Professional Documents
Culture Documents
Operating Manual
C S S42 1
Operating Manual Revision 1
Table of content
Unit overview..................................................................................................................................................3
Specifications ................................................................................................................................................4
QHSE .................................................................................................................................................................5
Personnel safety............................................................................................................................................5
Environmental................................................................................................................................................5
Local regulations...........................................................................................................................................6
Maintenance ...................................................................................................................................................8
Placement.......................................................................................................................................................8
Lifting .............................................................................................................................................................8
Transportation ...............................................................................................................................................8
Inspection.......................................................................................................................................................9
Confidential 2-13
C S S42 1
Operating Manual Revision 1
Unit overview
The CSS421 is a 30m3 cement silo mounted on a skid. It is designed to store dry cement or other bulk solids as
a part of cement storage area of a bulk plant. It is also used to prepare dry cement mixes.
The cement silo is a vertical reservoir consisting of a tank and a skid. The tank is made of a shell, a cone, and
elliptical flat bottoms (Ø2400mm and Ø1200mm). A discharge line, an airpad, and the air supply are placed in
the dished bottom of Ø1200мм. A hatch for maintenance access is welded on the cone, as well, as load/vent
lines. Schlumberger ID tag is riveted on skid beam, accessible in both vertical and horizontal silo position.
Steel ladder with Tank
safety cage
Discharge, fill,
load lines
Skid
SLB ID tag
Figure 1:CSS421 horizontal position
Confidential 3-13
C S S42 1
Operating Manual Revision 1
Specifications
Confidential 4-13
C S S42 1
Operating Manual Revision 1
QHSE
Due to the many hazards in the oilfield industry, all Schlumberger employees must be familiar with the
appropriate safety regulations and precautions described in the Safety Standards for Well Services Operations,
content ID#4055049.
Anyone who feels an operation is unsafe has the right and duty to stop the operation.
When handling chemicals, ensure that you know the applicable contents of the material data safety sheets
(MSDS) regarding required personal protective equipment (PPE) and handling procedures. PPE is important,
but does not in itself prevent accidents; that is the responsibility of the individual—you.
You should also be familiar with the following:
Schlumberger QHSE Standard S002: QHSE Reporting, InTouch content ID# 3260257
Schlumberger QHSE Standard S003: Personal Protective Equipment (PPE), InTouch content
ID# 3260259
Schlumberger QHSE Standard S007: Management System Audit, InTouch content ID#
3260262
Well Services Safety Standard 4: Facilities and Workshops, InTouch content ID# 3313678
Well Services Safety Standard 18: Hazcom, InTouch content ID# 3313694
Well Services Safety Standard 25: Confined Space Entry, InTouch content ID# 3313705
Well Services Safety Standard 26: Air Tanks and receivers, InTouch content ID# 3313706
Well Services Safety Standard 27: Inspection and Testing of Pressure Relief Valves and
Gauges, InTouch content ID# 3313707
Personnel safety
Ensure that all relevant procedures and standards are followed at all times. Make certain that PPE is always
worn around the unit. All nonessential personnel should stay away from the unit during operation. If it is
necessary to climb up on the unit, exercise extreme caution.
Environmental
Any chemical spill must be contained, cleaned up, and reported according to local procedures. Dispose of spills
in an environmentally acceptable way and in accordance with local regulations.
Safety signs
Pay attention to the information on all decals, plates, and safety signs when around equipment.
Confidential 5-13
C S S42 1
Operating Manual Revision 1
Local regulations
Specific local laws to be followed:
Only persons having reached 18 years age, learned manual, passed trough job related safety training,
regulatory attestation and safety induction are allowed for servicing of silo. Periodicity and order of inspection
and examination of vessel is to comply with “Rules of design and safe operation of pressure vessels PB 03-
576-03”.
Confidential 6-13
C S S42 1
Operating Manual Revision 1
Air manifold
Maintenance
Placement
The silo is to be placed on open or covered area on a monolith reinforced concrete base designed by a
competent 3rd party.
The silo must be mounted in vertical position by an erector truck. Install ladder before mounting and
demounting operations. After the silo is installed, connect all nipples to operation lines. Valves should be
installed on silo’s inlets/outlets. To prevent ingress of cement dust to air line and compressor install check
valves on air line. Make sure that relief valve sealed after calibration with proper reference in valve and silo
passport, and that manometer installed on silo is stamped by certification officer with date of verification.
Lifting
QHSE standard #13 “Mechanical Lifting” must be followed during all lifting operations.
Horizontal silo lifting is to be performed with 4-point slings set of length at least 3000mm, and applicable load
16 tons as a minimum. Use shell mounted shackles to perform horizontal lifting operations.
Transportation
The silo can be transported without packing by following ways:
- motor transport;
- railway transport;
- water transport,
Local and SLB rules and standards of transportation, technical shipment and strapping for each type of
applicable transport must be followed.
