etc. to designed section, grades and
3 3/10 (iv) profiles, excavated materiadisposed off and CM 63,750 601 870.73 55.51 415.00 26.46 29.05 52% New Item
dressed within 50 ft. (15 m) lead:-
(iv) gravel & shingle
4 NSI Admixture Ltrs 45,400 162 162.00 7.35 140.00 6.36 1.00 14% New Item
Providing ,laying,compacting and curing pre-
mixed Cement Concrete of specified strength
by using OP Cement of specified ratio
including screening washing of aggregate ;mixing
of constituents by using batching
6/8 plant,transported by transit mixer and pouring
5 c(iv)+Ch. with pumps,with specified consistency i/c the CM 1,860 14,015 20,321.75 37.80 22,846.89 42.50 -4.70 -12%
1.1 cost of shuttering, compaction with Viberator
but excluding, the cost of Admixture, as
approved and directed by the Engineer
Incharge. (c) Substructure without shuttering
(Foundations,Raft,Strip and Footing Beams and
other structural members not mentioned above
Cement concrete plain including placing,
6/5 (c),1- compacting, finishing and curing complete
6 CM 5,980 13,419 19,457.55 116.36 22,846.89 136.62 -20.27 -17%
1 (including screening and washing of stone
aggregate): (c) Ratio 1: 1½: 3 (PCC)
Approved/Proposed BOQ Rates profit
Pay Approved FWO Rates Amount Composit Amoun
Ser Description Unit Quantity Diff / Loss Remarks
item Rates incl incl Escl (Rs) (With t (Mn)
e
Cement concrete plain including placing,
6/5(i) + compacting, finishing and curing complete
7 CM 2,990 9,135 13,245.75 39.60 13,948.80 41.71 -2.10 -5%
1/1 (including screening and washing of stone
aggregate): (i) Ratio 1: 4: 8 Lean Conceret
Fabrication of mild steel reinforcement for
cement concrete, including cutting, bending,
laying in position, making joints and fastenings,
8 6/11 (c) Ton 100 245,518 356,001.10 35.60 300,000.00 30.00 5.60 16%
including cost of binding wire and labour charges
for binding of steel reinforcement (also includes
removal of
Providing and laying stone pitching, hand
packed, with surface levelled off to the correct
9 16/31 (i) section and voids filled in 1:8 cement, sand CM 69,630 3,450 5,002.50 348.32 6,389.00 444.87 -96.54 -28%
mortar, in floors of bridges along
banks and in appons etc. (i) top layer on slope
Providing and laying R.C.C. pipe sewers,
moulded with cement concrete 1:1½:3
conforming to ASTM Specification C-76-79, Class
II. Wall B, including carriage of pipe from factory
10 21/3 (iii) M 200 3,429 4,972.05 0.99 4,390.00 0.88 0.12 12%
to site of work, lowering in trenches to correct
alignment and grade, jointing with rubber
ring,cutting pipes where necessary, testing, etc.,
complete. (iii) 460 mm (18") i/d
Providing and laying R.C.C. pipe sewers,
moulded with cement concrete 1:1½:3
conforming to ASTM Specification C-76-79, Class
II. Wall B, including carriage of pipe from factory
11 21/3 (v) M 1,000 4,771 6,917.95 6.92 6,340.00 6.34 0.58 8%
to site of work, lowering in trenches to correct
alignment and grade, jointing with rubber
ring,cutting pipes where necessary, testing, etc.,
complete. (v) 610 mm (24") i/d
12 21/3 (xi) Providing and laying R.C.C. pipe sewers, M 488 16,755 24,295.33 11.86 23,500.00 11.47 0.39 3% New Item
6/5 (f) + moulded with cement concrete 1:1½:3
13 CM 520 12,167 17,642.15 9.17 17,642.15 9.17 0.00 0%
1-1 conforming to ASTM Specification C-76-20, Class

-
SUB TOTAL BILL- 697 777 -81
Bill. 6 ANCILLARY WORKS
Cement concrete plain including placing,
compacting, finishing and curing complete
6/5 (c),1-
1 (including screening and washing of stone CM 1,790 13,419.00 19,457.55 34.83 19,000.00 34.01 0.82 2%
1
aggregate): (c) Ratio 1: 1½: 3 (for Utility
Ducts)
Providing and fixing precast Edge Kerb Stone
(4"to 6" thick), of 3500 PSI Compressive
2 6/51 b(i) Strength, embeded in PCC 1:2:4 over lean M 18,370 1,193.00 1,729.85 31.78 1,650.00 30.31 1.47 5%
concrete 1:4:8 etc
complete in all respect. (b) With Painting (i) (i)
Providing and fixing W-Beam Guard Rail made of
1/8" thick galvanized sheet,fixed on vertical
posts of galvinized channel of (13.40 kg/Mtr @
