Professional Documents
Culture Documents
Risk Assessment
Risk Assessment
Team members
Risk Assessment for Lagoon water treatment by Nano Cons. Manager
bubble Oxygenation technology Site Engineer,
COSHH coordinator,
Work parties
HSE department,
Activities water treatment equipment Installation Legend:
Plant department
Site Supervisor
Persons at Risk All the entrants (Site team, Visitors) L = Likelihood, S = Severity, RF = Risk Factor
Logistic
Document No: Revision: 00 Date: 01/11/2023 Procurement
S. Risk Residual Risk
No Activity Hazard Hazard Effect Control Measure Responsible party
L S RF L S RF
.
Page 4 of 26
Page 5 of 26
Team members
Risk Assessment for Lagoon water treatment by Nano Cons. Manager
bubble Oxygenation technology Site Engineer,
COSHH coordinator,
Work parties
HSE department,
Activities water treatment equipment Installation Legend: Plant department
Site Supervisor
Persons at Risk All the entrants (Site team, Visitors) L = Likelihood, S = Severity, RF = Risk Factor
Logistic
Document No: Revision: 00 Date: 01/11/2023 Procurement
S. Risk Residual Risk
No Activity Hazard Hazard Effect Control Measure Responsible party
L S RF L S RF
.
Improper Operation Slide the forks carefully and slowly under the
and Use pallet.
Floor Conditions Inspect whether the materials are secure and in
Blind Spots place before moving.
When pallet jack is raised, keep feet and other
body parts away from underneath the MHE.
Make sure the load does not exceed the pallet
truck’s capacity.
Place the load evenly over the width and length
of the pallet truck.
Remove from service any forklift found to
be in unsafe operating condition.
Keep forklifts in clean condition; free of
excess oil and grease.
Repair and maintain according to the
manufacturer’s recommendations.
Only trained and certified workers may
operate a forklift.
Ensure operators are trained on types of
trucks in use.
Always wear a seatbelt when the forklift
has one.
Never exceed the rated load and ensure it is
stable and balanced.
Do not raise or lower the load while
traveling.
Page 6 of 26
Page 7 of 26
Risk Assessment for Lagoon water treatment by Nano Team members
Cons. Manager
bubble Oxygenation technology Site Engineer,
COSHH coordinator,
Work parties
HSE department,
Activities water treatment equipment Installation Legend: Plant department
Site Supervisor
Persons at Risk All the entrants (Site team, Visitors) L = Likelihood, S = Severity, RF = Risk Factor
Logistic
Document No: Revision: 00 Date: 01/11/2023 Procurement
S. Risk Residual Risk
No Activity Hazard Hazard Effect Control Measure Responsible party
L S RF L S RF
.
Page 7 of 26
Page 8 of 26
Risk Assessment for Lagoon water treatment by Nano Team members
Cons. Manager
bubble Oxygenation technology Site Engineer,
COSHH coordinator,
Work parties
HSE department,
Activities water treatment equipment Installation Legend: Plant department
Site Supervisor
Persons at Risk All the entrants (Site team, Visitors) L = Likelihood, S = Severity, RF = Risk Factor
Logistic
Document No: Revision: 00 Date: 01/11/2023 Procurement
S. Risk Residual Risk
No Activity Hazard Hazard Effect Control Measure Responsible party
L S RF L S RF
.
Page 10 of 26
Page 11 of 26
Team members
Risk Assessment for Lagoon water treatment by Nano Cons. Manager
bubble Oxygenation technology Site Engineer,
COSHH coordinator,
Work parties
HSE department,
Activities water treatment equipment Installation Legend: Plant department
Site Supervisor
Persons at Risk All the entrants (Site team, Visitors) L = Likelihood, S = Severity, RF = Risk Factor
Logistic
Document No: Revision: 00 Date: 01/11/2023 Procurement
S. Risk Residual Risk
No Activity Hazard Hazard Effect Control Measure Responsible party
L S RF L S RF
.
Page 11 of 26
Page 12 of 26
Team members
Risk Assessment for Lagoon water treatment by Nano Cons. Manager
bubble Oxygenation technology Site Engineer,
COSHH coordinator,
Work parties
HSE department,
Activities water treatment equipment Installation Legend: Plant department
Site Supervisor
Persons at Risk All the entrants (Site team, Visitors) L = Likelihood, S = Severity, RF = Risk Factor
Logistic
Document No: Revision: 00 Date: 01/11/2023 Procurement
S. Risk Residual Risk
No Activity Hazard Hazard Effect Control Measure Responsible party
L S RF L S RF
.
Sharp edge of of fatal Ensure Full body harness and 100% tie off
existing Tray injuries. Ensure the scaffold platform is properly erected
Physical injury with "Safe to use" tag.
Damage to Ensure castor wheels are locked and out rigger
property in place.
