The document outlines the schedule of activities for the Olive Garden Verve project located in Taguig from July 3 to September 2. Key activities included construction of seating areas, installation of ceilings, floors, tiles, plumbing and electrical works. Specific tasks varied each week but generally included painting, wood staining, flooring, lighting, kitchen equipment installation and punch listing. The schedule provides details on the planned progression of construction and interior finish works over the 7 week period.
The document outlines the schedule of activities for the Olive Garden Verve project located in Taguig from July 3 to September 2. Key activities included construction of seating areas, installation of ceilings, floors, tiles, plumbing and electrical works. Specific tasks varied each week but generally included painting, wood staining, flooring, lighting, kitchen equipment installation and punch listing. The schedule provides details on the planned progression of construction and interior finish works over the 7 week period.
The document outlines the schedule of activities for the Olive Garden Verve project located in Taguig from July 3 to September 2. Key activities included construction of seating areas, installation of ceilings, floors, tiles, plumbing and electrical works. Specific tasks varied each week but generally included painting, wood staining, flooring, lighting, kitchen equipment installation and punch listing. The schedule provides details on the planned progression of construction and interior finish works over the 7 week period.
1.0 Construction of Alcove/Booth Seating 2.0 Topping Works at Waterproofed Flooring of Kitchen, GRI and Prep Areas. 3.0 Installation of framings of Arch Ceiling 4.0 Installation of plumbing pipes at Kitchen, Prep, Bar and Toilet Areas. 5.0 Installation of Weathered Fire Bricks at Column Claddings 13 3-Jul 9-Jul 6.0 Construction of Drywall column cladding at POS Area. 7.0 Dismantling of beam and counter at expo bar 8.0 Wall preparation at Beverage Area prior to installation of PVC corrugated p 9.0 Installation of electrical pipes and wirings 10.0 Mechanical Works 11.0 Installation of Firepro pipes.
1.0 Construction of Alcove/Booth Seating
2.0 Installation of framings of Arch Ceiling 3.0 Installation of Weathered Fire Bricks at Column Claddings 4.0 Installation of ceiling framings at POS Area. 5.0 Installation of wall tiles at toilet 14 10-Jul 16-Jul 6.0 Reconstruction of beam and counter at Expo Bar 7.0 Construction of Raised floor at Kitchen, GRI and Prep Area 8.0 Installation of electrical pipes and wirings 9.0 Mechanical Works 10.0 Plumbing pipes and waterlines installation
1.0 Construction of Alcove/Booth Seating
2.0 Installation of boards of Arch Ceiling 3.0 Installation of Floor tiles at Dining area 4.0 Construction of Raised floor at Kitchen, GRI and Prep Area 5.0 Wood Doors and PVC door installation 6.0 Installation of window and glass door frames 7.0 Painting works 15 17-Jul 23-Jul 8.0 Wood stain application 9.0 Installation of Floor tiles at Toilet Area 10.0 Installation of Chestnut PVC corrugated panel 11.0 Installation of toilet lavatory granite 12.0 Installation of Toilet wood wall accents 13.0 Mechanical Works 14.0 Installation of electrical pipes, wirings and devices 15.0 Fabrication of Expo Bar Railings 1.0 Installation of window and glass door frames 2.0 Painting works 3.0 Wood stain application 4.0 Installation of Floor tiles at Dining area 5.0 Fabrication of Expo Bar Railings 6.0 CCTV Works 16 24-Jul 30-Jul 7.0 Installation of electrical pipes, wirings and devices 8.0 Installation of wood accents and finishes 9.0 Installation of Bar counter granite 10.0 Installation of toilet lavatory granite 11.0 Smoke detecting system installation 12.0 Installation of Toilet wood wall accents
1.0 Painting works
2.0 Wood stain application 3.0 Installation of Floor tiles at Dining area 4.0 Installation of Expo Bar railings 5.0 CCTV Works 6.0 Smoke detecting system installation 17 31-Jul 6-Aug 7.0 Ceiling frames installation at Kitchen and Preparation Areas 8.0 Board installation at POS Area ceiling 9.0 Installation of window and glass door frames 10.0 Installation of wood accents and finishes 11.0 Installation of Bar counter granite 12.0 Installation of Stone tiles at Toilet walls 13.0 Installation of Floor and wall tiles
1.0 Painting works
2.0 Wood stain application 3.0 Installation of Floor tiles at Dining Area, GRI, Hallway, Kitchen And Preparati 4.0 Installation of wall tiles at Kitchen And Preparation Areas 5.0 Installation of Expo Bar railings 6.0 CCTV Works 18 7-Aug 13-Aug 7.0 Smoke detecting system installation 8.0 Plumbing fixtures installation 9.0 Installation of window and glass door framing and glass 10.0 Installation of wood accents and finishes 11.0 Installation of Office Cabinet 12.0 Ceiling board installation at Arch ceiling and POS Area
1.0 Painting works
2.0 Wood stain application 3.0 Installation of Floor tiles at Dining area 4.0 Installation of Expo Bar railings 5.0 CCTV Works 19 14-Aug 20-Aug 19 14-Aug 20-Aug 6.0 Fire supression system installation 7.0 Installation of additional electrical outlets at Al Fresco 8.0 Plumbing fixtures installation 9.0 Lighting fixtures installation 10.0 Installation of window glass 11.0 Ceiling Board installation at Kitchen and Preparation Areas
1.0 Painting works
2.0 Wood stain application 3.0 Painting of of Expo Bar railings 20 21-Aug 27-Aug 4.0 Installation of additional electrical outlets at Al Fresco 5.0 Lighting fixtures installation 6.0 Fire supression system installation 7.0 Testing of devices and equipment
1.0 Painting works
2.0 Wood stain application 21 28-Aug 2-Sep 3.0 Lighting fixtures installation 4.0 Testing of devices and equipment 5.0 Punchlisting ACTIVITIES