18/34 6.25 ft c/c duly embeded in P.C.C (1:2:4) of M 37,400 12,384.35 17,957.31 671.60 13,000.00 486.20 185.40 28% New Item
specified depth i/c the cost of hardware,
Reflectors,Boxing glove end,Fish tail end and
double face reflectors etc, complete in all
3 Admixture 7,160 162.00 162.00 1.16 140.00 1.00 0.16 14% New Item
Providing, fabrication and fixing pole mounted
Direction Board / road delineator of any shape
and size, with specified Sheet and thickness,
4 18/24 (a) supported with G.I Channel, (excluding the SM 110 8,946.00 12,971.70 1.43 10,995.00 1.21 0.22 15%
cost of vertical post and painting) etc
complete in all respect. (a) G.I Sheet 14 SWG CI
RCULAR/TRI ANGULAR 3 ft size
Providing, fabrication and fixing pole mounted
Direction Board / road delineator of any shape
and size, with specified Sheet and thickness,
18/24 (a)
5 supported with G.I Channel, (excluding the SM 230 11,829.00 17,152.05 3.94 10,628.00 2.44 1.50 38%
I
cost of vertical post and painting) etc
complete in all respect. (a) G.I Sheet 14 SWG CI
RCULAR/TRI ANGULAR (I) 12 -48 sft
Approved/Proposed BOQ Rates profit
Pay Approved FWO Rates Amount Composit Amoun
Ser Description Unit Quantity Diff / Loss Remarks
item Rates incl incl Escl (Rs) (With t (Mn)
e
Providing, fabrication and fixing pole mounted
Direction Board / road delineator of any shape
and size, with specified Sheet and thickness,
18/24 (a)
6 supported with G.I Channel, (excluding the SM 280 11,829.00 17,152.05 4.80 9,624.00 2.69 2.11 44%
II
cost of vertical post and painting) etc
complete in all respect. (a) G.I Sheet 14 SWG CI
RCULAR/TRI ANGULAR (II) 54 -120 sft
Lettering and printing of signage / direction
boards / road delineators of any colour by
7 13/41 (a) machine i/c cost of Digital Lettering, Lamination SM 1,240 11,444.00 16,593.80 20.58 15,525.00 19.25 1.33 6%
& pasting etc complete in all
respect. (a) High Intensity Prismatic (HIP) Tape
Providing, fabrication and fixing Vertical Post
comprising of medium quality G.I Pipe of
specified diameter, including the cost of
8 18/26 (b) M 600 4,523.00 6,558.35 3.94 6,287.00 3.77 0.16 4%
clamping arrangements, top cover, hold fasts
embeded in PCC 1:2:4 etc complete in all
respect. (b) 3 inch
Providing, fabrication and fixing Vertical Post
comprising of medium quality G.I Pipe of
specified diameter, including the cost of
9 18/26 (c) M 300 6,252.00 9,065.40 2.72 8,300.00 2.49 0.23 8%
clamping arrangements, top cover, hold fasts
embeded in PCC 1:2:4 etc complete in all
respect. (c) 4 inch
Providing, fabrication and fixing Vertical Post
comprising of medium quality G.I Pipe of
specified diameter, including the cost of
10 18/26 (e) M 150 13,419.00 19,457.55 2.92 13,200.00 1.98 0.94 32%
clamping arrangements, top cover, hold fasts
embeded in PCC 1:2:4 etc complete in all respect
(e) 6 inch
Providing & fixing Cat Eyes of size 4" x 4" x
3/4" duly casted with specified material having
plastic strip containing mini retro-reflective
glass beads of color white/red/yellow having
18/27a specifid reflections , quality & shape i/c the cost Eac
11 38,140 348.00 504.60 19.25 355.00 13.54 5.71 30%
(B)(i) of self built in 12 mm diax120 mm long steel zinc h
plated nail,fixing to road with epoxy/
hammering with separate nail complete (a)
Acrylic material (B) Uni-Directional
(i) 31 Glass beads a side
Providing and fixing Full width Gantry
comprising of 3 mm thick GI sheet (Z-275) fixed
over double front and back truss made with Top
& bottom chords of MS angle iron L-100x100x10
mm, webs and struts of L 65x65x8 mm welded
with top and bottom truss of webs and struts of
65x65x8 mm duly supported on specified
vertical posts of double columns of MS pipe
18/38a
12 of size 7500x219x8 mm thick duly welded with SM 230 124,250.00 180,162.50 41.44 120,000.00 27.60 13.84 33%
(I)
Base plate of 600x400x50 mm with MS stiffners
of 350x150x15 mm thick MS sheet for each
column fixed in prelaid RCC footing i/c the cost
of polyurethene Paint to MS skeleton but
excluding the cost of lettering/printing as
approved and directed by the Engineer Incharge.