Major injury Hand tools must be secured/tethered
Hot work permit to be obtained and ensure that
there is no combustible materials near cutting
work.
Ensure Fire extinguisher in place with fire
blanket to protect the Fire flux
Ensure cutting wheel must be from standard
company and inspect before use.
Angle grinder must inspected by competent
electrician and maintain record.
Ensure operatives must alert while using cutting
tools for their clothing to avoid entanglement
with moving parts.
Angle grinder must have safety guard and
operatives must use face shield.
Dust mask and noise protection must use.
Safety data sheet and COSHH assessment must
briefed to the operatives before using any
chemicals and solvent.
Maintain good housekeeping.
PPE must be in use for every task.
21 While cable pulling activity need close
supervision and with good communication
Page 12 of 26
Page 13 of 26
Team members
Risk Assessment for Lagoon water treatment by Nano Cons. Manager
bubble Oxygenation technology Site Engineer,
COSHH coordinator,
Work parties
HSE department,
Activities water treatment equipment Installation Legend: Plant department
Site Supervisor
Persons at Risk All the entrants (Site team, Visitors) L = Likelihood, S = Severity, RF = Risk Factor
Logistic
Document No: Revision: 00 Date: 01/11/2023 Procurement
S. Risk Residual Risk
No Activity Hazard Hazard Effect Control Measure Responsible party
L S RF L S RF
.
Page 13 of 26
Page 14 of 26
Team members
Risk Assessment for Lagoon water treatment by Nano Cons. Manager
bubble Oxygenation technology Site Engineer,
COSHH coordinator,
Work parties
HSE department,
Activities water treatment equipment Installation Legend: Plant department
Site Supervisor
Persons at Risk All the entrants (Site team, Visitors) L = Likelihood, S = Severity, RF = Risk Factor
Logistic
Document No: Revision: 00 Date: 01/11/2023 Procurement
S. Risk Residual Risk
No Activity Hazard Hazard Effect Control Measure Responsible party
L S RF L S RF
.
Page 14 of 26
Page 15 of 26
Team members
Risk Assessment for Lagoon water treatment by Nano Cons. Manager
bubble Oxygenation technology Site Engineer,
COSHH coordinator,
Work parties
HSE department,
Activities water treatment equipment Installation Legend: Plant department
Site Supervisor
Persons at Risk All the entrants (Site team, Visitors) L = Likelihood, S = Severity, RF = Risk Factor
Logistic
Document No: Revision: 00 Date: 01/11/2023 Procurement
S. Risk Residual Risk
No Activity Hazard Hazard Effect Control Measure Responsible party
L S RF L S RF
.
Page 15 of 26
Page 16 of 26
Team members
Risk Assessment for Lagoon water treatment by Nano Cons. Manager
bubble Oxygenation technology Site Engineer,
COSHH coordinator,
Work parties
HSE department,
Activities water treatment equipment Installation Legend: Plant department
Site Supervisor
Persons at Risk All the entrants (Site team, Visitors) L = Likelihood, S = Severity, RF = Risk Factor
Logistic
Document No: Revision: 00 Date: 01/11/2023 Procurement
S. Risk Residual Risk
No Activity Hazard Hazard Effect Control Measure Responsible party
L S RF L S RF
.
Page 16 of 26
Page 17 of 26
Team members
Risk Assessment for Lagoon water treatment by Nano Cons. Manager
bubble Oxygenation technology Site Engineer,
COSHH coordinator,
Work parties
HSE department,
Activities water treatment equipment Installation Legend: Plant department
Site Supervisor
Persons at Risk All the entrants (Site team, Visitors) L = Likelihood, S = Severity, RF = Risk Factor
Logistic
Document No: Revision: 00 Date: 01/11/2023 Procurement
S. Risk Residual Risk
No Activity Hazard Hazard Effect Control Measure Responsible party
L S RF L S RF
.
Page 17 of 26
Page 18 of 26
Risk Assessment for Lagoon water treatment by Nano Team members
Cons. Manager
bubble Oxygenation technology Site Engineer,
COSHH coordinator,
Work parties
HSE department,
Activities water treatment equipment Installation Legend: Plant department
Site Supervisor
Persons at Risk All the entrants (Site team, Visitors) L = Likelihood, S = Severity, RF = Risk Factor
Logistic
Document No: Revision: 00 Date: 01/11/2023 Procurement
S. Risk Residual Risk
No Activity Hazard Hazard Effect Control Measure Responsible party
L S RF L S RF
.
Page 18 of 26
Page 19 of 26
Team members
Risk Assessment for Lagoon water treatment by Nano Cons. Manager
bubble Oxygenation technology Site Engineer,
COSHH coordinator,
Work parties
HSE department,
Activities water treatment equipment Installation Legend: Plant department
Site Supervisor
Persons at Risk All the entrants (Site team, Visitors) L = Likelihood, S = Severity, RF = Risk Factor
Logistic
Document No: Revision: 00 Date: 01/11/2023 Procurement
S. Risk Residual Risk
No Activity Hazard Hazard Effect Control Measure Responsible party
L S RF L S RF
.
