PROJECT : OLIVE GARDEN VERVE

LOCATION : VERVE 1 RESIDENCE, 26TH ST COR 7TH AVE., BGC, TAGUIG


SUBJECT : PROJECT CALENDAR SCHEDULE

WEEK NO. FROM TO ACTIVITIES


1.0 Construction of Alcove/Booth Seating
2.0 Topping Works at Waterproofed Flooring of Kitchen, GRI and Prep Areas.
3.0 Installation of framings of Arch Ceiling
4.0 Installation of plumbing pipes at Kitchen, Prep, Bar and Toilet Areas.
5.0 Installation of Weathered Fire Bricks at Column Claddings
13 3-Jul 9-Jul 6.0 Construction of Drywall column cladding at POS Area.
7.0 Dismantling of beam and counter at expo bar
8.0 Wall preparation at Beverage Area prior to installation of PVC corrugated p
9.0 Installation of electrical pipes and wirings
10.0 Mechanical Works
11.0 Installation of Firepro pipes.

1.0 Construction of Alcove/Booth Seating


2.0 Installation of framings of Arch Ceiling
3.0 Installation of Weathered Fire Bricks at Column Claddings
4.0 Installation of ceiling framings at POS Area.
5.0 Installation of wall tiles at toilet
14 10-Jul 16-Jul 6.0 Reconstruction of beam and counter at Expo Bar
7.0 Construction of Raised floor at Kitchen, GRI and Prep Area
8.0 Installation of electrical pipes and wirings
9.0 Mechanical Works
10.0 Plumbing pipes and waterlines installation

1.0 Construction of Alcove/Booth Seating


2.0 Installation of boards of Arch Ceiling
3.0 Installation of Floor tiles at Dining area
4.0 Construction of Raised floor at Kitchen, GRI and Prep Area
5.0 Wood Doors and PVC door installation
6.0 Installation of window and glass door frames
7.0 Painting works
15 17-Jul 23-Jul 8.0 Wood stain application
9.0 Installation of Floor tiles at Toilet Area
10.0 Installation of Chestnut PVC corrugated panel
11.0 Installation of toilet lavatory granite
12.0 Installation of Toilet wood wall accents
13.0 Mechanical Works
14.0 Installation of electrical pipes, wirings and devices
15.0 Fabrication of Expo Bar Railings
1.0 Installation of window and glass door frames
2.0 Painting works
3.0 Wood stain application
4.0 Installation of Floor tiles at Dining area
5.0 Fabrication of Expo Bar Railings
6.0 CCTV Works
16 24-Jul 30-Jul 7.0 Installation of electrical pipes, wirings and devices
8.0 Installation of wood accents and finishes
9.0 Installation of Bar counter granite
10.0 Installation of toilet lavatory granite
11.0 Smoke detecting system installation
12.0 Installation of Toilet wood wall accents

1.0 Painting works


2.0 Wood stain application
3.0 Installation of Floor tiles at Dining area
4.0 Installation of Expo Bar railings
5.0 CCTV Works
6.0 Smoke detecting system installation
17 31-Jul 6-Aug 7.0 Ceiling frames installation at Kitchen and Preparation Areas
8.0 Board installation at POS Area ceiling
9.0 Installation of window and glass door frames
10.0 Installation of wood accents and finishes
11.0 Installation of Bar counter granite
12.0 Installation of Stone tiles at Toilet walls
13.0 Installation of Floor and wall tiles

1.0 Painting works


2.0 Wood stain application
3.0 Installation of Floor tiles at Dining Area, GRI, Hallway, Kitchen And Preparati
4.0 Installation of wall tiles at Kitchen And Preparation Areas
5.0 Installation of Expo Bar railings
6.0 CCTV Works
18 7-Aug 13-Aug 7.0 Smoke detecting system installation
8.0 Plumbing fixtures installation
9.0 Installation of window and glass door framing and glass
10.0 Installation of wood accents and finishes
11.0 Installation of Office Cabinet
12.0 Ceiling board installation at Arch ceiling and POS Area

1.0 Painting works


2.0 Wood stain application
3.0 Installation of Floor tiles at Dining area
4.0 Installation of Expo Bar railings
5.0 CCTV Works
19 14-Aug 20-Aug
19 14-Aug 20-Aug 6.0 Fire supression system installation
7.0 Installation of additional electrical outlets at Al Fresco
8.0 Plumbing fixtures installation
9.0 Lighting fixtures installation
10.0 Installation of window glass
11.0 Ceiling Board installation at Kitchen and Preparation Areas

1.0 Painting works


2.0 Wood stain application
3.0 Painting of of Expo Bar railings
20 21-Aug 27-Aug 4.0 Installation of additional electrical outlets at Al Fresco
5.0 Lighting fixtures installation
6.0 Fire supression system installation
7.0 Testing of devices and equipment

1.0 Painting works


2.0 Wood stain application
21 28-Aug 2-Sep 3.0 Lighting fixtures installation
4.0 Testing of devices and equipment
5.0 Punchlisting
ACTIVITIES

chen, GRI and Prep Areas.

Bar and Toilet Areas.

allation of PVC corrugated panels.


ration Areas

llway, Kitchen And Preparation Areas