(a) Two Supported (I) Two
Lanes
Approved/Proposed BOQ Rates profit
Pay Approved FWO Rates Amount Composit Amoun
Ser Description Unit Quantity Diff / Loss Remarks
item Rates incl incl Escl (Rs) (With t (Mn)
e
Providing and fixing Full width Gantry
comprising of 3 mm thick GI sheet (Z-275) fixed
over double front and back truss made with Top
& bottom chords of MS angle iron L-100x100x10
mm, webs and struts of L 65x65x8 mm welded
with top and bottom truss of webs and struts of
65x65x8 mm duly supported on specified
18/38a vertical posts of double columns of MS pipe
13 SM 300 109,340.00 158,543.00 47.56 100,000.00 30.00 17.56 37%
(ii) of size 7500x219x8 mm thick duly welded with
Base plate of 600x400x50 mm with MS stiffners
of 350x150x15 mm thick MS sheet for each
column fixed in prelaid RCC footing i/c the cost
of polyurethene Paint to MS skeleton but
excluding the cost of lettering/printing as
approved and directed by the Engineer Incharge.
(a) Two Supported (II) Three Lanes
Providing and fixing Cantilever Gantry of
specified portal made of 3 mm thick GI sheet (Z-
275) of size 4000x2400x3mm supported with a
frame of MS angle iron frame of size
40x40x5mm all around the sheet with 3 no
vertical and one no horizontal braces of MS
tees of size 40x40x5 mm duly supported on a
truss of 2 no chords of MS pipes 273x7
14 18/37 (i) SM 120 124,250.00 180,162.50 21.62 135,000.00 16.20 5.42 25%
mmx9.27 mtr and 3 no struts of MS pipe of
size 143x4.5mmx3.098 mtr duly bolted with a
post of MS pipe of size 7500x457.5x 12.7 mm
thick duly welded with Base plate of 850x850x36
mm with MS stiffners of 18 mm thick MS sheet
and fixed with anchor bolts in prelaid RCC
footing i/c the cost of polyurethene Paint to
MS skeleton but excluding the cost of
Painting Traffic Lane Marking of specified width
(1.5mm thick), with
15 13/35 (ii) Thermoplastic (TP) Paint including Glass Beads, M 261,540 157.00 227.65 59.54 170.00 44.46 15.08 25%
complete in all respect, as approved and
directed by Engineer incharge.(ii) 6" wide
Painting Traffic Lane Marking of specified width
(1.5mm thick), with Thermoplastic (TP) Paint
16 13/35 (II) including Glass Beads, complete in all respect, as SM 5,000 1,044.00 1,513.80 7.57 1,135.00 5.68 1.89 25%
approved and directed
by Engineer incharge.Zibra crossing,stop lines
Providing and laying Tuff pavers, having 7000
PSI, crushing strength of approved