Page 20 of 26
Page 21 of 26
Team members
Risk Assessment for Lagoon water treatment by Nano Cons. Manager
bubble Oxygenation technology Site Engineer,
COSHH coordinator,
Work parties
HSE department,
Activities water treatment equipment Installation Legend: Plant department
Site Supervisor
Persons at Risk All the entrants (Site team, Visitors) L = Likelihood, S = Severity, RF = Risk Factor
Logistic
Document No: Revision: 00 Date: 01/11/2023 Procurement
S. Risk Residual Risk
No Activity Hazard Hazard Effect Control Measure Responsible party
L S RF L S RF
.
Page 21 of 26
Page 22 of 26
Team members
Risk Assessment for Lagoon water treatment by Nano Cons. Manager
bubble Oxygenation technology Site Engineer,
COSHH coordinator,
Work parties
HSE department,
Activities water treatment equipment Installation Legend: Plant department
Site Supervisor
Persons at Risk All the entrants (Site team, Visitors) L = Likelihood, S = Severity, RF = Risk Factor
Logistic
Document No: Revision: 00 Date: 01/11/2023 Procurement
S. Risk Residual Risk
No Activity Hazard Hazard Effect Control Measure Responsible party
L S RF L S RF
.
may result in
operator
pushed by
passers
Health
problems , Proper PPE according NEOM standards to be
respiratory followed Site Foreman
Dust 3 3 9 1 3 3
problems Nosh approved respirator shall be worn at all Workers
caused by silica times during the activity
dust
Ensure proper preventive maintenance of all
power tools on regular basis.
Try to control the noise at the source.
Ear muff/ plugs shall be worn by persons, if the
Hearing loss,
noise is more than 85 dB (A).
Annoyance Site Foreman
Noise 3 3 9 Decibel meter will be available with calibration 1 3 3
(noise Workers
certificate on site, checklist will be maintained
irritation)
and registered.
Where necessary, double ear protection to be
used (Earplugs and ear muffs).
Decibel meter will be on site for noise monitor.
Page 22 of 26
Page 23 of 26
Team members
Risk Assessment for Lagoon water treatment by Nano Cons. Manager
bubble Oxygenation technology Site Engineer,
COSHH coordinator,
Work parties
HSE department,
Activities water treatment equipment Installation Legend: Plant department
Site Supervisor
Persons at Risk All the entrants (Site team, Visitors) L = Likelihood, S = Severity, RF = Risk Factor
Logistic
Document No: Revision: 00 Date: 25/06/2023 Procurement
S. Risk Residual Risk
No Activity Hazard Hazard Effect Control Measure Responsible party
L S RF L S RF
.
Page 23 of 26
Page 24 of 26
Team members
Risk Assessment for Lagoon water treatment by Nano Cons. Manager
bubble Oxygenation technology Site Engineer,
COSHH coordinator,
Work parties
HSE department,
Activities water treatment equipment Installation Legend: Plant department
Site Supervisor
Persons at Risk All the entrants (Site team, Visitors) L = Likelihood, S = Severity, RF = Risk Factor
Logistic
Document No: Revision: 00 Date: 01/11/2023 Procurement
S. Risk Residual Risk
No Activity Hazard Hazard Effect Control Measure Responsible party
L S RF L S RF
.
Page 24 of 26
Page 25 of 26
Team members
Risk Assessment for Lagoon water treatment by Nano Cons. Manager
bubble Oxygenation technology Site Engineer,
COSHH coordinator,
Work parties
HSE department,
Activities water treatment equipment Installation Legend: Plant department
Site Supervisor
Persons at Risk All the entrants (Site team, Visitors) L = Likelihood, S = Severity, RF = Risk Factor
Logistic
Document No: Revision: 00 Date: 01/11/2023 Procurement
S. Risk Residual Risk
No Activity Hazard Hazard Effect Control Measure Responsible party
L S RF L S RF
.
Page 25 of 26
Page 26 of 26
Team members
Risk Assessment for Lagoon water treatment by Nano Cons. Manager
bubble Oxygenation technology Site Engineer,
COSHH coordinator,
Work parties
HSE department,
Activities water treatment equipment Installation Legend: Plant department
Site Supervisor
Persons at Risk All the entrants (Site team, Visitors) L = Likelihood, S = Severity, RF = Risk Factor
Logistic
Document No: Revision: 00 Date: 01/11/2023 Procurement
S. Risk Residual Risk
No Activity Hazard Hazard Effect Control Measure Responsible party
L S RF L S RF
.
Name T Name
Sign Sign
Page 26 of 26