Confidential 8-13
C S S42 1
Operating Manual Revision 1
Inspection
Daily:
- Visual inspection:
o Check shell and piping against leaks, cracks, splits and impacts.
o Look for hoses with loose clamps, clamps tightness.
o Check butterfly valves condition and performance.
- Fasteners, fittings tightness:
o Wing union’s connections to be tightened, if required.
o Impermeability of threaded connections to be checked with soap water.
- Painting:
o Corrosion and paint defects should be addressed in a proper way.
Annually:
- Airpad inspection. The silo must be emptied out and non-pressurized. Needle punched fabric to be
visually checked against burst and sanding/cementing to prevent low air flow rate. New needle punched fabric
to be installed if required.
Every 8 years:
- Hydraulic test must be done with pressure P=0.475 MPa, duration – 10 minutes. Vessel is to be
equipped with armature. Vessel must be stopped, emptied, hermetically plugged on all lines before hydraulic
test.
SLB must control periodicity of inspections, internal examinations, hydraulic tests and technical examinations.
NOTE: Periodical technical examination is to be provided by 3rd party specialist with proper attestation.
Confidential 9-13
C S S42 1
Operating Manual Revision 1
Confidential 10-13
C S S42 1
Operating Manual Revision 1
Confidential 11-13
C S S42 1
Operating Manual Revision 1
1. Location
Workshop area for low pressure tests.
2. Test equipment
- Pumping unit 6 bar;
- Pressure gauge (manometer) 0-6 bar;
- PRV set to 3.6 bar;
- Hose with Weco male 4” union Fig.206 on one end, connection to pump on other one;
- Ball valve G1½”, 6 bar;
- Fitting G1½” (threaded pipe);
- Three plugs with G2” thread, male;
- Plug with G1” thread, male.
3. Tank preparation
In preparation for the hydrostatic tests, the following procedure must be used:
3.1 Stop the compressor. Use Lock out/Tag out procedures on the air compressor during
the test.
3.2 Completely release all air pressure from the tank. Vent line must always be hard pipe
and placed in a direction away from any personnel in the area.
3.3 Disconnect all air and operation lines from the tank. Plug the dished head and the
discharge line jet with G2” plugs. Plug the vent and the fill lines with Weco female unions
Fig.206.
3.4 Inspect the outside surface of the tanks for corrosion or damage. Any minor damage
must be fixed. Tank replacement must be considered in case of senior damage.
3.5 Remove the safety manifold from the vent line. Plug the hole on vent line with G1”
plug.
3.6 Remove the square head plug from the top of tank and install G½” fitting with a ball
valve G1½”. It is important that this valve be placed so that all the air is removed. (Make
sure the working pressure rating of the valve is higher than the test pressure.)
3.7 Install the tank in vertical position.
3.8 Remove the pads (airpad belting assembly) from inside of tank. Ensure compliance
with “Confined space entry” standard during this procedure.
3.9 The tank can be tested at a test bay or wash bay. At the test location, install warning
signs marked: “WARNING - KEEP CLEAR. HIGH-PRESSURE TEST.”
3.10 The working pressure can be applied with a water pump. The pump assembly must
have a calibrated pressure gauge (manometer) that can show readings in units of 0.145
psi (0.01 bar). PRV for water must be installed on the pump discharge line and set to open
at 52.2 psi (3.6 bar).
Confidential 12-13
C S S42 1
Operating Manual Revision 1
3.11 If a hydraulic pump is not used (for example, air pump in the test bay), a regular PRV
must be installed on the discharge pump line and set to open at 52.2 psi (3.6 bar). Before
starting the test, this opening pressure must be checked by applying pressure to the valve.
4. Test procedure
It is recommended to follow this test procedure. Location can adopt these procedures, but must
make sure that the tank is tested correctly and safely.
4.1 Connect the test pump discharge to the tank discharge line with a hose with Weco
male union.
4.2 All other connections on the tank must be plugged except the pump discharge line and
the vent connection (on top of tank).
4.3 Open the vent valve and fill the tank with water on approximate 1/3 of volume.
4.4 Turn off the pump and close vent connection on top of the tank.
4.5 Check tightness, leaks on all connections, tighten as required.
4.6 Open the vent connection on top, fill the tank.
4.4 When the tank is full and the vent valve is open, pump additional water with the test
pump so that all the air is removed from the tank.
4.5 Close the vent valve and slowly increase the pressure in the tank to 51.5 psi (3.55 bar).
4.6 Stop the pump and hold pressure in the tank while you check for leaks.
4.7 After the tank holds pressure for 10 minutes, release the pressure and drain the tank.
The tank can be returned to service after drying and re-installation of airpad. Mark the test
information on the tank.
Confidential 13-13