17 10/41 b manufacturer, over 2" to 3" sand cushion i/c SM 1,000 1,272.00 1,844.40 1.84 1,695.79 1.70 0.15 8%
grouting with sand in joints i/c finishing to
require slope . complete in all respect.(50% Grey
Providing and fixing barbed wire fencing, with 4
horizontal and two cross wires, with
R.C.C. 1:2:4 posts, 5.5'x6"x9"
(1.68mx150mmx225 mm) at 8 ft. (2.45 m) centre
18 26/42 (II) M 76,600 2,485.00 3,603.25 276.01 2,845.00 217.93 58.08 21%
to centre, reinforced with 4 No. 3/8" (10 mm)
dia vertical bars and 1/8" (3 mm) dia stirrups 12"
(300 mm) centre to centre, complete in all
respects in cement concrete 1:4:8 base of size
Providing and Fixing L-type Barrier delineator of
specified material of Size 150 x 100mm i/c the Eac
19 18/29 b 18,490 646.00 936.70 17.32 775.00 14.33 2.99 17%
cost of hardware, reflective tape etc complete in h
all respect.(b) Alluminium (3mm thick)
Providing and fixing of PVC/uPVC pipe dia
20 - M 54,110 1,268.00 1,838.60 99.49 1,600.00 86.58 12.91 13%
100mm (NJ barrer)
21 - Providing and fixing of PVC/uPVC pipe dia M 12,000 2,446.00 3,546.70 42.56 3,150.00 37.80 4.76 11%
-
SUB TOTAL BILL- 1,414 1,081 333
Bill. 7 MISCOLLANEOUS
1 - Provide Survey Instruments PS 1 2,000,000 2,000,000.00 2.00
Operational Cost of Consultant & Client's Offices Mo
2 - 24 250,000 250,000.00 6.00
(Rental Basis) nth
3 - Provide Material Testing Laboratory PS 1 5,000,000 5,000,000.00 5.00
Approved/Proposed BOQ Rates profit
Pay Approved FWO Rates Amount Composit Amoun
Ser Description Unit Quantity Diff / Loss Remarks
item Rates incl incl Escl (Rs) (With t (Mn)
e
Operational Cost of Project Laboratory (including Mo
4 - 24 250,000 250,000.00 6.00
Helpers) nth
Provide, Running and all Maintenance of
Mo
5 - Vehicles (Rental Basis) 3Nos. Toyota Hilux Vigo 72 245,000 245,000.00 17.64
nth
(For PD, Chief Engineer, Consultant)
Provide, Running and all Maintenance of
Mo
6 - Vehicles (Rental Basis) 3Nos. Toyota GLI (For 72 225,000 225,000.00 16.20
nth
PMU & Consultant)
Provide, Running and all Maintenance of
Mo
7 - Vehicles (Rental Basis) 2Nos. Suzuki 48 200,000 200,000.00 9.60
nth
Cultus (For Consultant)
Provide, Running and all Maintenance of
Mo
8 - Vehicles (Rental Basis) 2Nos. Suzuki Bolan (For 48 190,000 190,000.00 9.12
nth
PMU & Consultant)

SUB TOTAL BILL- 72 -


Bill. 8a ELECTRIC WORKS
Design, Supply, transportation, storage,
installation, testing and commissing of the
following item of work, including all material.
-
Labour, tools and accessories etc. required for
proper completion of each item as per
specification, drawings and/or as directed by the
10m high single arm octagonal shape electric
street light pole, made of hot dipped
4.5 mm thick (7 SWG) galvanized steel tappered
from 225 mm at bottom to 100 mm at top with
1500mm x 60mm dia, arm for luminaire
68 (a-
installation, duly Gl welded with 470x470x20
i)/24 Eac
1 mm base plate with the help of 4 no trianguler 25 105,050 152,322.50 3.81 143,500.00 3.59 0.22 6%
86 (a- h
stiffeners 100x350x20 mm of GI sheet, with built
i)/24
in junction box with shutter & one (01) no. 2A SP
MCB 10KA breaker, pole numbering, i/c the cost
of nuts & J-rag bolts duly fixed in prelaid
concrete foundation, foundation will be paid
additionally as approved and directed by the
10m high Double arm octagonal shape electric
street light pole, made of hot dipped
4.5 mm thick (7 SWG) galvanized steel tappered
from 225 mm at bottom to 100 mm at top with
1500mm x 60mm dia, arm for luminaire
68 (b-
installation, duly Gl welded with 470x470x20
i)/24 Eac
2 mm base plate with the help of 4 no trianguler 25 107,250 155,512.50 3.89 154,500.00 3.86 0.03 1%
86 (a- h
stiffeners 100x350x20 mm of GI sheet, with built
i)/24
in junction box with shutter & two (02) no. 2A SP
MCB 10KA breaker, pole numbering, i/c the cost
of nuts & J-rag bolts duly fixed in prelaid
concrete foundation, foundation will be paid
additionally as approved and directed by the
12m high Single arm octagonal shape electric
street light pole, made of hot dipped
4.5 mm thick (7 SWG) galvanized steel tappered
from 225 mm at bottom to 100 mm at top with
1500mm x 60mm dia, arm for luminaire
68 (b-
installation, duly Gl welded with 470x470x20
ii)/24 Eac
3 mm base plate with the help of 4 no trianguler 485 114,975 166,713.75 80.86 154,500.00 74.93 5.92 7%
86 (a- h
stiffeners 100x350x20 mm of GI sheet, with built
I)/24
in junction box with shutter & one (01) no. 2A SP
MCB 10KA breaker, pole numbering, i/c the cost
of nuts & J-rag bolts duly fixed in prelaid
concrete foundation, foundation will be paid
additionally as approved and directed by the
Approved/Proposed BOQ Rates profit
Pay Approved FWO Rates Amount Composit Amoun
Ser Description Unit Quantity Diff / Loss Remarks
item Rates incl incl Escl (Rs) (With t (Mn)
e
12m high Double arm octagonal shape electric
street light pole, made of hot dipped
4.5 mm thick (7 SWG) galvanized steel tappered
from 225 mm at bottom to 100 mm at top with
1500mm x 60mm dia, arm for luminaire
68 (b-
installation, duly Gl welded with 470x470x20
ii)/24 Eac
4 mm base plate with the help of 4 no trianguler 411 117,075 169,758.75 69.77 166,500.00 68.43 1.34 2%
86 (a- h
stiffeners 100x350x20 mm of GI sheet, with built
i)/24
in junction box with shutter & two (02) no. 2A SP
MCB 10KA breaker, pole numbering, i/c the cost
of nuts & J-rag bolts duly fixed in prelaid
concrete foundation, foundation will be paid
additionally as approved and directed by the
11(c) /6,
8(ii)/6, Eac
5 Road Lighting Pole foundation. 946 40,000 58,000.00 54.87 55,000.00 52.03 2.84 5%
12/9, h
30/7
Road Light & Accessories for flood light
- 0.00
Installation
Road Lighting LED Cobra-head Luminaries of
90W and 120 im/W conforming to IP
65. Philips/Osram/Thron with corrosion resistant
die casted aluminum housing, silicon gas kit,
thermally hardened giass complete with LED
69(c-
6 drivers, surge protection i/c the cost of all No 25 46,970 68,106.50 1.70 83,500.00 2.09 -0.38 -23%
v)/24
accessories/components required for proper
operation, fully flexible for future upgradation
and easy replacements for maintenance
purposes, bucket elevator charges as approved
and directed by the Engineer Incharge.
Road Lighting LED Cobra-head Luminaries of
120W and 120 im/W conforming to IP
65. Philips/Osram/Thron with corrosion resistant
die casted aluminum housing, silicon gas kit,
thermally hardened giass complete with LED
69(c-
7 drivers, surge protection i/c the cost of all No 510 48,290 70,020.50 35.71 89,500.00 45.65 -9.93 -28%
vi)/24
accessories/components required for proper
operation, fully flexible for future upgradation
and easy replacements for maintenance
purposes, bucket elevator charges as approved
and directed by the Engineer Incharge.
Road Lighting LED Cobra-head Luminaries of
150W and 120 im/W conforming to IP
65. Philips/Osram/Thron with corrosion resistant
die casted aluminum housing, silicon gas kit,
thermally hardened giass complete with LED
69(c-
8 drivers, surge protection i/c the cost of all No 822 52,646 76,336.70 62.75 89,500.00 73.57 -10.82 -17%
viii)/24
accessories/components required for proper
operation, fully flexible for future upgradation
and easy replacements for maintenance
purposes, bucket elevator charges as approved
and directed by the Engineer Incharge.
Road Lighting LED Cobra-head Luminaries of
180W and 120 im/W conforming to IP
65. Philips/Osram/Thron with corrosion resistant
die casted aluminum housing, silicon gas kit,
thermally hardened giass complete with LED
69(c-
9 drivers, surge protection i/c the cost of all No 25 56,507 81,935.15 2.05 89,500.00 2.24 -0.19 -9%
ix)/24
accessories/components required for proper
operation, fully flexible for future upgradation
and easy replacements for maintenance
purposes, bucket elevator charges as approved
and directed by the Engineer Incharge.
Approved/Proposed BOQ Rates profit
Pay Approved FWO Rates Amount Composit Amoun
Ser Description Unit Quantity Diff / Loss Remarks
item Rates incl incl Escl (Rs) (With t (Mn)
e
Flod lighting LED Luminaries of 120W make
Philips, GE or equivalentsuitable for M- 2 & M-3
roads of wattage suitable for the project
requirements, fully IP 66 with corrosion resistant
die caste aluminum housing, silicon gas kit,
NS (MRS thermally hardened giass complete with LED
10 No 24 58,850 85,332.50 2.05 79,500.00 1.91 0.14 7%
Base) drivers, surge protection i/c the cost of all
accessories/components required for proper
operation of the system. The luminaries shall be
fully flexible for future upgradation and easy
replacements for maintenance purposes.
Contractor to submit lighting design calculation
NS (MRS Hot Dipped galvanized bracket for mounting of Eac
11 24 3,500 5,075.00 0.12 5,700.00 0.14 -0.02 -12%
Base) flood lights alongwith all accessories. h
Junction box size 12"x08"x06" (for Flood Light
connection) with angle iron frame claded 16
SWG, sheet steel enclosure having high quaility
NS (MRS
12 powder coated paint, color RAL 7032. Suitable 9,144.14 0.22 0.21 0.01 6%
Base)
for connections with IP 54 protection cl;ass,
door, locking arrangement etc and all other
No 24 6,306 8,640.00
accessories as required for quality work.
Junction box size 12"x08"x06" (for Flood Light
- 0.00 0.00
connection)
01 No. 2 Amp SP MCB, 10 KA - 0.00 0.00
04 NO. Terminal block - 0.00 0.00
GI flexible pipe 1" dia - 0.00 0.00
Conduites/Pipe - 0.00 0.00
PVC pipe/conduit class-D 50 mm dia with
13 12 (c)/23 accessories suitable for laying multi-core Rm 750 670 971.12 0.73 1,265.00 0.95 -0.22 -30%
cables on road crossings.
PVC pipe/conduit class-D 100 mm dia with
14 12 (e)/23 accessories suitable for laying multi-core cables Rm 2,600 2,476 3,590.19 9.33 3,830.00 9.96 -0.62 -7%
on road crossings.
PVC pipe/conduit class-B 100 mm dia with
15 11 (b)/23 accessories suitable for laying multi-core cables Rm 33,500 739 1,071.55 35.90 1,306.00 43.75 -7.85 -22%
from pole to pole and in walls/structure.
Low Voltage Power Cables - 0.00 0.00
4 Core 25 mm2 Cu. PVC 600/1000 Voltage grade
Unarmored cable (Tranformer to
13(c-
16 LCP) (Verrified docomentry evidence for source Rm 2,050 3,061 4,437.99 9.10 4,390.00 9.00 0.10 1%
viii)/24
of Aluminium & PVC shall be furnished prior to
manufacturing)
1 Core 25 mm2 Cu. PVC 450/750 Voltage grade
NS (MRS
17 earth cable including all fixing accessries as Rm 320 924 1,339.80 0.43 1,540.00 0.49 -0.06 -15%
Base)
requried for earthing of lighting control panels.
4 Core 16 mm2 Cu. PVC 600/1000 Voltage grade
13(c- Unarmored cable (Tranformer to LCP) (Verrified
18 Rm 38,700 1,986 2,880.25 111.47 3,830.00 148.22 -36.76 -33%
vii)/24 docomentry evidence for source of Aluminium &
PVC shall be furnished prior to manufacturing)
1 Core 16 mm2 Cu. PVC 450/750 Voltage grade
10(c-
19 earth cable including all fixing accessries as Rm 40,750 538 780.69 31.81 1,005.00 40.95 -9.14 -29%
vii)/24
requried for earthing of lighting control panels.
3 Nos. 1 Core 16 mm2 Cu. PVC 450/750 Voltage
10(c-
grade earth cable including all fixing accessries Rm - 0.00 0.00
iii)/24
as requried for earthing of lighting control
20 i For 10m No 75 6,199 8,988.55 0.67 11,700.00 0.88 -0.20 -30%
21 ii For 12m No 1,307 7,232 10,486.40 13.71 9,800.00 12.81 0.90 7%
22 iii For Flood light to be istalled in underpass No 24 517 749.65 0.02 925.00 0.02 0.00 -23%
Approved/Proposed BOQ Rates profit
Pay Approved FWO Rates Amount Composit Amoun
Ser Description Unit Quantity Diff / Loss Remarks
item Rates incl incl Escl (Rs) (With t (Mn)
e
Road lighting control panel with angle iron
framecladded 14 SWG sheet steel enclose having
high quailty powder coated paint, color Ral 7032.
The LCP shall be complete with incoming and
outgoing MCCBs. Cu bus bars, magnetic
contactores, photo protection class, door,
locking arrangement etc. and all other
accessories as required for quality work.
Materil
88(a- 1 No. Incoming 63 Amp. (adj.) TP MCCB, 25 KA 4
i)/24,94(x No. outgoing 25 Amp. (adj.) TP MCCBs, 25 KA
v- 2 No. outgoing 25 Amp. (adj.) TP MCCB, 25 KA
b)/24,94( (Spare) 4 No. 32 Amp magnetic contactor
i)/24,94 2 No. 32 Amp magnetic contactor (Spare)
23 Job 16 440,096 638,139.20 10.21 720,000.00 11.52 -1.31 -13%
(iv)/24,9 3 No. photo-electric switch's with indication
4(iii)/24, lights.
94(x)/24, a) 1 No. ammeters0-100 Amp, with selector
94(vi)/2 switch (04 position) and CT of 100/5 Amp
4 b) 3 No Indication lights
c) 1 No. Voltmeter with fuse and 7 position
selector switch.
d) 3 Ph. N &Earth copper bus bars internal wiring
& line-up leminals etc. Brass cable
glands/accessories
e) 06 Nos. Auto-MAnual-OFF (3 position switches
for operation in auto (with photocell) and
normal (manual mode-photocell override)
f) 06 Nos. on & 06 Nos. OFF push button switch's
Earth point comprising of 10 ft. 5/8" dia. Copper
coated M.S rods driven in grpound near each
NS (MRS Eac
24 lighiting control panel. The earthing road shall be 32 30,000 43,500.00 1.39 37,750.00 1.21 0.18 13%
Base) h
computered with fixing
clamps etc.
Oil Cooied type, step down power Transformer
of 25 KVA rating, 110/0.415 KV, i/c the cost of
liting hooks, thermoneters, LT & HT bushing5-
steps, tap changer, imported double float
bucholz relay, 2 earthing terminals, roller
105 wheels, connecting terminals for cables M.S box
(iii)/24,7 on transformer in order to cover complete LT
25 Job 16 454,250 658,662.63 10.54 820,500.00 13.13 -2.59 -25%
7(b- side. all necessary materials required for
ii)/24 connections on H.T & LT side, rated voltage
11000/415/240 V impedance 6.25% or as
specified by WAPDA/IEC system earth Delta /
Star, Nutral solidily earthed. i/c wapda testing
charges complete in all respects made of PEL,
Siements, as approved and directed by the
SUB TOTAL BILL-8a 553 622 -68
GRAND TOTAL (Mn) 40,443 29,649 10,722
Material of Asphalt (i,e Crush & Khaka) Rs in Mn 1,710.00
Total after Material Amount of Asphlat Work Rs in Mn 31,359 9,012 22%

You might also like